[Cites 0, Cited by 0] [Section 31] [Entire Act]

Union of India - Subsection

Section 31(6) in Central Electricity Regulatory Commission (Terms and Conditions of Tariff) Regulations, 2014

(6)In case the actual total energy generated by a hydro generating station during a year is less than the design energy for reasons beyond the control of the generating station, the following treatment shall be applied on a rolling basis on an application filed by the generating company:
(a)In case the energy shortfall occurs within ten years from the date of commercial operation of a generating station, the ECR for the year following the year of energy shortfall shall be computed based on the formula specified in clause (5) with the modification that the DE for the year shall be considered as equal to the actual energy generated during the year of the shortfall, till the energy charge shortfall of the previous year has been made up, after which normal ECR shall be applicable:
Provided that in case actual generation form a hydro generating station is less than the design energy for a continuous period of 4 years on account of hydrology factor, the generating station shall approach CEA with relevant hydrology data for revision of design energy of the station.
(b)In case the energy shortfall occurs after ten years from the date of commercial operation of a generating station, the following shall apply.
Explanation. - Suppose the specified annual design energy for the station is DE MWh, and the actual energy generated during the concerned (first) and the following (second) financial years is A1 and A2 MWh respectively, A1 being less than DE. Then, the design energy to be considered in the formula in clause (5) of these regulations for calculating the ECR for the third financial year shall be moderated as (A1 + A2 - DE) MWh, subject to a maximum of DE MWh and a minimum of A1 MWh.
(c)Actual energy generated (e.g. A1, A2) shall be arrived at by multiplying the net metered energy sent out from the station by 100 / (100 - AUX).