[Cites 0, Cited by 0] [Section 14] [Entire Act]

Union of India - Subsection

Section 14(3) in Central Electricity Regulatory Commission (Cross Border Trade of Electricity) Regulations, 2019

(3)In case of delay in commissioning of generating station or unit(s) thereof and associated dedicated transmission system in the neighbouring country beyond the scheduled date agreed in the Long Term Transmission Access Agreement, the generator shall be liable to pay full transmission charges from the date of operationalisation of long-term access.