State of Rajasthan - Subsection

Section 95(2) in Rajasthan Electricity Regulatory Commission (Terms and Conditions for Determination of Tariff) Regulations, 2009

(2)The investment plan shall be a least cost plan for undertaking investments on strengthening and augmentation of the intra-State transmission system for meeting the requirement of power evacuation, load growth, reduction in transmission losses, improvement in quality of supply, reliability, metering, etc.