Section 17(3)(b) in Himachal Pradesh Electricity Regulatory Commission (Promotion of Generation from the Renewable Energy Sources and Terms and Conditions for Tariff Determination) Regulations, 2017
(b)in relation to the additional capacity of the project or a part thereof,(i) neither any synchronization of the same, with the Grid has taken place even once, nor (ii) any joint petition for approval of any PPA (or supplementary PPA), in relation for such additional/enhanced capacity, whether under REC mechanism or long term basis, has been filed before the Commission, nor (iii) any PPA, or supplementary PPA, for such additional/enhanced capacity has been signed by the developer of the concerned project with the distribution licensee for such additional/enhanced capacity;