Section 19(2) in Tamil Nadu Electricity Regulatory Commission Tamil Nadu Electricity Distribution Code
| (a) | Deviations in the system voltage or frequencyExceeding the set tolerance level | - Monthly |
| (b) | Major deviation in load drawals | - Monthly |
| (c) | Major breakdowns of lines/cables/equipments(Including any loss of capacity of 5 MVA and above) | |
| • Preliminary report followed by a detailedreport Indicating status, nature of break down, total Hours breakdown period, restoration period, and estimate of losses/ repairs,loss to persons /property, number of consumers affected etc. | - Within 24 | |
| (d) | Any other incident referred to in the Code | - Monthly |