Section 17(a) in Bihar Electricity Regulatory Commission (Standards of Performance of Distribution Licensee) Regulations, 2006

(a)On receipt of an application in the prescribed form for enhancement of the contract demand, the Licensee's engineer shall inspect the premises within seven (7) days of receipt of application and shall allow the enhancement of load within twenty (20) days if no extension and alteration of distribution network is required.