State of Himachal Pradesh - Section

Section 14 in Himachal Pradesh Electricity Regulatory Commission (Terms and Conditions for Determination of Hydro Generation Tariff) Regulations, 2011

14. Renovation and Modernisation.

(1)The generating company for meeting the expenditure on renovation and modernization for the purpose of extension of life beyond the useful life of the generating station or a unit thereof shall make an application before the Commission for approval of the proposal with a Detailed Project Report giving complete scope, justification, cost-benefit analysis, estimated life extension from a reference date, financial package, phasing of expenditure, schedule of completion, reference price level, estimated completion cost including foreign exchange component, if any, record of consultation with beneficiaries and any other information considered to be relevant by the generating company.
(2)Where the generating company makes an application for approval of its proposal for renovation and modernisation, the approval shall be granted after due consideration of reasonableness of the cost estimates, financing plan, schedule of completion, interest during construction, use of efficient technology, cost-benefit analysis, and such other factors as may be considered relevant by the Commission.
(3)Any expenditure incurred or projected to be incurred and admitted by the Commission after prudence check based on the estimates of renovation and modernisation expenditure and life extension, and after deducting the accumulated depreciation already recovered from the original project cost, shall form the basis for determination of tariff.