Central Information Commission

Mrdavis George Thomas vs Ministry Of Environment & Forests on 23 October, 2015

                        CENTRAL INFORMATION COMMISSION
         (Room No.315, B­Wing, August Kranti Bhawan, Bhikaji Cama Place, New Delhi 110 066)

                    Prof. M. Sridhar Acharyulu (Madabhushi Sridhar)
                                     Information Commissioner

                                        CIC/SA/A/2015/000635
                                    (Video Conference - Bangalore)
                                                         
Davis George Thomas Vs. Ministry of Environment & Forest, Climate Change, GOI

                                     Important Dates and time taken:

      RTI/CPIO:19­11/6­2­15(79)         FA/FAO: 17­1/13­2­15(27)   2nd Appeal: 27­4­2015

      Disposed of with directions       Hearing:13­10­2015         Decision:23­10­2015 




Parties present: 


    The appellant is present for video conference at Bangalore.  The Public Authority is represented 

by Ms. Rita Khanna, Scientist­F and Mr. Y.P.Singh, Scientist­D. 


FACTS: 

2.   The appellant is seeking information regarding the details of the agencies/projects proposed to  be established at Amrit Mahal Kavals, Challakers Taluk, Chitradurga District, Karnataka. As no  information was received he approached the Commission in second appeal after exhausting the  first appeal. 

DECISION: 

CIC/SA/A/2015/000635                               Page 1
 3.         Both   the   parties   made   their   submissions.     The   respondent   officer   submitted   that   the 

information sought by the appellant is of strategic importance and hence cannot be disclosed as  per the exemptions provided under the RTI Act

4.     The   Environment   Support   Group   (ESG),   to   which   appellant   also   belonged,   has   filed  Applications No. 6/2013 and 12/2013 before the Hon'ble National Green Tribunal. In those cases,  the ESG raised a variety of grounds highlighting how project proponents had commenced work in  total   disregard   of   applicable   laws,   norms   and   clearance   procedures.     In   particular   it   was  highlighted   that   fundamental   provisions   of   the  Environment   Protection   Act,   1986  (and   Rules),  Environment Impact Assessment Notification, 2006, Water (Prevention and Control of Pollution)  Act, 1974Air (Prevention and Control of Pollution) Act, 1981Forest Conservation Act, 1980, etc.  had been flouted by the proponents, who started ground work without any clearances whatsoever.  The Petitioners also demonstrated that none of the projects had been grouped together flouting  risk   assessment   norms   (for   instance   an   uranium   enrichment   plant   is   proposed   next   to   a  weaponised drone testing facility) and without addressing basic land use planning, industrial and  hazardous  facilities   citing  norms.   In  addition,   the  locating  of   the   projects   were  in  violation  of  provisions of the Factories Act, 1948Karnataka Town and Country Planning Act, 1961, Aircraft  th Act, 1934 and the Constitutional 74  Amendment (Nagarpalika) Act, 1992.  

6.      The appellant stated that the NGT (Southern Zone, Chennai) in order dated 27th August 2014  in Application No.6/2013 and 12/2013 had given directions to the respondent Ministry to revisit the  exemptions given to the M/s Sagitaur Ventures India Pvt Ltd to commission solar power project.  Brief background of the case is as follows :

CIC/SA/A/2015/000635                                 Page 2
 Background of the NGT order

1. Chitradurga distict is in the agro­ecological sub­region of the Eastern Ghats and the Tamil  Nadu   Uplands   and   Deccan   Plateau.   It   is  a   hot   semi­arid   eco­region,   according   to   Indian  Council for Agricultural Research.

2. In Chellakere talug 52% of the area falls under semi critical and 47% under over exploited  category as per Central Ground Water Board. A total of 101 farmers have committed suicide  in the district between 2003­07 of which 45 suicides are reported to be due to crop failure.  Highest number suicides happened in the lowest rainfall year in the last decade. ... Major part  of the district is falling under over­exploited and critical category. The stage of groundwater  development in the district is more than 100% which requires immediate intervention by way  of conservation and artificial recharge to ground water in order to arrest the declining trend in  water level.  Clearly therefore, farming distress associated with water insecurity is a matter of  serious concern in the district. 

3. It is evident from these facts stated above that the Amrit Mahal Kavals of Challakere taluk  of Chitradurga district constitute a criticial component of the last few remaining flagship faunal  species   of   grasslands   ecosystem   in   India.   There   is   very   little   understanding   of   the   floral  diversity of such ecosystems (13th para of judgment) 

4. During   2008­10   the   Government   of   Karnataka   through   the   office   of   the  DeputyCommissioner of the Chitradurga District began to divert almost all the Amrit Mahal  Kavals   in   Challakere   Taluk   to   a   variety   of   urban,   industrial,   infrastructure   development,  research and defence related projects without consultation process of any kind. 

CIC/SA/A/2015/000635 Page 3

5. Appellant alleged that for seven projects 9273 acres of forest land was diverted for non­ forest purposes and allocated for various activities as per confirmed figures besides 10000  acres are being converted to station Indian Army, which is to be confirmed. 

6. Karnataka State Pollution Control Board issued a Notice on 12th April 2011 for starting the  projects without CFE and directed to start process of taking consent for establishment CFE  from   KSPCB   immediately.   Such   notices   were   issued   to   occupiers   such   as   ISRO,   Indian  Institute of Science IISC, Chitradurga, Bhabha Atomic Research Centre BARC, Aeronautical  Development Establishment ADE, M/s Sagitaur Ventures Pvt Ltd, Bangalore, etc. All such  notices were received by the seven respondents, certified copies of receipt were obtained  under RTI Act were submitted by the appellant. 

7. Such activities in Challakere Amrit Mahal Kavals are in violation of Section 2 of the Forest  Conservation  Act  1980,  according to  which  no state shall divert  forest land  for non­forest  purpose without prior approval of the Central Government.  Diversion of 9273 acres of forest  land here was without such permission.   Supreme Court in TN Godavarman Thirumalpad v  Union of India AIR 1997 SC 1228 specifically ordered to cease all on­going activity within any  forest in any State throughout the country without the approval of central government. 

8. The Planning Commission (Environment and Forest Division) constituted a Task Force on  Grasslands and Deserts for the Environment and Forests Sector for the Eleventh Five Year  Plan 2007­12 stated that the Grasslands are the common lands of the community and are the  responsibility of none. They should be protected. Some of recommendations of Task Force  CIC/SA/A/2015/000635 Page 4 are relevant for Amrit Mahal Kaval. The report recommended modification of the new EIA  guidelines to make it mandatory to have EIA for preservation of forest containing wild life and  flora and founa like grasslands of Amrit Mahal Kaval, and give high priority to protecting semi 

-arid regions and increase grasslands and desert ecosystems. 

9. The NGT in para 26 mentioned that it was clear that Karnataka state has diverted almost  all of the Amrit Mahal Kavals of Challakere Taluk to non­forest and non­pastoral purposes  without application of mind. The proposed investments will directly and irreversibly affect the  impacted   communities   and   biodiversity   of   the   area   especially   the   pastoral   communities,  whose  livelihoods are  intricately linked to the  existence  of  these  grasslands.  The  projects  have commenced in blatant violation of all the applicable rule, norms, standards and statutes  as   evident   from   the   fact   that   the   Amrit   Mahal   Kavals   have   been   blocked   off   to   pastoral  communities by building 28 km long wall that fundamentally attacks their very right to live. So  serious has been the impact on pastoral communities from this one act, that already several  families have run into huge debts trying to find fodder for their cattle, several more are forced  to   sell   their   livestock   to   survive   and   there   is   widespread   pain   and   agony   suffered   as   a  consequence of these illegal activities by the impacted communities. 

10. Hon'ble High Court of Karnataka in writ petition 17954/1997 directed to protect  these lands and no portion of that land in any way be diverted or illegally encroached upon.  This was not appealed and thus became final and binding. Karnataka state law department  rightly   opined   that   this   order   binds   the   state   including   all   its   departments.   High   Court  confirmed this aspect and thus the Amrit Mahal Kavals Gomala lands need to be protected. 

CIC/SA/A/2015/000635 Page 5

11. During Vijaya nagar empire these grasslands spread over 4.15 lakh acres across  Karnataka were meticulously protected and trespassers were prosecuted. 

12. Almost   all   respondents   contended   that   Amrit   Mahal   Kavals   lands   are   not  designated forestlands, no wall of 28 km long was constructed, and no rule is flouted. 

13. Though   the   relief   is   barred   by  limitation,   however,   there   is   no   impediment   on  considering the issues of environmental degradation. (Para 154) 

14. The   NGT   concluded   that   the   above   referred   lands   are   not   forest   lands.  (Paragraphs 164 ­174) Specific directions of NGT

15.   The NGT observed: Grasslands have to be protected as a wild life habitat. ....It becomes  imperative to recognize the ecological, hydrological, economic and sociological role of grasslands  as   source   of   survival   for   millions   of   livestock   and   rural   people.....   Bustard   species   can   be  considered   as   indicators   of   grassland   ecosystem   and   by   conserving   the   bustards   and   their  habitats,   a   large   number   of  species   that   are   dependent   on   the   healthy   grasslands   can   be  protected. Keeping in view that these magnificent birds are now on the verge of extinction, there is  an urgent need to launch Project Bustards and immediately provide all the necessary steps to  ensure their survival. (Paragraph 181) CIC/SA/A/2015/000635 Page 6

16. ...It becomes necessary to issue directions to the Government of Karnataka to preserve  and maintain the remaining area of Amrit Mahal Kaval lands in Chitradurga  district without any  diversion, thereby enabling the villagers around the Kaval lands to use the same as they have  been used by them in the past. (Paragraph 199) 

17. In   view   of   fact   that   Amrit   Mahal   Kavals   lands   are   shrinking   and   only   a   small   extent  remains,   the   Government   of   Karnataka   is  directed   to   firm   up   and   finalize   action   plan   for  the  protection and conservation of the said endangered species and initiate time bound execution of  the plan forthwith. In this exercise, the Government of Karnataka is also directed to ensure proper  and timely coordination amongst concerned departments and agencies to achieve the planned  objectives. (Paragraph 203) 

18. Regarding   the   approvals   to   be   obtained   by   the   respondents   in   response   to   KSPCB  notifications, the NGT held that the answer by these respondents will not satisfy the law. The law  mandates   that   without   obtaining   the   prior   environmental   clearances   and   prior   consent   for  establishment   the   project   proponents   should   not   commence   any   activity   connected   to   and  concerned with the establishment of the project. ..it is made clear that both BARC and ISRO shall  proceed   with   the   activities   either   constructional   or   otherwise   on   establishment   of   respective  projects only after obtaining environmental clearance from MoEF and consent for establishment  from KSPCB.  Paragraph 205.

19. DRDO need not take clearance from MoEF CIC/SA/A/2015/000635 Page 7

20. Karnataka Government is restrained from making any further allotment in Amrit Mahal  Kaval lands in Chitradurga district to any one on any reason or for any purpose.  Para 212

21. Paragraph   214:   Both   MoEF   and   KSPCB   are   directed   to   strictly   comply   with   the  observations and also the directions given to them at the time of grant of Environmental clearance  and or Consent for Establishment as the case maybe. 

22. Para 215. In addition to directions given under different heads at appropriate sections  of the judgment, we give the following "Specific" directions to the MoEF, KSPCB and the Allottee  Project Proponents: 

1. At the time of granting EC or CFE to the Project Proponents who have been allotted  sites in the land in question, the MoEF and/or KSPCB as the case may be, are directed to  take   strict   note   of   the   observations   and   comments   made   in   this   judgment   regarding  several environmental issues and concerns raised by the applicants and include verifiable  and measurable "conditions" regarding the same to be complied in full, at all stages, by  the project proponents. 
2. Citing an Office Memorandum issued by the MoEF, M/s. Sagitaur Ventures India Pvt. 

Limited, the 14th Respondent in Application no. 6 of 2013, claims that it need not obtain  EC   from   the   MoEF.   We   are   of   the   considered   view   that   the   Solar   thermal   power  technology is still at its infancy. Its impacts on environment are being investigated in many  research institutes across the globe and newer and newer information on this aspect in  emerging. In fact, the applicant placed before the tribunal a few of the recent literature on  this aspect and took us through the significant findings in this regard. Keeping these and  the  averments  made  by the   applicant  on  the   subject   in   mind   and  also  guided  by the  CIC/SA/A/2015/000635 Page 8 "Precautionary Principle"­ one of the legs of the concept of "Sustainable Development",  we direct the MoEF to revisit the exemption order with regard to EC given to M/s. Sagitaur  Ventures   India   Pvt.   Limited   and   pass   suitable   orders   in   the   light   of   recent   research  findings and other relevant materials available. 

3. We direct the KSPCB to issue the Consent to Establish to M/s. Sagitaur Ventures India  Pvt. Limited only after satisfying itself with the compliance of all items listed in the Office  Memorandum No. J­11013/41/2006­IA.II (1) dated 30th June, 2011 issued by the MoEF. 

4. The KSSIDC and the IISc are directed to permit the villagers to offer pooja, celebrate  festivals and conduct traditional rituals on concerned days at the temples located in the  sites allotted to them in the land under question, during and even after their establishment  and subsequent operation. 

5. The BARC is directed to shift the temporary fence abutting the mud road near the  south western corner of their land suitably and open up a passage to the villagers to  enable them to reach their respective agricultural lands and also Kaluvehalli village. 

6. The BARC and IISc are directed to evolve and implement a joint action to plan to  enable   free   movement   of   villagers   from   Khudapura   to   Old   Sheep   farm   through   their  respective premises. 

7.  The  ISRO  is directed to provide  water to the  villagers  of  Ullarti village  through the  borewells   located   in   the   site   allotted   to   them,   on   a   continuous   basis   i.e.,   during   the  establishment and operating phases of the organization.

23. The   above   directions   of   the   NGT   are   well   balanced   and   did   not   impose   any   undue  restraints   on   developmental   activities   initiated   by   these   public   authorities   in   true   spirit   of  sustainable development principles. These directions are also significant as the villagers had right  to water, right to way, right to livelihood and to culture in rest of the lands left after allocations of  land  made.  The  NGT has rightly  prohibited  and restricted  the Government  of  Karnataka from  further allocation of lands in Amrit Mahal Kavals grasslands area. The Government of Karnataka  CIC/SA/A/2015/000635 Page 9 has a responsibility to honour the right of people to way, water, culture and livelihood in these  lands.

24. The appellant sought information about action taken to implement the directions of the  NGT as mentioned above. Hence the Commission directs the public authorities to provide the  following information to the appellant within one month from the date of this order. 

a) The MoEF to provide comprehensive information as to implementation of the directions of the  NGT  in paragraph  181  stating:  Bustard  species can be considered  as  indicators  of  grassland  ecosystem and by conserving the bustards and their habitats, a large number of species that are  dependent on the healthy grasslands can be protected. Keeping in view that these magnificent  birds are now on the verge of extinction, there is an urgent need to launch Project Bustards and  immediately provide all the necessary steps to ensure their survival. Whether MoEF has launched  project Bustard? If so details of the same and if not the reasons for the same shall be explained in  a note to the applicants and same shall be placed on official website. 
b) The Government of Karnataka to explain what measures it has taken to implement the orders of  NGT  in paragraph  199 referred  above to preserve and  maintain the  remaining  lands  of  Amrit  Mahal Kaval and whether it has refrained from allotment of further lands in Amrit Mahal Kaval,  whether any orders prohibiting allotment was issued, if so the copy of the same, if not, reasons. 
c) The Government of Karnataka to explain whether the direction of NGT "to firm up and finalize  action plan for the protection and conservation of the said endangered species and initiate time  bound   execution   of   the   plan   forthwith.   In   this  exercise,   the   Government   of   Karnataka   is   also  directed to ensure proper and timely coordination amongst concerned departments and agencies  to achieve the planned objectives", is implemented, whether action plan is firmed up and finalized,  if so details with concerned documents and if not why, the reasons shall be explained.
CIC/SA/A/2015/000635 Page 10
d) In view of direction: 'Karnataka Government is restrained from making any further allotment in  Amrit Mahal Kaval lands in Chitradurga district to any one on any reason or for any purpose. 

Para 212", the Government of Karnataka to inform how they are implementing this direction.

e) In view of the observation "... it is made clear that both BARC and ISRO shall proceed with the  activities   either   constructional   or   otherwise   on   establishment   of   respective   projects   only   after  obtaining   environmental   clearance   from   MoEF   and   consent   for   establishment   from   KSPCB  (Paragraph 205)", whether BARC and ISRO obtained necessary clearances and consent? The  BARC   and   ISRO   are   directed   to   provide   information   along   with   the   necessary   copies   of  documents. 

f) The MoEF is directed inform whether BARC and ISRO obtained the above referred clearances  and consent.

g) In view of the direction of NGT: "Both MoEF and KSPCB are directed to strictly comply with the  observations and also the directions given to them at the time of grant of Environmental clearance  and or Consent for Establishment as the case maybe", the MoEf and KSPCB to inform what  measures they have taken to implement this direction? Any specific notification issued, if yes, the  copy of the same, if not the reasons.

h) The MoEF and KSPCB to inform how they are implementing direction of NGT in  paragraph 215  point 1. 

CIC/SA/A/2015/000635 Page 11

i) Whether MoEF revisited the exemption deemed to have been given to M/s Sagitaur Ventures  India Pvt Ltd and passed suitable orders as per Point 1 in Paragraph 215.

j) The KSPCB and MoEF to inform whether it has complied with the order of NGT under Point 3 of  Para 215, whether M/s Sagitaur Ventures complied with OM 2006 dated 30 th June 2011 issued by  MoEF.

k) The KSSIDC and IISc to inform whether they are permitting the villagers to offer pooja, celebrate  festivals and conduct traditional rituals on concerned days at the temples located in the sites  allotted to them during and even after their establishment and subsequent operation, how are  they doing it,  have  they notified  the same in  Kannada  language  and  the language which  the  people of locality understand, is there any oral notification? KSSCIDC and IISC to provide proof of  the participation of the people in above referred activities regularly. 

l) The BARC to inform whether they shifted the temporary fence and opened up a passage to the  villagers as directed by NGT in point 5 paragraph 215, provide the proof of the same.

m) The  BARC and  IISc  are  to  inform  whether  they  have  evolved  joint   action   plan  and  how  they  implemented that to enable free movement of villagers from Khudapura toOld Sheep farm through  their respective premises. 

CIC/SA/A/2015/000635 Page 12

n) The ISRO to inform whether they are providing water to the villagers of Ullarti village through the  borewells located in the site allotted to them, on a continuous basis. Commission directs them to  facilitate   inspection   to   appellants,   who   in   turn   are   directed   to   report   their   findings   to   the  Commission in a month. 

7. The   Commission   finds   it   is   absolutely   irrelevant   and   non­applicable   the   claim   of   the  respondent authority that information sought is barred from disclosure under Section 8(1)

(a) stating that it would impact the strategic security installations of the nation. They have  not shown any evidence or convincing reason to show how disclosure of this information  about implementation of NGT order affects security interests of the nation. It is ridiculous  that MoEF did not understand the implication of their claim of this exemption. How can  informing   about   implementation   of   environmental   protection   order   of   NGT   affect   the  security of the country? The orders of NGT are so clear and specific that they pertain to  various  rights  of  the people.  It  is  surprising  that  well  educated CPIOs  who  are senior  Scientists in Environmental sciences have taken this stand without applying their minds to  the   rights   of   the   people   and   environmental   degradation.   The   Commission   records   its  displeasure. 

8. In   view   of   the   observations   in   above   paragraph,   the   Commission   observers   that   the  information   sought   was   unduly   delayed   by   the   MoEF   raising   irrelevant   grounds,   the  Commission, in exercise of its powers under Section 19(8)(b)  directs the MoEF to pay Rs  10,000 as compensation to the appellant and recommend not to claim serious exemptions  without any seriousness, just to block the information sought as they did in this case and  train their CPIOs properly to prevent such inordinate delay in disclosure like this.  With this  observation, the present appeal is disposed of.

CIC/SA/A/2015/000635                                   Page 13
                                                                      (M. Sridhar Acharyulu)
                                                                 Information Commissioner
Authenticated true copy




(U.C.Joshi)
Deputy Secretary




Address of the parties :

   1. The CPIO under the RTI Act, Govt. of India
         Ministry of Environment and Foresits & Climate change
         Indira Parvaran Bhavan, Jor Bagh Road  (RTI Cell)
         Lodi Road PO, New Delhi­110003




   2. Shri Davis George Thomas

           3354, K.R.Road, 

           Bangalore­560070



   3. The Project Director,
         Bhabha Atomic Research centre 
         Post Box No. 1, Yelwal 
         Mysore - 571130


   4. Group Head, Construction and Maintenance 
         ISRO Satellite Centre 
         Department of Space Government of India 
         PO Box No. 1795, Airport road, 
         Vimanapura 

CIC/SA/A/2015/000635                     Page 14
          Post Bangalore - 560 017


  5. The Chairman 

Karnataka Small Scale Industries Development Corporation Ltd.  Industrial Estate, Rajaji Nagar West off Chord Road  Bangalore - 560 010

6. Chairman  Karnataka State Pollution Control Board  Parisara Bhavan Church Street  Bangalore ­560001 CIC/SA/A/2015/000635 Page 15