Section 10(10)(e) in The Maharashtra Electricity Regulatory Commission (Distribution Open Access) Regulations, 2014
(e)The bank guarantee may be encashed by the Distribution Licensee, if the application is withdrawn by the applicant or the Long-term Open Access rights are relinquished prior to the operationalisation of such rights when augmentation of distribution system is not required.