[Cites 0, Cited by 0]
[Entire Act]
State of Maharashtra - Section
Section 35 in The Maharashtra Electricity Regulatory Commission (Terms and Conditions of Tariff) Regulations, 2005
35. Energy charges.
- 35.1 Thermal generating stations(a)Energy charges shall cover fuel costs and shall be worked out on the basis of ex-bus energy sent out corresponding to scheduled generation as per the following formula:Energy Charges (Rs) = Rate of Energy Charges in Rs/kWh X Ex-bus energy sent out corresponding to scheduled generation for the month in kWhWhere,Rate of Energy Charges (REC) shall be the sum of the cost of normative quantities of primary and secondary fuel for one-kWh of ex-bus energy sent out corresponding to scheduled generation and shall be computed as under:| REC =| 100 {Ppx (Qp)n+ Psx (Qs)n }(100-(AUXn))| (Rs/K Wh) |