Section 5(2)(f) in Central Electricity Regulatory Commission (Deviation Settlement Mechanism and Related Matters) Regulations, 2014
(f)The charges for deviation in respect of an entity falling in different bid areas, shall be computed on the basis of the daily average ACP of the bid area in which such entity has largest proportion of its demand.]