State of Maharashtra - Act
The Maharashtra Electricity Regulatory Commission (Distribution Open Access) Regulations, 2014
MAHARASHTRA
India
India
The Maharashtra Electricity Regulatory Commission (Distribution Open Access) Regulations, 2014
Rule THE-MAHARASHTRA-ELECTRICITY-REGULATORY-COMMISSION-DISTRIBUTION-OPEN-ACCESS-REGULATIONS-2014 of 2014
- Published on 1 January 2014
- Commenced on 1 January 2014
- [This is the version of this document from 1 January 2014.]
- [Note: The original publication document is not available and this content could not be verified.]
Part A – Preliminary
1. Short Title, extent and commencement.
- 1.1. These Regulations may be called the Maharashtra Electricity Regulatory Commission (Distribution Open Access) Regulations, 2014.2. Definitions.
- 2.1 In these Regulations unless the context otherwise requires:(a)"Act" means the Electricity Act, 2003 (36 of 2003);(b)"Admissible Drawal" or "Allotted Capacity" means the power transfer in MW between the specified point(s) of injection and point(s) of drawal allowed to a consumer on the Distribution system;(c)"Applicant" means such person who has made an application for Grant of connectivity and/or Open Access to the distribution system of a Distribution Licensee in accordance with these Regulations;(d)"Authorised Representative" means all such officers, staff or representatives of the Distribution Licensee or the Supplier, discharging functions under the general or specific authority of the Distribution Licensee or the Supplier, as the case may be;(e)"Balancing and Settlement Code" means such code as may be developed by the State Load Despatch Centre and approved by the Commission for the balancing of energy accounts and settlement of differences between energy scheduled and actual energy delivered among the users of the grid in the State of Maharashtra;(f)"Bilateral transaction" means a transaction for exchange of energy (MWh) between a specified buyer and a specified seller, directly or through a Trading Licensee or discovered at Power Exchange, from a specified point of drawal for a fixed or varying quantum of power (MW) for any time period.(g)"Billing Demand for Partial Open Access Consumer" means monthly Billing Demand shall be higher of following:(i)Actual Maximum Demand recorded less Open Access Demand availed by Partial Open Access Consumer in the month during 0600 to 2200 Hours;(ii)75% of the highest Billing Demand pertaining to retained Contract Demand recorded during preceding eleven (11) months;(iii)50% of retained Contract Demand with the Licensee.(h)"Central Commission" means the Central Electricity Regulatory Commission referred to in Section 76 of the Act;(i)"Commission" means the Maharashtra Electricity Regulatory Commission;(j)"Congestion" means a situation where the demand for distribution capacity exceeds the Available Transfer Capability;(k)"Connection" means the connecting the premises of the Consumer with the distribution system of the Distribution Licensee so as to enable the transfer of electricity between such premises and such distribution system;(l)"Connection and Use of Distribution System Agreement" means an agreement for connection to and use of the distribution system of a Distribution Licensee and are of the following types -(i)an agreement entered into between the Distribution Licensee and a person whose premises are situated within the area of supply of the said Distribution Licensee where such person requires supply of electricity from a Generating Company or Licensee other from the said Distribution Licensee;(ii)an agreement entered into between the Distribution Licensee and a Generating Company or Licensee, as the case may be, intending to give supply of electricity to such person referred to in (i) above by using the distribution system of such Distribution Licensee for wheeling of electricity;(iii)an agreement entered into between the Distribution Licensee and a person whose premises are situated within the area of supply of the said Distribution Licensee where such a person requires supply of electricity from a Power exchange formed under the CERC (Power Market) Regulation, 2010 as amended from time to time either through a Member or by becoming a Member himself;in accordance with these Regulations and subject to the terms and conditions contained therein;(m)"Connectivity" for a generating station, including a captive generating plant, a consumer or a Licensee means the state of getting connected to the distribution system;(n)"Consumer" shall carry the same meaning as in the Act, but shall be restricted to such consumers within the State of Maharashtra to whom these Regulations will apply and have been granted Open Access in accordance with these Regulations;(o)"Consumer Grievance Redressal Forum" means such forum for redressal of Grievances as is set up by the Distribution Licensee under the provisions of sub-section (5) of Section 42 of the Act and the Regulations specified there under;(p)"Contract Demand" means demand in kilowatt (kW) or megawatt (MW) or horse power (HP) or kilovolt ampere (KVA) or megavolt ampere (MVA), mutually agreed between the distribution licensee and the consumer as entered into:(i)in the agreement for supply of electricity; or(ii)in the Connection and Use of Distribution System Agreement; or(iii)as agreed through other written communication;Provided that unity power factor shall be considered for the purpose of unit conversion from MVA/kVA to MW/kW,.(q)"Day" means the day starting at 00.00 hours and ending at 24.00 hours;(r)"Detail procedure" means the procedure issued by the Distribution Licensee as referred to in Regulation 8, 9, 10, 11, 12, 36 hereof;(s)"Electricity Supply Code" means the Regulations specified by the Commission under clause (u), clause (v), clause (w), clause (x) and clause (zp) of sub-section (2) of Section 181 of the Act;(t)"IEGC" means Indian Electricity Grid Code specified by Central Electricity Regulatory Commission under clause (h) of sub-section (1) of section 79 of the Act, and as amended from time to time;(u)"Long-term Open Access" means the right to use the Distribution system for a period exceeding twelve (12) years but not exceeding twenty-five (25) years;(v)"Maximum Demand" in kilowatts or kilo-volt-amperes, in relation to any period shall, unless otherwise provided in any general or special Order of the Commission, mean two times the largest number of kilowatt-hours or kilo-volt ampere-hours supplied and taken during any consecutive fifteen (15) minute blocks in that period;(w)"Medium-term Open Access" means the right to use the Distribution system for a period exceeding three (3) months but not exceeding three (3) years;(x)"Month" means a calendar month as per the Gregorian calendar;(y)"Nodal agency" means the nodal agency as defined in Regulation 3 of these Regulations(z)"Open Access Customer" means a consumer, Licensee or a Generating Company or a person who has been granted Open Access under these Regulations;(aa)"Partial Open Access Consumer" means a consumer who has been granted Open Access under these Regulations to source power from a generating company or generating companies or other Licensee or through Power exchange and at the same time maintains partial demand with Distribution Licensee (in whose area of supply the consumer is located) to cater its load requirement;(bb)"Sanctioned Load" means load in kilowatt (kW)/Horse power (HP) mutually agreed between the Distribution Licensee and the consumer;(cc)"Short-term Open Access" means the right to use the Distribution system for a period not exceeding one (1) month at a time;(dd)"SLDC" means the State Load Despatch Centre in Maharashtra established under sub-section (1) of Section 31 of the Act;(ee)"State Grid Code" means the State Grid Code specified by the Commission under clause (h) of sub-section (1) of section 86 of the Act, applicable on the date of commencement of these Regulations and as amended from time to time;(ff)"State Transmission Utility (STU)" means the Government Company notified by the Government of Maharashtra under sub-section (1) of section 39 of the Act;(gg)"Special Energy Meters" means meters installed in accordance with the Central Electricity Authority (Installation and Operation of Meters) Regulations, 2006, specified by the Central Electricity Authority and amended from time to time;(hh)"Standards of Performance Regulations" means the Regulations specified by the Commission under clause (za) of sub-section (2) of Section 181 of the Act;(ii)"Supplier" means a Generating Company or Licensee, as the case may be, giving supply of electricity to a consumer or a person situated in the area of supply of the other Distribution Licensee by using the distribution system of the other Distribution Licensee in his area of supply, pursuant to a Connection and Use of Distribution System Agreement or giving supply by laying the dedicated Transmission lines;(jj)"Supply Agreement" means the agreement contemplated under Section 49 of the Act;(kk)"Tariff Regulations" means the Regulations as specified by the Commission under clause (zd) of sub-section (2) of Section 181 read with Section 61 of the Act;(ll)"Transmission Open Access Regulations" means the Regulations as specified by the Commission under sub-section (47) of Section 2 read with Section 30 and sub-section (3) of Section 32 of the Act, as amended from time to time.(mm)"Time Block" means time block of 15-minute each for which special energy meters record specified electrical parameters and quantities with first time block starting at 00:00 hours.3. Eligibility to seek Open Access and Nodal Agency.
- 3.1 Subject to the provisions of these Regulations, a consumer having contract demand of 1 MW and above and where the minimum power to be made available for Open Access at any time is 1 MW and above, shall be eligible for seeking Open Access to the distribution system of such Distribution Licensee for obtaining supply of electricity from a Generating Company or Captive Power Plant or from a Licensee other than such Distribution Licensee or through the Power Exchange :Provided that Open Access Consumers may avail Open Access from Multiple Generating Companies only to extent so as to meet their Renewable Purchase Obligations as specified in the MERC (Renewable Purchase Obligation, its Compliance and Implementation of REC Framework) Regulations, 2010 and as amended from time to time :Provided that for the purpose of unit conversion from MVA/kVA to MW/kW, the unity power factor shall be considered :Provided that the necessary conditionality mentioned in Regulation 3.1 about minimum power to be made available for Open Access at any time is 1 MW and above, for being eligible for seeking Open Access shall not be applicable for Open Access getting supply from a Renewable Energy generating plant identified as 'Non firm power' under MERC (Terms and conditions for determination of RE Tariff) Regulations, 2010, as amended from time to time :Provided also that the Maximum Demand of such consumer or person in each financial year subsequent to his being granted Open Access shall be equal to or greater than seventy (70) percent of the threshold level at which he has become eligible for Open Access. If the consumers fail in achieving maximum demand in three consecutive months, failing which the Distribution Licensee shall be entitled to levy a penalty equal to the two times wheeling charges for the financial year or part thereof for which he had failed to achieve such Maximum Demand :Provided also that, if such consumer or person has not complied with the above proviso in consecutive 3 months, the Distribution Licensee may initiate the process of reassessment and reinstatement/reduction of Contract Demand :Explanation. - For the purposes of these Regulations, a consumer who is otherwise eligible for Open Access in accordance with Regulation 0 and who wishes to procure power through a Power Exchange must either be a 'Member' or must procure power through a 'Member' of any power exchange, in accordance with the Central Electricity Regulatory Commission (Power Market) Regulations, 2010, as amended from time to time :Provided that power procurement through Power Exchange shall be permissible only on week-ahead basis or higher denomination of days and not on Day-Ahead basis :Provided that for Rooftop Solar projects, the Commission by general or specific Order or Regulations may specify separate terms and conditions :Provided that individual eligible consumers in Distribution Franchisee Area may apply for Open Access, in accordance with these Regulations. Individual eligible consumers should have metering and other infrastructure for seeking Open Access in accordance with these Regulations.However, Distribution Franchisee shall not be eligible for seeking Open Access :Provided that the Open Access quantum shall be limited to the Original Contract Demand before seeking Open Access of the consumer with the Distribution Licensee for availing Open Access from Generating Stations other than Renewable Energy generating plant identified as 'Non firm power' under MERC (Terms and conditions for determination of RE Tariff) Regulations, 2010, as amended from time to time.4. Processing of Applications for Distribution Open Access.
- 4.1. Application Formats, etc :An application for Open Access to the distribution system of a Distribution Licensee shall be made to such Distribution Licensee in the Form provided in Annexure I herein:Provided that such application shall be accompanied by necessary particulars/documents and fees for processing the application as provided in Regulation 9.Provided also that every Distribution Licensee shall put up with the prior approval of the Commission, on its internet website, within a period of sixty (60) days from the date of notification of these Regulations or within sixty (60) days from the grant of licence, whichever is applicable, the information requirements, procedures, application forms and fees, in downloadable format, as may be necessary for an application to be made by such a consumer seeking Open Access to its distribution system.Provided further the application formats issued under the Maharashtra Electricity Regulatory Commission (Distribution Open Access) Regulations, 2005, shall continue to be in use till such time the new application formats are issued and/or uploaded on the internet website of the Distribution Licensee, and any inconsistency between the existing formats and the provisions of these Regulations shall be harmoniously construed for purposive application of these Regulations.| Particulars | Demand (MW) | |
| Original Contract Demand with the Distribution Licensee | (a) | 10 |
| Open Access quantity | (b) | 4 |
| Revised Contract Demand with Distribution Licensee | (c) = (a) - (b) | 6 |
Part B – Connectivity
5. Grant of Connectivity.
- 5.1. A Generating Station having installed capacity less than 5 MW shall be eligible to obtain connectivity to the Distribution system and shall apply for connectivity as per the provisions of these Regulations, unless already connected, in accordance with the provisions in this chapter :Provided that a generating station having installed capacity of 5 MW and above may also get connectivity to the distribution system but only after such connectivity is technically feasible in accordance with Regulation 5.5.Part C – General Provisions for Open Access
6. Agreements.
- 6.1. A Connection and Use of Distribution System Agreement shall be in the Form provided in Annexure II herein upon grant of Open Access in accordance with these Regulations :Provided that this Regulation shall also be applicable in case Open Access is applied to obtain supply from a Power Exchange in accordance with Regulation 3.1. :Provided that the Distribution Licensee shall put up the said Form of the Connection and Use of Distribution System Agreement on its internet website, in downloadable format, within sixty (60) days from the date on which such consumer/person becomes eligible for Open Access or within sixty (60) days from the grant of licence, whichever is later, to enable such consumer/person to obtain supply through Open Access in accordance with these Regulations :7. Access to premises and property.
- 7.1. No person other than the Authorised Representative of the Distribution Licensee or any other person authorised under the Act and the Rules and Regulations laid down there under shall be authorised to operate, handle or remove any electrical plant, electric lines or meter or break, remove, erase or otherwise interfere with the seals, name plates and distinguishing numbers or marks affixed on the property of the Distribution Licensee in the Consumer's premises:Provided that such Authorised Representative shall not perform any of the aforesaid acts except in the presence of the Consumer or his representative:Provided further that the Distribution Licensee shall provide prior intimation of the visit of the Authorised Representative to the Consumer's premises, except where there is reason to believe that any person is indulging in unauthorized use of electricity and/or is committing an offence of the nature provided in Part XIV of the Act on such premises.8. Category of Open Access.
- 8.1. Categories of Open Access Consumers The application procedure, application fee and the time frame of processing request by eligible consumers seeking Open Access shall be based on the following criteria.9. Application procedure for Open Access.
- 9.1. All applications for Open Access shall be made in the prescribed Form and submitted to the Nodal agency along with application fees and any other charges as may be specified by the Commission from time to time, in accordance with these Regulations :Provided that the time frame mentioned in Regulation 9.2 shall be applicable from the date of submission of completed Application in all respect.| Consumer seeking Distribution Open Access | |||||
| S. No. | Period | Inter se location of drawal and injectionpoint | Nodal agency | Documents to accompany the application | Time frame for processing the application(days from the receipt of application) |
| 1. | Short Term Open Access | Both within the same Distribution Licensee | Distribution Licensee on whose DistributionSystem the Consumer is connected to | Proof of payment of Application fee, PPA orSale-purchase agreement of power, copy of latest consumer bill incase the applicant is a consumer of Distribution Licensee | Ten (10) workingdays in case STOA applied for first time.Five (5) working days on subsequent STOAapplications. |
| 2. | Both within the State but in areas of differentDistribution Licensees | Distribution Licensee on whose DistributionSystem the Consumer is connected to | Proof of payment of Application fee, PPA orSale-purchase agreement of power, copy of latest consumer bill incase the applicant is a consumer of Distribution Licensee | Ten (10) workingdays in case STOA applied for first time.Five (5) working days on subsequent STOAapplications. | |
| 3. | Injection point in the intra-State transmissionsystem within the State | Distribution Licensee on whose DistributionSystem the Consumer is connected | Proof of payment of Application fee, PPA orSale-purchase agreement of power, copy of latest consumer bill incase the applicant is a consumer of Distribution Licensee | Ten (10) workingdays in case STOA applied for first time.Five (5) working days on subsequent STOAapplications. | |
| 4. | In different States | RLDC of the region where consumer is located to | Consent from concerned SLDCs and DistributionLicensees as applicable, Proof of payment of Application fee, PPAor Sale-purchase agreement of power, copy of latest consumer billin case the applicant is a consumer of Distribution Licensee | As per Central Commission's Regulation | |
| 5. | Consumer opting to avail power supply from Powerexchange | Distribution Licensee on whose DistributionSystem the Consumer is connected to | Proof of payment of Application fee, PowerExchange related documents, copy of latest consumer bill in casethe applicant is a consumer of Distribution Licensee | Ten (10) workingdays in case STOA applied for first timeFive (5) working days on subsequent STOAapplications | |
| 6. | Medium-Term Open Access | Both within the same Distribution Licensee | Distribution Licensee on whose DistributionSystem the Consumer is connected to | Proof of payment of Application fee, PPA orSale-purchase agreement of power, in case of generating stationnot already connected to grid, documentary evidence forcompletion of the connectivity showing that the same shall becompleted before intending date of MTOA | Thirty (30) days |
| 7. | Both within the State but in areas of differentDistribution Licensees | Distribution Licensee to on whose DistributionSystem the Consumer is | Proof of payment of Application fee, PPA orSale-purchase agreement of power, in case of generating stationnot already connected to grid, documentary evidence forcompletion of the connectivity showing that the connected to | Sixty (60) days | |
| 8. | Injection point in the intra-State transmissionsystem within the State | Distribution Licensee on whose DistributionSystem the Consumer is connected to | Proof of payment of Application fee, PPA orSale-purchase agreement of power, in case of generating stationnot already connected to grid, documentary evidence forcompletion of the connectivity showing that the same shall becompleted before intending date of MTOA | Sixty (60) days | |
| 9. | In different States | CTU | Proof of payment of Application fee, PPA orSale-purchase agreement of power. In case of generating stationnot already connected to grid, documentary evidence forcompletion of the connectivity showing that the same shall becompleted before intending date of MTOA, Consent from concernedSLDCs and Distribution Licensees as applicable | As per Central Commission's Regulation | |
| 10. | Long Term Access | Both within the same Distribution Licensee | Distribution Licensee on whose DistributionSystem the Consumer is connected to | Proof of payment of Application fee, PPA orSale-purchase agreement of power. , In case of generating stationnot already connected to grid, documentary evidence forcompletion of the connectivity showing that the same shall becompleted before intending date of LTA. | Thirty (30) days |
| 11. | Both within the State but in areas of differentDistribution Licensees | Distribution Licensee on whose DistributionSystem the Consumer is connected to | Proof of payment of Application fee, PPA orSale-purchase agreement of power, In case of generating stationnot already connected to grid, documentary evidence forcompletion of the connectivity showing that the same shall becompleted before intending date of LTA, consent from concernedDistribution Licensees | One hundredtwenty (120) days where augmentation of distribution system isnot requiredOne hundred eighty (180) days, whereaugmentation of distribution system is required. | |
| 12. | Injection point in the intra-State transmissionsystem within the State | Distribution Licensee on whose DistributionSystem the Consumer is connected to | Proof of payment of Application fee, PPA orSale-purchase agreement of power, In case of generating stationnot already connected to grid, documentary evidence forcompletion of the connectivity showing that the same shall becompleted before intending date of LTA, Consent from concernedDistribution Licensee | One hundredtwenty (120) days where augmentation of distribution system isnot required.One hundred eighty (180) days, whereaugmentation of distribution system is required. | |
| 13. | In different States | CTU | Proof of payment of Application fee, PPA orSale-purchase agreement of power, In case of generating stationnot already connected to grid, documentary evidence forcompletion of the connectivity showing that the same shall becompleted before intending date of LTA, Consent from concernedSLDCs and Distribution Licensees as applicable | As per Central Commission's Regulation |
10. Procedure for Long Term Open Access.
- 10.1. Involving inter-State Transmission System :Notwithstanding anything contained in Regulation 10.2 herein below, the procedure for inter-State Long-term Open Access shall be as per Central Electricity Regulatory Commission (Grant of Connectivity, Long-term Open Access and Medium-term Open Access in inter-State Transmission and related matters) Regulations, 2009 as amended from time to time:Provided that in case of a consumer connected to a distribution system seeking inter-State Long-term Open Access, the SLDC, before giving its consent to the RLDC as required under the Central Commission's Regulations, shall require the consumer to submit the consent of the Distribution Licensee concerned in accordance with Regulation 13 hereof.11. Procedure for Medium Term Open Access.
- 11.1. Involving inter-State transmission system :Notwithstanding anything contained in Regulation 11.2 herein below, the procedure for inter-State Medium-term Open Access shall be as per Central Electricity Regulatory Commission (Grant of Connectivity, Long-term Open Access and Medium-term Open Access in inter-State Transmission and related matters) Regulations, 2009 as amended from time to time:Provided that in case of a consumer connected to a distribution system seeking Inter-State Long term Open Access, the SLDC, before giving its consent to the RLDC as required under the Central Commission's Regulations, shall require the consumer to submit the consent of the Distribution Licensee concerned in accordance with Regulation 13 hereof.12. Procedure for Short Term Open Access.
- 12.1 Supply of electricity involving inter-State Transmission System where the Applicant is connected to the Distribution System :Notwithstanding anything contained in Regulation 12.2 of these Regulations, the procedure for inter-State short-term Open Access shall be as per Central Electricity Regulatory Commission (Open Access in inter-State Transmission) Regulations, 2008 as amended from time to time:Provided that in respect of a consumer connected to a distribution system seeking inter-State short-term Open Access, the SLDC, before giving its consent to the RLDC as required under the Central Commission's Regulations, shall require the consumer to submit the consent of the Distribution Licensee concerned in accordance with Regulation 13 hereof:Provided further that the Distribution Licensee shall provide its consent in case there are no pending claims against the consumer.13. Consent by Distribution Licensee.
- 13.1 Before giving consent for Open Access, and subject to the other provisions of these Regulations, a Distribution Licensee shall verify the following :(i)Existence of infrastructure necessary for time-block-wise energy metering and accounting in accordance with the provisions of the State Grid Code in force, and(ii)Availability of capacity in the distribution system.14. Allotment Priority.
- 14.1 The priority for allotment of Open Access in Distribution system shall be decided on the following criteria:Part D – Open Access Charges
15. Billing.
- 15.1 The bill for supply of electricity to the consumer shall be raised by the Supplier and such bill shall separately and clearly indicate the following:(i)Charges for supply of electricity, in accordance with the terms and conditions of the Supply agreement, if any(ii)Any other charge or other sum recoverable from the consumer under the Act or these Regulations or under any other law for the time being in force.16. Wheeling Charges.
- 16.1 Open Access customer using Distribution system shall pay the wheeling or Dedicated Distribution facility charge, as the case may be, as under:(a)Wheeling charges payable to the Distribution Licensee by an Open Access customer for usage of their system shall be determined under the Maharashtra Electricity Regulatory Commission (Multi Year Tariff) Regulations, 2011, as amended from time to time:Provided that the Wheeling charges shall be payable on the basis of actual energy flow at the consumption end:Provided that the charges payable by a user of the Distribution System User under this Regulations may comprise of any combination of fixed/demand charges, and variable charges, as may be stipulated by the Commission from time to time:Provided further that where a dedicated distribution system used for Open Access has been constructed for exclusive use of an Open Access customer, the wheeling charges for such dedicated system shall be worked out by Distribution Licensee for their respective systems and got approved by the Commission and shall be borne entirely by such Open Access customer till such time the surplus capacity is allotted and used for by other persons or purposes.17. Cross Subsidy Surcharge.
- 17.1 Every consumer of a Distribution Licensee who has been granted Open Access in accordance with these Regulations or any consumer situated within area of the supply of Distribution Licensee and/or receiving supply from a Generating Company using dedicated transmission line, shall be liable to pay a cross subsidy surcharge, as may be stipulated, as a condition for availing Open Access:Provided further that such surcharge shall not be leviable in case Open Access is provided to a person who has established a captive generating plant, in respect of his captive generation, for carrying the electricity to a destination of his own use.18. Additional Surcharge.
- 18.1 An Open Access consumer, receiving supply of electricity from a person other than the Distribution Licensee of his area of supply, shall pay to the Distribution Licensee an additional surcharge on the charges of wheeling and cross-subsidy surcharge, to meet the fixed cost of such Distribution Licensee arising out of his obligation to supply as provided under sub-section (4) of section 42 of the Act.19. Standby Charges for drawal of power by Open Access Consumer from Distribution Licensee.
- 19.1 In the event of termination of supply by the Supplier or in case of outages of generator supplying to Open Access consumer, the Distribution Licensee shall provide Standby supply to meet the requirement of load catered through Open Access until such time as alternative arrangements for supply has been arranged by the Open Access consumer.Provided that such Standby supply would continue to be provided by the Distribution Licensee at day ahead request from the Open Access consumer.Provided further that such Standby supply once commenced shall be applicable for all 96 time blocks for the day.Provided further that such Standby supply shall be governed by the terms and provisions of the Connection and Use of Distribution System Agreement.Provide that the Open Access consumer shall for that supply be liable to pay energy charges either at UI charge or the System Marginal Price identified under the Intra-state ABT mechanism or the Energy charge or Variable Charge of temporary tariff category, whichever is applicable of the Distribution Licensee on which consumer is connected as provided in the Tariff schedule approved by the Commission, whichever is higher.Provided further that if a consumer opts for Open Access to avail 'Non-firm power' from a Renewable energy generator as defined in MERC (Terms and conditions for determination of RE Tariff) Regulations, 2010, as amended from time to time, and for such energy supplied to extent of retained Contract Demand maintained by the consumer with the Distribution Licensee, the charge payable shall be tariff applicable for the category applicable to such consumer and appropriate penalty shall be levied on exceeding Contract Demand in accordance with the Orders of the Commission.Provided also that Open Access customers would have the option to arrange stand-by power from any other source.20. Security Deposit.
- 20.1 Except where the Consumer chooses to purchase the meter, the Distribution Licensee may require the Consumer to provide security for the price of the meter, in accordance with the provisions of clause (b) of sub-section (1) of Section 47 of the Act:Provided that in no case shall the amount of the security exceed the price of the meter.21. Compliance with State Grid Code.
- 21.1 It shall be the duty of all Consumers and all Suppliers to comply with the State Grid Code, as may be specified, to the extent made applicable to them:Provided that failure of the Consumer and/or Supplier to comply with the State Grid Code shall render such Consumer and/or Supplier, as the case may be, liable to consequences for contravention of the Act:Provided further that failure of the Consumer and/or Supplier to comply with the State Grid Code may also render such user liable to revocation of the Connection and Use of Distribution System Agreement:Part E – Scheduling, Metering, Revision and Losses
22. Scheduling.
- 22.1 Scheduling of inter-State Open Access transactions shall be as per IEGC, as amended from time to time.23. Metering and Communication.
- 23.1 In case of Open Access consumer and all generating stations irrespective of their capacity, Special Energy Meters shall be installed by the Distribution Licensee, for and at the cost of the consumer.Provided that such meters may be procured from the Distribution Licensee or from any supplier duly approved by the Distribution Licensee in accordance with specification made in compliance with Central Electricity Authority (Installation and Operation of Meters) Regulation, 2006 and its amendment from time to time.Provided also that the specification to be issued by the Distribution Licensee should be compatible with SLDC's requirement for energy accounting.Provided further that the Distribution Licensee should notify the particulars of at least two meter manufacturers from whom the consumers can purchase the Special Energy Meters that shall have provisions to meet billing requirements of Distribution Licensee.24. Revision.
- 24.1 Revision of scheduled energy shall be permitted in accordance with the provisions of IEGC or the State Grid Code as the case may be.25. Losses.
- 25.1 Transmission losses:25.1.1Inter-State transmission:25.1.1.1Long-term Open access and Medium-term Open Access: The buyers shall bear apportioned energy losses in the transmission system in accordance with the provisions specified by the Central Commission.25.1.1.2Short-term Open Access: The Open Access customer shall absorb energy losses in the transmission system in accordance with the provisions specified by the Central Commission.25.1.2Intra-State transmission:The transmission losses for the Intra-State system, as determined by the Commission shall be applicable for Open Access transactions.Provided that the schedule to be submitted by Open Access consumer shall consider the approved intra-State transmission loss.Provided that the energy settlement shall be done based on the normative loss in the intra-State transmission system.Part F – Imbalance and Reactive Energy Charges
26. Imbalance Charge.
- 26.1 Scheduling of all transactions pursuant to grant of Long-term Open Access or Medium-term Open Access or short-term Open Access shall be carried out on day-ahead basis in accordance with the relevant provisions of IEGC for Inter-State transactions and in accordance with State Grid Code/Commission's Orders for Intra-State transactions.Provided that the provisions of the Regulation 26 of these Regulations are not applicable for Open Access generators and consumers who are participants of State Pool and for them the provisions of energy balancing and settlement as specified in Final Balancing and Settlement Mechanism or any other Balancing Settlement Mechanism stipulated by the Commission from time to time, shall be applicable.27. Reactive Energy Charge.
- 27.1 In respect of Open Access Customer having a load of 5 MW or above, the methodology for payment for the reactive energy charges by Open Access consumers shall be in accordance with provisions stipulated in the State Grid Code and MYT Regulations, 2011 as amended from time to time.Part G – Commercial Matters
28. Billing, Collection and Disbursement.
- Billing in respect of the charges payable under these Regulations shall be made as per the following procedure :-29. Late Payment Surcharge.
- 29.1 In case the payment of any bill for charges payable under these Regulations is delayed by an Open Access customer beyond the due date, without prejudice to any action under the Act or any other regulation thereunder, a late payment surcharge at the rate of 1.25 per cent (%) per month shall be levied.30. Default in Payment.
- 30.1 Non-payment of any charge or sum of money payable by an Open Access customer under these Regulations shall be considered non-compliance of these Regulations. The Distribution Licensee may discontinue Open Access after giving customer an advance notice of fifteen days without prejudice to its right to recover such charges as per provisions of the Act.In case of default in payment of charges due to the SLDC, it may refuse to schedule power to the defaulting Open Access customer and direct the Distribution Licensee to disconnect such customer from the grid.31. Payment Security Mechanism.
- 31.1 In case of Long-term Open Access and Medium-term Open Access, the applicant for Open Access will open an irrevocable Letter of Credit in favour of the agency responsible for collection of various charges for the estimated amount of various charges for a period of two months.32. Flexibility to change points of Injection and Drawal.
- 32.1 The Long-term Open Access consumer shall have the flexibility to change the point of injection and/or point of drawal twice in a year subject to the results of system impact studies to be carried out by the concerned Distribution Licensee at the behest of such consumers :Provided that while providing this flexibility to the applicant the rights of existing consumers shall not be adversely affected :Provided that any additional expense to be incurred by Distribution Licensee pertaining to such a change shall be borne by the Long term Open Access Consumer.Part H – Information System
33. Information System.
- 33.1 Every Distribution Licensee shall maintain an internet based information system giving the following details:Part I – Open Access to Generating Station Connected to Distribution System
34. Applicability.
- 34.1 A generating station connected to a Distribution system seeking Open Access shall have to follow, except in respect of the case covered under Regulation 36.1, the same procedure as applicable for a consumer seeking Open Access under different scenarios, namely Long-term Open Access, Medium-term Open Access and short-term Open Access. Such generating station shall also be liable to pay the same application fee, and other Open Access charges except the cross subsidy surcharge and additional surcharge as are applicable to a consumer seeking Open Access.35. Processing of Application.
- The Distribution Licensee, while processing the application of such a generating station, shall follow the following procedure.Part J – Miscellaneous
36. Obligations of a Transmission Licensee.
- 36.1 Where the consumer or person, having been granted Open Access under these Regulations, obtains supply of electricity from a connection to the intra-State transmission system of a Transmission Licensee and the distribution system of the Distribution Licensee is not used for the supply of electricity to such consumer or person, the provisions of the Connection and Use of Distribution System Agreement shall not be applicable.Provided that surcharge will be payable if the Open Access consumer is located within the area of supply of the Distribution Licensee.37. Curtailment Priority.
- 37.1 Subject to any technical constraints in the operation of the State grid, if it becomes necessary to curtail the Open Access service of the customers, subject to the requirements of State Grid Code, the Open Access to a Distribution Licensee shall be the last to be curtailed. Among others, short term Open Access customers shall be curtailed first, followed by the Medium-term Open Access customers followed by Long-term Open Access customers.Provided that among Short-term Open Access transactions, bilateral transactions will be cancelled or curtailed first, followed by Power Exchange transactions.38. Existing Contracts.
- 38.1 Anything done or any action taken or purported to have been done or taken including any existing contract or document or instrument issued or executed prior to the notification of these Regulations and which relates to the use of the distribution system shall be deemed to be valid and binding only in so far as it is not inconsistent with the Act.Provided that a consumer on completion of his Open Access period would be recognised and billed in a manner similar to all other consumers of the Distribution Licensee, there would be no change in his status and would receive similar services as provided by the Distribution Licensee prior to the Open Access period.39. Disputes.
- 39.1 Any dispute under these Regulations shall be adjudicated upon by the Commission.Provided that the Commission shall take into account the report of the Committee referred to below for adjudication of the dispute.1. Committee
40. Force Majeure.
- 40.1 Nothing contained in these Regulations shall be taken as requiring a Distribution Licensee to grant connectivity, consent for Open Access if it is prevented from so doing, by the occurrence of any Force Majeure event. Force Majeure events are:41. Exemption.
- 41.1 Nothing contained in these Regulations shall apply to a local authority engaged in the business of distribution of electricity before the appointed date.42. Power to Amend.
- 42.1 The Commission may, at anytime, amend any provisions of these Regulations.43. Powers to Remove Difficulties.
- 43.1 If any difficulty arises in giving effect to the provisions of these Regulations, the Commission may, by general or specific order, make such provisions, not inconsistent with the provisions of the Act, as may appear to be necessary or expedient for the purpose of removing difficulties.44. Repeal and Savings.
- 44.1 Save as otherwise provided in these Regulations, the Maharashtra Electricity Regulatory Commission (Distribution Open Access) Regulations, 2005, shall stand repealed from the date of notification of these Regulations.1. Current status of applicant: Consumer/Intending consumer
2. Particulars for connection to Consumer:
3. Particulars for connection to intending Consumer or person requiring supply within area of supply of Distribution Licensee:
4. Particulars for connection to Generating Company or Licensee, against application by consumer/intending consumer : As provided by the Distribution Licensee based on technical requirements relating to connection to the distribution system.
Annexure II[See Regulation 6 of MERC (Distribution Open Access) Regulations, 2014]Form of Connection and Use of Distribution System AgreementThis agreement is made on the _______ day of _________ 20 __ between,-Part A – General
1. Definitions. - In this agreement, unless the context otherwise requires-
2. Compliance with Act, Rules and Regulations. - 2.1. All parties to this agreement shall comply with the provisions of the Act and the rules and Regulations laid down there under. Where any provision of this agreement is inconsistent with the provisions of the Act and/or the rules or Regulations laid down there under, the provisions of the Act, rules or Regulations, as the case may be, shall take precedence to the extent of such inconsistency.
3. Compliance with Distribution and Transmission Open Access Regulations, 2014, State Grid Code and Balancing and Settlement Code and as amended from time to time. - 3.1. All parties to this agreement shall comply with the provisions of the Distribution and Transmission Open Access Regulations, 2014 the State Grid Code and the Balancing and Settlement Code, to the extent applicable to them.
4. Term of agreement. - 4.1. This agreement shall commence from the date and time of commencement, as provided in the agreement and shall continue for such duration as may be agreed between the parties, unless terminated in accordance with clause 5 herein.
5. Termination of agreement. - 5.1. Any party intending to terminate this agreement shall give the other parties not less than thirty (30) days prior written notice of termination of this agreement:
Provided, that termination shall be subject to settlement of all dues of the Distribution Licensees in accordance with the Act, the Regulations and this agreement.6. Dispute resolution. - 6.1. Each party shall use all reasonable endeavors to resolve any disputes through bilateral mechanisms that may be mutually agreed upon.
7. Force Majeure. - 7.1. If either party is unable wholly or partly to perform on time any obligation under this agreement by reason of occurrence of a Force Majeure Event, that obligation shall be suspended, without liability, so far as the party's ability to perform is affected by the Force Majeure Event.
8. Representations and warranties. - 8.1. The Supplier represents and warrants that -
(a)he is a Generating Company or Licensee who is supplying to or intends to supply to an eligible person requiring supply, in accordance with the provisions of the Act and the Distribution Open Access Regulations9. Changes to agreement. - 9.1. The parties agree to negotiate in good faith any amendments to this agreement that may be reasonably required as a result of experience gained in the introduction of open access in the State.
Part-B Connection10. Agreement to Connect. - 10.1. This agreement shall be entered into pursuant to an application made by:
(a)a consumer; and(b)a person requiring supply, whose premises are situated within the area of supply of a Distribution Licensee.for access to the distribution system of the Distribution Licensee in accordance with the provisions of the Act and the Distribution Open Access Regulations.11. Processing of applications. - 11.1. Upon receipt of an application under clause 10.1 above, the Distribution licensee shall, where the applicant is not an existing consumer, send his Authorised Representative to :
(a)study the technical requirements of making connection to the distribution system; and(b)inspect the premises which is to be connected, with prior intimation to the consumer12. Rights of Way and Access Conditions. - 12.1. The applicant shall grant to the Distribution Licensee all consents that the applicant is empowered to give as are required by the Distribution licensees for carrying out of works to give access to the distribution system.
13. Principles for levy of charges. - 13.1. Where the connection entails works of laying a service-line from the distributing main to the applicant's premises, the Distribution Licensee shall be authorized to recover all expenses incurred on such works from the applicant based on the schedule of charges approved by the Commission under the Electricity Supply Code.
14. Change of name. - 14.1. A connection may be transferred in the name of another person upon death of the Consumer or in case of transfer of ownership or occupancy of the premises, upon application for change of name by the new owner or occupier :
Provided that such change of name shall not entitle the applicant to require shifting of the connection to a new premises.15. Wiring of Consumer's Premises. - The work of wiring at the premises of the Consumer beyond the point of connection shall be carried out by the Consumer and shall confirm to the standards specified in the Indian Electricity Rules, 1956 until the introduction of any rules or Regulations for the same under the provisions of the Act.
16. Limitation on Demand and Export. - 16.1. The Consumer shall not import or export electricity through the Connection Point exceeding the Contract Demand (Import or Export, as applicable) as agreed from time to time, without the prior written consent of the Distribution Licensee.
17. Power Factor/Harmonics. - 17.1. It shall be obligatory for the Consumer to maintain the average power factor of his load at levels prescribed by the Indian Electricity Rules, 1956 with such variations, if any, adopted both by the Distribution Licensee, in accordance with Rule 27 of the Indian Electricity Rules, 1956 and in accordance with the relevant orders of the Commission.
18. Access to premises. - 18.1. No person other than an Authorised Representative of the Distribution Licensee or any other person authorised under the Act and the rules and Regulations made there under shall be authorised to operate, handle or remove any electrical plant, electric lines or meter or break, remove, erase or otherwise interfere with the seals, name plates and distinguishing numbers or marks affixed on such property of the Distribution Licensee placed in the Consumer's premises:
Provided that such Authorised Representative of both the Distribution Licensee shall not perform any of the acts under this clause 18 except in the presence of the Consumer or his representative:Provided further that the Distribution Licensees shall provide prior intimation to the Consumer of the visit of the Authorised Representative to the Consumer's premises, except where the Distribution Licensee has reason to believe that any person is indulging in unauthorized use of electricity and/or is committing an offence of the nature provided for in Part XIV of the Act on such premises.19. Meters. - 19.1. Meter specifications
(a)Every Consumer shall install or have installed a correct meter in accordance with the Regulations made in this behalf by the Authority under Section 55 of the Act:Provided that every Consumer who is either :(i)a consumer with contract as permitted under Regulation 3.1 of MERC (Distribution Open Access) Regulation, 2014 and its amendment from time to time; or(ii)a person requiring supply, whose premises are situated within the area of supply of the Distribution Licensee, with a contract demand as permitted under Regulation 3.1 of MERC (Distribution Open Access) Regulation, 2014 and its amendment from time to time; or(iii)a Generating Company or Licensee;shall install or have installed a Special Energy Meter:20. Use of Distribution System. - 20.1 The Distribution Licensee shall allow the use of distribution system for wheeling of electricity, in a non-discriminatory manner, on terms and conditions that are no more onerous than those applicable to other comparable users of the distribution system of the Distribution Licensee.
21. Quality and reliability of supply. - 21.1 The Distribution licensee shall maintain the standards for quality and reliability of supply of electricity over its distribution system, rectification of faults and other consumer complaints pertaining to the distribution system, in accordance with the Standards of Performance Regulations.
22. Information exchange. - 22.1 The Distribution Licensee and the Supplier agree to use their reasonable endeavours to provide each other, in a timely manner, such information in respect of the open access consumers and their connection to and use of distribution system as either of them may possess and as the other may reasonably require to carry out their obligations under the Act, the Rules, the Distribution Open Access Regulations or this agreement :
Provided further that the provision of information under this clause shall be subject to the obligations of both parties to maintain confidentiality of such information being requested for, under the Act or any other law for the time being in force.23. Co-ordination of services. - 23.1 The Distribution Licensee and the Supplier agree to co-ordinate their functions to facilitate the supply of electricity to the consumer in accordance with this clause 23.
24. Payments for services. - 24.1 Billing
24.1.1The Distribution Licensee shall bill the Supplier/consumer for the services provided under this agreement on a monthly basis. Bills shall be issued by the tenth (10th) day of each month for charges payable for the previous month.24.1.2The Supplier/consumer shall pay for the charges within such period as may be specified in the Electricity Supply Code.24.1.3The Supplier/consumer shall be required to pay the charges in accordance with Distribution Open Access Regulations, 2014 and as amended from time to time.25. Security deposits. - 25.1 The Distribution Licensee shall be entitled to security equivalent to one month's billing for wheeling charge, cross-subsidy surcharge and additional surcharge on charges of wheeling, in accordance with clause 24.1 above.
| Name & Signature Consumer | Name & Signature Distribution Licensee | Name & Signature Supplier |
| Application forGrant of Short Term Open Access(To be submitted by Short Term Open AccessApplicant) | ||||||
| 1 | Customer Application No.: | Date: | ||||
| 2 | Name of the Applicant | |||||
| 3 | Consumer No.: | Existing Supplier (if any): | ||||
| 4 | Meter No.: | Connection Type: | ||||
| 5 | Address for Correspondence: | |||||
| Phone no: | (off.) | (Res.): | (Fax): | |||
| E-mail id: | Mobile no. | |||||
| 6 | Contract details (Agreement/MoU details) | |||||
| Applicant type | Buyer/ Seller/ Trader/ Captive Generator/ Renewable EnergyGenerator | |||||
| With | No. | date | Valid upto | Capacity in the Contract (MW) | Capacity if contracted to other source (MW) | No. of days Open Access Applied |
| Buyer | ||||||
| Seller | ||||||
| Power | ||||||
| Exchange | ||||||
| 7 | Co-ordinator details | |||||
| Name and Designation: | ||||||
| Phone no: | (off.) | (Fax): | Mobile | |||
| Email id: | ||||||
| 8 | Capacity applied | |||||
| Period | Time period | Capacity (MW) | ||||
| From (Date) | To (date) | From (hrs.) | To (hrs.) | |||
| 9 | Details of PPA/ PSA/ MoU | Date of PPA/ PSA/ MoU | Validity period | Capacity | ||
| Name & Address of Parties | Commencement | Expiry | MW | |||
| Seller | Buyer | |||||
| 10 | Injecting utility details | |||||
| Name : | ||||||
| Point of Injection : | ||||||
| Name of the concerned Discom/ Licensee : | ||||||
| Details (path to the nearest sub-station) : | ||||||
| Meter No.: | ||||||
| 11 | Drawing utility details Name: | |||||
| Point of Drawl: | ||||||
| Name of the concerned Discom/ Licensee: | ||||||
| Details (path to the nearest sub-station): | ||||||
| Meter No.: | ||||||
| 12 | Name of the trader, if any: | |||||
| 13 | Details of application fee payment: |
14. It is hereby, certified that :-
15. The provisions of the 'Procedure for reservation of transmission capacity to Short-term Open Access users issued by SLDC are hereby agreed.
Place :Date:Signature :Name and Designation :Enclosure:| For use of Distribution licensee (with reference toapplication submitted by Applicant) | |
| Distribution licensee's ref. no. | Date |
| Distribution licensee approval/refusal no. | |
| Remarks (reasons for refusal to be provided) |
| For use of SLDC (with reference to application submitted by Applicant) | |
| SLDC ref. no. | Date |
| SLDC approval/refusal no. | |
| Remarks (reasons for refusal to be provided) |
| 1 | Customer Application No. | Date | |
| 2 | Period of Transaction | ||
| 3 | Nature of Customer* | < seller/buyer/captive user/trader(on behalf ofseller/buyer/captive user) > | |
| 4 | Customer Name | ||
| 5 | Registration Code | Valid upto |
| Date and Time of Receipt of Application |
| 1 | Customer Application No. | Date | |
| 2 | Period of Transaction | ||
| 3 | Nature of Customer* | < seller/buyer/captive user/trader(on behalf ofseller/buyer/captive user) > | |
| 4 | Customer Name | ||
| 5 | Registration Code | Valid upto |
| Date and Time of Receipt of Application |
| Distribution licensee Approval No. | / (R-0) | Date |
| 1 | Customer Application No. | < as provided by customer on FORMAT-ST1 > | Date | |
| 2 | Period of Transaction | |||
| 3 | Nature of Customer* | < seller/ buyer/ captive user/ trader (on behalf ofseller/ buyer/ captive user) > |
| 4 | Customer Name | ||
| 5 | Registration Code | Valid up to |
| 6 | Details of Transaction Party's to Distribution system | ||
| Injecting Entity | Drawee Entity | ||
| Name of Entity | |||
| Status of Entity* | |||
| Utility in which it is embedded |
| 7 | Details of Injecting/Drawee Connectivity with DistributionSystem | ||
| Injecting Entity | Drawee Entity | ||
| Name of Sub-station | Transmission | ||
| Distribution | |||
| Voltage level | Transmission | ||
| Distribution | |||
| Name of Licensee (Owner of S/S) | |||
| Intervening Intra-State Licensee | |||
| Intervening Inter-State Licensee |
| 8 | Open Access Approved for (Period from date ______to date ______) | Revision No. | 0 | ||||
| Month | Date | Hours | Capacity (MW) | MWh | |||
| From | To | From | To | Applied | Allotted | ||
| TOTAL MWh |
| 9 | Details of Bidding< only in case of Bidding > | ||||
| Details of Intra-State System | Date | Hours | Applicable Rate (Rs./kWh) | ||
| From | To | From | To | ||
| Transmission System | |||||
| Distribution System |