[Cites 0, Cited by 0] [Section 3] [Entire Act]

State of Jharkhand - Subsection

Section 3(3) in Jharkhand State Electricity Regulatory Commission (Electricity Supply Code) Regulations 2005

3.2Cost of Service Connection/Extension/Upgradation. - 3.2.1 The licensee shall be authorized to recover from the applicant all expenses reasonably incurred in laying service line from the distribution mains to the point of supply based on the schedule of charges approved by the Commission as per Clause 17 of these Regulations.
3.2.2Where the provision of supply to an applicant requires works of installation of dedicated distribution facilities, the licensee shall be authorized to recover all expenses reasonably incurred on such works from the applicant based on the schedule of charges approved by the commission as per Clause 17 of these Regulations.
Where the provisions of supply to an applicant entails works, not being works referred to in Clause 3.2.1 and 3.2.2 above of these Regulations, for augmentation/up gradation of the distribution system, the licensee shall be authorized to recover from the applicant such portion of the expenses reasonably incurred on such works as the load or additional load applied for bears to the incremental capacity that will be created by augmentation of the distribution system as per the schedule of charges approved by the Commission in accordance with Clause 17 of these Regulations.Provided that where the load or additional load applied for by the applicant does not exceed one third of the capacity that will be created by augmentation of the distribution system, the licensee shall not be entitled to recover any expenses under this Clause 3.2.3 of these Regulations form such applicant.
3.2.3Where the licensee permits the applicant to carry out works of laying service line and/or dedicated distribution facilities for the power supply requisitioned by him, the licensee shall not be entitled to recover expenses relating to such portion of work so carried out by the applicant.
Provided how ever that the licensee shall be entitled to recover from the applicant, supervision charges as per schedule of charges approved by the Commission in accordance with Clause 17 of these Regulations, not exceeding 15 percent of the labor cost that would have been incurred by licensee in carrying out such work.Provided further that the applicant shall have to get the works carried out by licensed electrical contactor as per the estimate and lay-out approved by the licensee. The material purchased by the applicant in such cases should conform to relevant BIS specification or its equivalent and should bear its mark where applicable. The licensee may ask for documentary evidence to verify the quality of material. The consumer should get the work done within time frame provided in these Regulations failing which the licensee may on giving fifteen days notice treat this application for supply as cancelled.
3.2.4The service line and /or the dedicated distribution facility, not withstanding that it has been paid for by the consumer, shall remain the property of the licensee who shall maintain it and who shall have the right to use the same for supply of electricity to any other person provide that such supply should not adversely affect the supply to the consumer who has paid for it.