Legal Document View

Unlock Advanced Research with PRISMAI

- Know your Kanoon - Doc Gen Hub - Counter Argument - Case Predict AI - Talk with IK Doc - ...
Upgrade to Premium
[Cites 13, Cited by 0]

Jharkhand High Court

Steel Authority Of India Limited ... vs The Union Of India Through The Secretary ... on 28 April, 2017

Author: Aparesh Kumar Singh

Bench: Aparesh Kumar Singh

                                                 W. P. (C) No. 5695 of 2016

                                                  ­­­­
                 An application under Article 226 of the Constitution of India
                                     --

Steel Authority of India Limited ......Petitioner

-Versus-

The Union of India & others ......Respondents

--

For the Petitioner : M/s. M. S. Ganesh, Sr. Adv.

Indrajit Sinha, Bibhash Sinha & Vipul Poddar,Advs.

          For the U.O.I                  : Mr. Rajiv Sinha, ASGI
          For the State                  : J. C to A.G
                                      --
                                       PRESENT
                    HON'BLE MR. JUSTICE APARESH KUMAR SINGH
By Court                      Petitioner   approached   this   Court   in   the   present   matter   being 

aggrieved   by   Circular   letter   bearing   no.   F.No.11­599/2014­FC  dated 1st April, 2015 (Annexure­1) and in particular paragraph 3(v) (a) & 

(b)   issued   by   Respondent­Union   of   India,   Ministry   of   Environment,  Forest and Climate Change. Petitioner has questioned the competence of  respondent to issue such a direction as being ultra vires Section 2(iii) of  the Forest (Conservation)  Act, 1980 and Articles 14, 73(1)(a ), 141 and 144  of the Constitution of India.   It is also contended that petitioner cannot  be made liable to pay Net Present Value (NPV) of the entire forest land  comprising its leasehold area.  

Petitioner is a Company and a Public Sector Undertaking being the  largest   producer   of   Iron   and   Steel   in   India.   It   owns   and   operates   five  integrated   Steel   Plants   (i)   Bhilai   Steel   Plant   at   Bhilai,   Chattisgargh   (ii)  Durgapur Steel Plant at Durgapur, West Bengal (iii) Rourkela Steel Plant  at Rourkela, Odisha (iv) Bokaro Steel Plant, Bokaro, Jharkhand and (v)  IISCO Steel Plant at Burnpur, West Bengal. 

Subject matter of the writ petition  is demands of NPV relating to  following leases held by the petitioner.

(i) Kiriburu­Meghahatuburu lease­II for an area of 879.439 Ha.

(ii) Kiriburu­Meghahatuburu lease­III for an area of 82.00 Ha. for  captive mining. 

(iii) Gua, Duarguiburu of an area of 1443.756 Ha. All three leases concern mentioned above are extant.  2. When   the   matter   was   taken   up   on   29th   September,   2016,   after  consideration   of   the   submission   of   learned   Senior   Counsel   for   the  petitioner and Respondent­Union of India, State as well,  the following  order was passed: 

" Learned   Senior   counsel   for   the   petitioner   in   support   of   the  challenge to the conditions incorporated in the Letter F. No. 11599/   2014 - FC, dated 1st April, 2015, issued by the Director, Ministry of   Environment,   Forest   and   Climate   Change   (Forest   Conservation   Division), Government of India, submits that 
(i) the condition to realise Net Present Value ('NPV' in   short)   of   the   entire   forest   land   falling   in   the   mining  lease is not in consonance with the specific provisions of   Section 2(ii) of the Forest Conservation Act, 1980 itself. 
(ii)   such   a   general   direction   in   the   nature   of   an  executive instruction overreaching the provisions of the  Parent Act is untenable in law. 
(iii) the petitioner has paid NPV for the diverted portion   of the forest land falling in the mining lease as per the   forest clearance granted to it, as is also evident from the   letter dated 14.12.2015, issued by the Divisional Forest  Officer,   Saranda   Forest   Division,   Chaibasa   (Annexure2). 

On   instructions   it   is   further   submitted   that   there   are   no  proposal   for   diversion   of   remaining   area   of   the   leasehold   land   falling within the forest land. In such circumstances the directions   contained in the impugned letter dated 01.04.2015 upon the State   Government to realise from the user agency such as the petitioner   NPV of the entire forest land in a mining lease within a period of   one year from the date of issue of the letter is wholly untenable in  law and on facts. This is also in teeth of the Judgment rendered by   the Apex Court in the case of T.N. Godavarman Thirumulpad (104)   Vs. Union of India and others reported in (2008) 7 SCC 126. 

As   a   consequence   of   the   general   directions   issued   under  the   impugned letter, the State Government has been authorised in an   illegal   manner   to   keep   approval   of   the   mining   lease   itself   in   abeyance and stop such activities in the mining lease till such time   NPV of such forest land is realised. The petitioner herein, therefore,   has been compelled to move this Court in the present writ petition as   the   respondents   may   take   coercive   steps   against   it   to   enforce   aforesaid conditions as is evident from the letter dated 16.09.2016   (Annexure­3) issued by the Divisional Forest Officer, Saranda Forest   Division, Chaibasa (Respondent No. 4). 

Learned ASGI Shri Rajiv Sinha appearing for the respondent  nos. 1 and 2 and learned JC to AG appearing for the respondent nos.   3   and   4   both   pray   for   time   to   seek   instructions   and   file   counter   affidavit in the matter. 

Accordingly, as prayed for, four weeks' time is allowed. List this   case again on 27.10.2016. 

In   the   mean   time,   no   coercive   steps   be   taken   against   the   petitioner   pursuant   to   the   impugned   letter   dated   16.09.2016  (Annexure­3)."

The Respondent­Union of India as well as the State of Jharkhand  have filed their respective counter affidavits.  

Today when the matter was taken up for hearing, learned Senior  Counsel for the petitioner has inter alia made the following submissions:­ 

(i) In terms of constitutional provisions such as Articles 265 and  366(28),  the impugned levy does not fit into the Jural character of a tax or  even fee though it is in the nature of compulsory exaction.  3.

(ii)   Hon'ble   Supreme   Court   in   the   case   of  T.N.Godavarman  Thirumulpad Vs. Union of India  and others reported in  (2006)1 SCC 1  has clearly opined that such a levy would be in the nature of fee falling  within Entries 20 read with 47 of List­III under Seventh Schedule to the  Constitution   of   India.     Hon'ble   Supreme   Court   while   constituting   the  CAMPA  Fund and the authorities to administer it had a pious hope  that  the   Legislature   would   step   in   and   enact   a   legislation   to   levy   such   an  impost or fee.  Ten years hence no such legislation has come.  

(iii) The executive cannot, in the absence of a legislative sanction,  impose a compulsory exaction in the nature of a tax or fee as has been  done.

(iv) The very character of NPV as a compensatory levy for diversion  of forest land also becomes questionable now in the light of Constitution  Bench   Judgment   rendered   by   Hon'ble   Supreme   Court   in   the   case   of  Jindal Stainless Ltd. Vs. State of Haryana reported in (2016) 11 Scale 1. 

(v) The Respondent­Union of India cannot justify the levy even on  the  basis of the directions contained by Hon'ble  Suprme  Court in the  case of  T.N.Godavarman Thirumulpad Vs. Union of India and others   reported in (2006) 1 SCC 1 (Supra).   The impugned action is not even  authorized in terms of  Article 77 of the Constitution of India.  The matter  is of wide public importance and has larger significance. 

Learned ASGI has defended the impugned decision.  He also relies  upon   the   order   passed   by   Hon'ble   Supreme   Court   in   the   case  T.NGodavarman   Thirumulpad   Vs.   Union   of   India   (2006)   1   SCC   and   (2008) 7 SCC 126.  It is also submitted that reason for the petitioner to be  aggrieved   herein   is   liability   to   pay   NPV   for   the   entire   portion   of   the  leasehold area comprising forest land though NPV has been duly paid  and not questioned  earlier for  diverted portion of the forest land.   He  however also submits that the issue involved has larger repercussion and  is of wide public importance.  

4.

Having regard to the nature of the issues involved, this Court is of  the opinion that the matter is required to be heard by learned Division  Bench of this Court.  Accordingly, let the matter be placed before learned  Division Bench at an early date. 

Interim order dated 29.09,2016 shall continue till the next date. 

       

 

                                                              (Aparesh Kumar Singh,J) Jharkhand High Court, Ranchi The 28th April, 2017 jk/NAFR