State of Rajasthan - Subsection
Section 4(7) in Rajasthan Electricity Regulatory Commission (Investment Approval) Regulations, 2006
| (a) | Distribution scheme | 1 year |
| (b) | Transmission scheme | 2 years |
| (c) | Generation scheme | 3 years. |