[Cites 0, Cited by 0] [Section 18] [Entire Act]

State of Bihar - Subsection

Section 18(3) in Bihar Electricity Regulatory Commission (Standards of Performance of Distribution Licensee) Regulations, 2006

(3)On receipt of payment from the consumer the Licensee shall complete the work within the following time periods.
(a) Shifting of meter/service wire 15 days
(b) Shifting of pole, LT or HT Line 60 days
(c) Shifting of underground Cable 45 days
(d) Shifting of Distribution Transformer alongwith thestructure 90 days