Union of India - Section

Section 14 in Central Electricity Regulatory Commission (Cross Border Trade of Electricity) Regulations, 2019

14. Treatment of delay in Transmission system and Generation projects.

(1)Designated Authority shall monitor the progress of generating station including units thereof in neighbouring country along with transmission system for evacuation of power for cross border trade of electricity in consultation and co-ordination with CTU of India, Transmission Planning Agency(ies) of neighbouring country(ies) and the developer of the generating station, at regular interval.
(2)The generating company located in the neighbouring country, implementing agency(ies) and the transmission licensee(s) shall endeavour to commission the generating station, Cross Border Transmission Link(s) and the transmission system within India respectively in matching time-frame as far as practicable.
(3)In case of delay in commissioning of generating station or unit(s) thereof and associated dedicated transmission system in the neighbouring country beyond the scheduled date agreed in the Long Term Transmission Access Agreement, the generator shall be liable to pay full transmission charges from the date of operationalisation of long-term access.
(4)In case of delay in commissioning of Cross Border Transmission Link, compensation if any to the generating company or transmission licensee or both, as the case may be, shall be as decided by the respective Governments.
(5)In the event of delay by the transmission licensee in commissioning of transmission system within India beyond its scheduled date and the generating company is ready with its generating station or unit(s), the transmission licensee shall pay transmission charges to generating company proportionate to commissioned generation capacity in case no alternative arrangement is made by the CTU.Provided that in case of non-payment of transmission charges by the transmission licensee to the generating company, such charges shall be recovered by the CTU from the Contract Performance Guarantee furnished by the transmission licensee and paid to the generating company.