State of Uttar Pradesh - Act
The U.P. Electricity Regulatory Commission (Captive and Non-Conventional Energy Generating Plants) Regulations, 2009
UTTAR PRADESH
India
India
The U.P. Electricity Regulatory Commission (Captive and Non-Conventional Energy Generating Plants) Regulations, 2009
Rule THE-U-P-ELECTRICITY-REGULATORY-COMMISSION-CAPTIVE-AND-NON-CONVENTIONAL-ENERGY-GENERATING-PLANTS-REGULATIONS-2009 of 2009
- Published on 22 March 2010
- Commenced on 22 March 2010
- [This is the version of this document from 22 March 2010.]
- [Note: The original publication document is not available and this content could not be verified.]
Chapter 1
Preliminary
1. Short title and commencement.
2. Scope and extent of application.
3. Tariff determination.
- The tariff in respect of a Generating Plant under these Regulations shall be applicable to the capacities or the units in respect to which an agreement has been reached between the parties for supply of electricity:Provided also that any commercial arrangement, other than tariff, made or agreed between the parties in a Power Purchase Agreement for supply of electricity, prior to UPERC CNCE Regulations, 2005, may be continued with the approval of the Commission for such time as considered appropriate by the Commission. However the tariff under such agreement shall be determined as per provisions of these Regulations.4. Tariff for Non-Conventional Energy Generating Plants other than covered under these Regulations.
- For Non-Conventional Energy Generating Plants, other than covered under these Regulations, the tariff shall be determined by the Commission on case to case basis on receipt of an application for this purpose.5. Approval of Power Purchase Agreement.
- The Distribution Licensee shall make an application for approval of Power Purchase Agreement entered into with the Generating Plant in such form and such manner as prescribed in these Regulations and UPERC (Conduct of Business) Regulations notified by the Commission from time to time.6. Definitions.
- (i) "Banking of power" is the process under which a Generating Plant supplies power to the grid not with the intention of selling it to either a third party or to a Licensee, but with the intention of exercising its eligibility to draw back this power from the grid;7. General Power to Amend.
- The Commission may, at any time and on such terms as to costs or otherwise, as it may think fit, amend any defect or error in any proceeding before it, and all necessary amendments shall be made for the purpose of determining the real question or issue arising in the proceedings.8. Power to Relax.
- The Commission, for reasons to be recorded in writing, may vary any of the provisions of these Regulations on its own motion or on an application made before it by any interested party.Chapter 2
Captive Power Generation
9. Object.
- As per the provisions of the Act, supply of electricity from a Captive Generating Plant through the grid shall be regulated in the same manner as the Generating Station of a Generating Company. These Regulations seek to achieve efficient, safe, well-co-ordinated operation of the plant, connectivity with the grid and exchange of information among the various utilities in the State grid, Central Utilities and Northern Regional Grid, as the case may be. Non-compliance of these Regulations shall be liable for action under the appropriate provision of the Act.10. Generation from Captive Power Plants.
11. General conditions for Captive Generating Plants.
12. Obligations of the Captive Generating Plant.
13. Duties of the Captive Generating Plant.
14. Open Access.
15. Transmission Charges and Wheeling Charges.
- The Plant or the Consumer, seeking 'Open Access' to the State and/or Inter State Transmission Systems and/or distribution system for carrying the electricity to the destination of use, shall pay the transmission charges, wheeling charges and such other charges for use of such facilities as determined by the Appropriate Commission(s).16. Surcharge and Additional Surcharge.
17. Sale of Power.
18. Tariff.
- The tariff for supply of electricity by a plant at pithead location to a Distribution Licensee shall be as per Schedule-1 of these Regulations:Provided that the Commission shall approve the transportation cost of fuel for non-pithead locations on case to case basis on a petition filed by the Generating Plant.Note. - (1) The tariff for supply of electricity from the plant, having more than one unit commissioned in different years, shall be based on weighted average of the contracted capacities of the units commissioned in different years.19. Purchase of Electricity.
- Any person, who establishes, maintains and operates a Generating Plant, may purchase electricity from a Generating Company or Distribution Licensee in case his plant is not in a position to generate electricity to meet the requirement in the event of emergency or shut down or maintenance of the plant including supply to township housing the operating staff:Provided that such purchase of electricity, from a Distribution Licensee of the area in which the plant is located, shall be charged under appropriate category of the rate schedule of tariff. This shall apply only to those generators who have entered into PPA with the Distribution Licensee:Provided also that in case of purchase of power for purposes other than mentioned above, the generator may purchase electricity through a trader or a Generating Company or a Distribution Licensee other than Distribution Licensee of the area in which the plant is located at the rate as mutually agreed however, surcharge and additional surcharge besides other charges shall be payable as determined by the Commission:Provided further that the tariff payable by a captive plant to a Distribution Licensee, in case of banking of energy, shall be as per Regulation 39(B), if that plant has an arrangement of banking of energy with such Distribution Licensee.20. Capacity of the Plant and Location.
21. Environmental Clearance.
- The Captive Generating Plant owner shall abide by the emission standards set by the Union/State Government. The Captive Generating Plant shall obtain all the required environmental and pollution clearances from the Central/State pollution control authorities and submit copies of clearance certificates to the Commission.Chapter 3
Non-Conventional Energy (Nce) Source Based Generation And Co-Generation
22. Object.
23. Generation from Non-Conventional Energy Sources.
24. General conditions for NCE source based Generation.
- These Regulations shall apply to:25. Capacity of NCE Generating Plants.
26. Environmental and other Clearances.
27. Obligations of NCE Generating Plants.
28. Duties of NCE source based Generating Plants.
29. Sale of Power.
30. Tariff.
- The tariff for supply of electricity by the plant to a Distribution Licensee shall be as per Schedule-II of these Regulations.Note. - (1) The tariff for supply of electricity from the plant, having more than one unit commissioned in different years, shall be based on weighted average of the contracted capacities of the units commissioned in different years.| PLF =| ES X 10000000CC X (100 - AUX) X 8760| % |