Section 25(4) in The U.P. Electricity Regulatory Commission (Captive and Non-Conventional Energy Generating Plants) Regulations, 2009

(4)The Generating Plant shall abide by the grid discipline and shall not be entitled for any compensation in the event of grid failure or any interruptions or damage to the plant or its associated sub-stations or transmission line on account of any happening in the grid.