State of Tamilnadu- Act
Tamil Nadu Electricity Regulatory Commission Tamil Nadu Electricity Distribution Code
TAMILNADU
India
India
Tamil Nadu Electricity Regulatory Commission Tamil Nadu Electricity Distribution Code
Rule TAMIL-NADU-ELECTRICITY-REGULATORY-COMMISSION-TAMIL-NADU-ELECTRICITY-DISTRIBUTION-CODE of 2004
- Published on 21 July 2004
- Commenced on 21 July 2004
- [This is the version of this document from 21 July 2004.]
- [Note: The original publication document is not available and this content could not be verified.]
Chapter 1
Preliminary
1. Short title and commencement.
2. The provisions of this Code shall come into effect on the [date of its publication in the Tamil Nadu Government Gazette] [Tamil Nadu Electricity Distribution Code has come into force from 1st September 2004.]
2. Definitions.
Chapter 2
Entities Pertaining to Distribution
3. Entities involved in distribution and their respective roles.
- The following are the entities involved in the distribution of electricity and their respective roles,Chapter 3
Distribution System Planning
4. Distribution System Planning.
5. Distribution Planning Framework.
| Sl.No. | Describition | Tasks & problems | Activities |
| 1 | Expansion planning | Local increase New transformer, substationsIntegration of peripheral -Networks Cable relaying Modernizationof substations Network coupling Power station extension *[upgradingthe voltage level] Network ocumentation Graphic InformationSystem | Network calculation forload flowandshort-circuit. Dynamic network Calculation. |
| 2 | Component design | Circuit-breaker stress cable cross sectionTransformer size Neutral earthing resistor | Stability Fault analysis Relay coordinationstudies |
| 3 | Operational problems | Substation faults Voltage quality HarmonicsEarthing problems Motor starting Power swings Frequency ofoccurrence of faults Fault tripping | Harmonics analysis Harmonics filter designEarthing measurement Network configuration Substation designEconomic analysis Relay selection **[provision of effectiveearthing' Insulation coordination |
6. Planning process.
- The system planning considerations are:Chapter 4
Connectivity Conditions
7. Connectivity Conditions.
- The Connectivity Conditions specify the minimum technical and design criteria, which shall be complied by any agency connected to, or seeking connection to the Distribution System. The Licensee shall ensure compliance of the above criteria by any agency as a pre-requisite for the establishment of an agreed connection. The terms and conditions of supply under Chapter 6 of this code shall be read in conjunction with this chapter. The connectivity conditions shall fulfill the requirement stipulated in section 50 and 53 of the Act. The Connectivity Conditions are provided to ensure that:8. Distribution System Interface with Small Generators.
- The electricity generated by the private developers pertaining to power projects based on [renewable] [Substituted for the expression 'non-conventional' as per Commission's Notification No.TNERC/DC/8-8dated 8.2.2008 (w.e.f 27.2.2008).] energy sources of wind, biomass etc or captive power plants shall be evacuated by interfacing with the distribution system or intra state grid. The voltage levels, connection points and connectivity conditions, safety etc., for such interfacing shall comply with the conditions laid down under Tamil Nadu Electricity Grid Code (TNEGC) and the regulations issued by the Authority in this regard.9. Distribution Systems protection arrangement.
10. Operational Labeling.
- The Licensee and the consumers shall be responsible for the provision and maintenance of clear, unambiguous signs and labels indicating the numbering and / or name of the equipment / apparatus and circuit at the substations and connection sites.11. Metering.
- [The minimum requirement of metering for substations in distribution system, Generating station and higher voltage consumer shall conform to the requirement stipulated in Tamil Nadu Electricity Grid Code (TNEGC)] [[Substituted as per Commission's Notification No. TNERC/DC/8-8 dated 8.2.2008 (w.e.f. 27.2.2008). Before substitution it read as under:'The minimum requirement of commercial and operational metering at distribution system substations and higher voltage consumer's sub stations shall conform to the requirement stipulated in Tamil Nadu Electricity Grid Code (TNEGC)']]12. Communication.
- Reliable communication links shall be established for the exchange of data, information and operating instructions between the Licensees, consumers with demand of 1 MW and above, the load control centers of the Distribution Licensee and the SLDC / SSLDC, as the case may be.13.
The Licensee shall monitor the voltage, frequency and power factor in the distribution system at different points, during the peak and off peak hours and take all reasonable measures for the improvement of the same, if it falls below the prescribed level continuously.14. [ Demand Side Management. [Substituted for the expression '13' i.e. renumbered as per Commisioin's Notification No. TNERC/DC/8 dated 8.2.2008(w.e.f.27.2.2008).]
- The Licensee shall make suitable provisions in the Service Connection Agreements to make it mandatory on the part of selected categories of consumers with a contracted Demand over and above a specified KVA limit (to be specified [by the Commission]) to carry out an Energy Audit at their establishment for in-plant load management and for carrying out end use energy efficiency / conservation measures. On their part, the Licensee shall provide such consumers with relevant information relating to energy audits and its methodologies and the financial incentives offered by recognized financial institutions, banks and other government organizations.]Chapter 5
Operation Guidelines for Distribution System
15.
The procedures and practices to be followed by the Licensees and consumers whose electric lines and electrical plants are connected to the Licensee's distribution system for safe and efficient operation of then-respective systems are -,16. Safety Aspects.
17.
Protective clauses as applicable to Railways, Highways, Airport, telegraphic signaling line etc., are as follows:18. Accident Reporting.
- Notice of accidents and inquiries as set out in section 161 of the Act reads as:"(1) If any accident occurs in connection with the generation, transmission, distribution, supply or use of electricity in or in connection with, any part of the electric lines or electrical plant of any person and the accident results or is likely to have resulted in loss of human or animal life or in any injury to a human being or an animal, such person shall give notice of the occurrence and of any such loss or injury actually caused by the accident, in such form and within such time as may be prescribed, to the Electrical Inspector or such other person as aforesaid and to such other authorities as the Appropriate Government may by general or special order, direct.19. Major Incident Reporting.
| (a) | Deviations in the system voltage or frequencyExceeding the set tolerance level | - Monthly |
| (b) | Major deviation in load drawals | - Monthly |
| (c) | Major breakdowns of lines/cables/equipments(Including any loss of capacity of 5 MVA and above) | |
| • Preliminary report followed by a detailedreport Indicating status, nature of break down, total Hours breakdown period, restoration period, and estimate of losses/ repairs,loss to persons /property, number of consumers affected etc. | - Within 24 | |
| (d) | Any other incident referred to in the Code | - Monthly |
20. Condition based monitoring/Preventive Maintenance programmes.
- shall be designed as follows:21. Tools, plants and Spares.
- The Licensee shall ensure availability of proper tools and plants and keep the work places in good condition for carrying out the required repairs/maintenance. Serviceability of tools and plants must be checked periodically and certified for their healthiness. The Licensee shall maintain an inventory of replacement spares required for maintenance purposes at suitable locations. A clear policy may be laid down by the Licensee in this regard and submitted to the Commission for reference.22. Training.
- The Licensee shall set up Training centers (or in coordination with the established Training centers) to impart proper and adequate training to its workmen and supervising staff in modern distribution practice, maintenance techniques and safety procedures. A syllabus suitable for the intended purpose shall be followed by them. The syllabus shall be submitted to the Commission for its perusal and approval.23. Research and Development.
- The STU shall, in consultation and approval of the Commission, carry out R&D to analyze and solve common operational and other problems related to distribution. Also they will be responsible for carrying out improvement and updation studies. The study results shall be properly communicated to all the distribution licensees for adoption. The expenditure towards the R&D work shall be met from a common fund for which the Commission shall prescribe the rate of contribution from each Licensee.Chapter 6
Terms and Conditions for Supply of Electricity
24. Terms and conditions for supply of Electricity.
- The terms and conditions for supply of electricity is meant to govern the supply of electricity and procedures thereof, including the powers, functions and obligations of the Licensee and the rights and obligations of the consumers and matters connected therewith and incidental thereto. The terms and conditions are not exhaustive as to the requirements to be complied with by Users connected or seeking connection to the Licensee's distribution system.25. System of Supply.
- The Licensee's declared voltage of supply will be generally as follows:26. Categories of Supply.
- Supply of electricity shall be made available to the consumer under the following categories:27. Requisitions for Supply of Energy.
28. Additional terms of supply as stipulated in section 48 of the Act reads as.
- "A distribution licensee may require any person who requires a supply of electricity in pursuance of section 43 to accept:29. Service Lines.
| Voltage level of the sub-station | Land Requirement in Sq.Mts. | |
| Normal sub-station | Compact sub-station | |
| 33 KV Sub-Station | 1520 (indoor) 3160 (outdoor) | 225 |
| 110 KV Sub-Station | 4000 (outdoor) | 1050 |
| 230 KV Sub-Station | 16000 (outdoor) | 7750 |
30. Consumer's installation.
| Nature of supply | Size of installation | Limit of maximum current demand |
| Single Phase | Up to 3 H.P | Full load current W 6 |
| Three Phase | i. Up to 3 HP | Full load current W 6 |
| ii. Above 3 HP and up to 15 HP | Full load current W 2 | |
| iii. Above 15 HP and up to 100 | HP Full load current W 1.5 | |
| iv. Above 100 HP | Full load current W 1.25 |
2. Providing of automatic switching facilities to the three phase motors with a direct on line starter is prohibited.
3. The use of phase shifters ( to operate the three phase motors during two phasing by the Licensee) in respect of Agricultural services by the consumers is prohibited.
Failure to restrict within these limits and also to comply with the above requirements will render the service connection liable for disconnection.31. Inspections, testing and effecting supply.
32. Licensee's supply mains and equipments.
33. Agreements.
34. Earnest money deposit.
35. Security deposit.
36. Access to premises, installations and equipments.
- The access to premises, installations and equipments is subject to the provisions envisaged under sections 163 of the Act, which reads as:37. Shifting of service connection.
38. Restrictions on use of electricity.
- The consumer shall curtail, stagger, restrict, regulate or altogether cease to use electricity when so directed by the Licensee, if the power position or any other emergency in the Licensee's power system or as per the directives of SLDC/ SSLDC warrants such a course of action. The Licensee shall not be responsible for any loss or inconvenience caused to the consumer as a result of such curtailment, staggering, restriction, regulation or cessation of use of electricity. Notwithstanding anything contained in any agreement/ undertaking executed by a consumer with the Licensee or in the tariff applicable to him, the consumer shall restrict the use of electricity in terms of his/her maximum demand and / or energy consumption in the manner and for the period as may be specified in any order that may be made by the Licensee on the instructions of State Government or the Commission.39. [ Temporary supply. [Substituted by Notification No. TNERC/DC/8-17, dated 06-09-2013.]
- Temporary supply of electricity to any premises shall be dealt with as below: -40. Energy conservation.
- Promoting efficient use of energy including energy audit towards this end and energy conservation by all the consumers and the Licensee shall be mandatory as per the provisions contained in the Energy Conservation Act 2001 subject to the condition that such stipulations are not inconsistent with the Electricity Act 2003.41. Service of notice.
- All letters, bills and notices including those under statutory requirements will be sent by the Licensee to the consumer by ordinary post or by messenger. Documents of notices so dispatched shall be presumed to have been duly received by the consumer on the date on which he could be reasonably expected to receive the same. The Licensee may, if it chooses, adopt any other mode of service of documents and notices to the consumer.42. [ Knowledge of Acts, Rules, Regulations, Orders, etc. [[Substituted by Commission's Notification No. TNERC/DC/8-8 dated 8.2.2008 (w.e.f. 27.2.2008) Before substitution it was as under:
42. Knowledge by facts, rules, orders, etc.: Subject to the provisions contained in Note 1 to sub-regulation(13) of regulation 29, the consumer will be deemed to have full knowledge of the provisions of 'applicable Acts, Rules and all regulations and notifications made there under. The consumer shall act in due conformity with all the applicable Acts, Rules and all regulations mentioned above and, if he does not so act, his/her supply may be discontinued without prejudice to any other action that may be taken by the Licensee.]]
- Subject to the provisions contained in the Note 1 to sub-regulation (13) of regulation 29, the consumer will be deemed to have full knowledge of the provisions of 'applicable Acts, Rules and all Regulations and Notifications' made there under. The consumer shall act in due conformity with all the applicable Acts, Rules and all Regulations and Notifications mentioned above.] [[Substituted as per Commission's No TNERC/DC/8-2 (1) dated, 14.06.2006 (w.e.f. 23.2.2006) which before substitution stood as under:Provided that the Chief Executive Officer of the Licensee may approve the point of supply at a place beyond30. meters from the main gate, if he is satisfied that such place is
43. Interpretation.
- These terms and conditions shall be read and construed as being subject in all respects to the provisions of the Act, Rules, and regulations in force and as amended from time to time.Chapter 7
Recovery Charges
44.
The Licensees are entitled to collect the charges from a person requiring supply of electricity any expenses reasonably incurred in providing any electrical line or electrical plant used for the purpose of giving that supply. These charges have also to be reviewed either periodically or at times of an urgent need for a revision. The consumers are liable to pay such charges as applicable and at the rates specified by the Commission from time to time through separate orders/ notifications. The various charges to be collected are furnished in the following clauses.45. Service Connection Charges.
46. Meter Security Deposit.
- The Licensee is authorized to collect security for the price of meter from LT/FIT consumers at the rates specified by the Commission from time to time and enter into an agreement for hiring of the meter. The Licensee may permit the consumer to install his/her own meter. However, it shall be calibrated by the Licensee.Note: - 1. The above rate shall also apply to L.T. Temporary Supply.2. Interest is payable on the above deposit at the rate specified by the Commission from time to time. The deposit shall be refunded after termination of service agreement, as per rules.
3. If a consumer elects to purchase his own meter, he is not required to pay Meter Security Deposit.
47. Development Charges.
- The Licensee is authorized to collect development charges from LT/HT consumers at the rates specified by the Commission from time to time.Note: - (1) The above development charges (one time payment) shall be collected from all applicants both for new and additional loads.48. Earnest Money Deposit (EMD).
- The Licensee is authorized to collect Earnest Money Deposit from all applicants for HT and LT industrial applicants at the rates specified by the Commission from time to time. This will be adjusted against the quantum of initial Security Deposit payable by the applicants before availing supply.49. Security Deposit.
- The Licensee is authorized to collect initial security deposit at the rates specified by the Commission from time to time. Wherever Earned Money Deposit has been adjusted against the initial security deposit the balance if any will be collected from the applicants before giving supply.50. Code to be read along with Supply Code, Electricity Act 2003 and amendments etc.
Chapter 8
Code Review Panel
51. Appointment of Code Review Panel etc.
- [(1) The Commission may appoint a Code Review Panel (hereafter in this Chapter referred to as "Panel") consisting of -(a)A Chairperson at the level of Director of the Distribution Licensee.(b)A Member Secretary, who shall be the Chief Engineer/Commercial of the Distribution Licensee.(c)One Member from the SLDC who is not below the rank of Chief Engineer.(d)Three representatives from the Distribution Licensee who are not below the rank of Chief Engineer and one representative from the Distribution Licensee who is not below the rank of Chief Financial Controller.(e)One representative from LT domestic consumer sector, one from LT commercial sector, one from LT industry sector and one from LT agricultural consumer sector.(f)One member representing the EHT / HT consumers.(g)One member representing open access consumers.1. Type of Load
2. Minimum Demand (KVA)
3. Year/Years by which full / part supply is required
4. Load location details
5. Rated Voltage and Frequency
6. Expected load curve
7. Withstand level of equipments/devices for the fluctuations, surges, swells, flickers and spikes
8. Characteristics of the loads (State whether the loads are steel melting furnace Arc/induction furnace and rolling mills, traction, containing welding sets in large numbers, software, park, etc)
(Furnish location map to scale, indicate details of nearest consumer and category / capacity)i. Motors ( with a specific focus on variable speed motors; soft start motors; fans; Blowers etc.) (State purpose and number of Installations, voltage and KW rating, starting current, type of Motors, types of drives and control arrangements.)ii. Heating (Type and KW rating)iii. Furnace (Type, Furnace Transformer Capacity and voltage ratio)iv. Computer, Inverters, UPS and other switched mode supply unitv. Electrolysis (Purpose, kVA capacity)vi. Lighting (types of lighting used) (Low loss energy conservation lamps, fluorescent Lamps, M.V Lamps, Sodium Vapour lamps) demand in kVAvii. P.F improvement capacitors/ Capacitor Banks (Nos, Capacity in MVAR)viii. Air conditioning / Chilling plantix. Electronic Regulator for fanx. Phase unbalance imposed on system9. Maximum harmonic content imposed on the supply system on the end consumer level in percentage of fundamental voltage/current.
10. Details of any loads, which may cause demand fluctuations of greater than 10 MW at the point of connection, including Voltage Dips (percentage) lasting for 5 seconds and more
MVAR/KVMW/HzMVAR/Hz(Furnish details of devices included in system for the suppression of harmonics i.e. the details of harmonic filter in use.)11. Details of Captive Power Plants:
Annexure IISystem Data to Be Provided to the Intending, Consumep With A Contracted Demand of 1 MW or More (Refer clause 6(3))1. A topographical map indicating the area of the licensee's supply network in the State of Tamil Nadu.
2. Single line diagram of distribution system (OH lines / UG cables -length and conductor sizes) Primary and secondary substation capacity in KVA, capacitor bank sizes, fault level etc. to be indicated, (restricted area of concern for the prospective consumers)
3. Protective relaying and metering arrangements at substations
4. Details of the substation and its main equipments (Transmission/Sub Transmission) along with a single line diagram of the SS.
Furnish the details of Auto/Power Transformer| Capacity in MVA | Primary KV |
| Voltage rating | Secondary KV |
| Current rating | Primary Amps |
| Secondary Amps | |
| Tap changing | off load / on load |
| Range | ..% to +...% |
| Percentage impedance | ....percent |
| Vector group | .... |
| Impulse level (BIL) | .....KVP |
| Fault level of the system | ..... MVA |
| Earthing system | solidly earthed or not |
| Power frequency voltage | ..KV for one minute withstand |
| Circuit breakers | Type: Vacuum/SF6/Oil (OMCB,OCB) |
| Current rating | |
| Voltage rating | |
| Rupturing capacity in (KA) | |
| Symmetrical Asymmetrical | |
| Impulse withstand level KVP | |
| Operating mechanism | |
| Surge arrester | (Gapless) - MCOV |
| Surge current rating | |
| (Gapped) - rated voltage | |
| Surge current rating | |
| Provision of spiked Mats for the Power/ AutoTransformer | |
| Ground wire for the station | |
| Line entrance Arrester | |
| Earth mat | |
| Current Transformer | Type: Rated voltage |
| Current ratio | |
| Potential Transformer | Type: Rated voltage |
| Burden | |
| Capacitor Bank | MVAR/Bank |
| Voltage rating ...KV | |
| Current rating ...Amp | |
| Fire fighting equipment | Type - Nos |
| (Details) |
| FORM 1 | Application Form for L.T. Service Connection(except agriculture and hut) |
| FORM 2 | Application Form for Agriculture ServiceConnection |
| FORM 3 | Application Form for Hut Service Connection |
| FORM 4 | Application Form for H.T. Service Connections(including additional demand) |
| FORM 5 | Owner Consent Letter for getting New Supply |
| FORM 6 | Indemnity Bond from the Occupier when there isno Consent letter from owner |
| FORM 7 | L.T. Agreement for Industrial / AgriculturalServices |
| FORM 8 | H.T. Agreement Form |
1. I hereby require you to supply electrical energy to the premises hereinafter described.
(Note this undertaking does not preclude a separate written contract being entered into, if so desired by the Licensee or the consumer.)2. I agree to pay for said energy, service connection and other dues including the deposit of such security, meter rent, as may be demanded in accordance with the scale of rates prescribed under Tamil Nadu Electricity Distribution Code, Supply Code, notifications and orders issued in this regard by Tamil Nadu Electricity Regulatory Commission.
3. I wish to be charged under Tariff........... under schedule of the TNERC tariff order dated.
4. 1 agree to take supply for............years and utilize the energy in the premises described hereunder or outside the premises for my bonafide use.
5. In case I sell or otherwise dispose of the property / vacate the premises while the supply is continued, I agree to give one Calendar month notice in writing and pay all the arrears to the Licensee. Failing such notice, I hold myself responsible for energy consumed in the premises till such notice is given to the Licensee.
6. Description of the premises
Door No. and / or name of the house or premisesStreetTown / village and TalukOwned by (Name in Block letters)Tenanted by (Name in block letters)Applicant's correspondence address7. The following are my requirements:
| (A) | Lighting | Number of point's | Wattage of point's | Total wattage |
| (i) Lights | - | - | - | |
| (ii) Fans | - | - | - | |
| (iii) Convenient wall plugs | - | - | - | |
| (B) | Domestic electrical apparatus: | |||
| (i) Cookers | ||||
| (ii) Water heaters | ||||
| (iii) Refrigerator | ||||
| (iv) Air Conditioners | ||||
| (v) Other purpose | ||||
| (vi) Convenience wall plugs | ||||
| (C) | Power Loads | |||
| (i) Domestic | ||||
| (ii) Industrial | ||||
| (iii) Welding | ||||
| (iv) Other purposes | ||||
| (v) Convenient Wall Plugs |
| Place: | Signature of the Consumer |
| Date: |
2. Additions or omissions to the connected load to be notified to the Licensee before effecting the electricity connections.
Precaution to be Adopted by Consumers, Owners Electrical Contractors, Electrical Workmen, and other Suppliers of EnergyNo electrical installation work, including additions, alterations, repairs and adjustments to existing installations except such replacement of lamps, fans, fuses, switches and other component parts of the installations as in no way alter its capacity or character shall be carried out upon the premises or on behalf of any consumer or owner for the purpose of the supply of energy to such consumer or owner, except by an authorized person specified by the Authority.Form-2Application Form For Agriculture Service Connection(refer clause 27(2)Application For Supply of Power To Agricultural Pump Sets(Note: The application should be signed by the owner of the well, if there are partners, all must sign or consent to be given by co-owners)ToThe Designated Engineer,(Address of the Licensee's Distribution Centre)1. Name of owner of the well or partners
2. Full residential address of the owner or partners
3. S.F. No. in which the well is situated
4. Revenue village name,Taluk and District
5. Area and type of land to be irrigated by this well (Wet / Dry)
6. Horse Power of motor pump sets proposed to be installed.
7. Type of pump set (Centrifugal/ Submersible/ Air compressor)
8. Consent to abide by R&C of Licensee with regard to duration of supply
It is certified, I am the sole owner of the well / this application is signed by all partners| Place:Date: | Signature of the Applicant/Partners |
1. I hereby request you to supply electrical energy to my hut described below:
2. I agree to pay for energy, service connection meter rent and other charges including security deposit as demanded in accordance with the regulations prescribed by Tamil Nadu Electricity Regulatory Commission.
3. I wish to be charged under Tariff ............... under schedule of the TNERC tariff order dated.
4. I agree to receive supply only for 40 W lamp and utilize the energy for my hut described hereunder and I agree that the authorities may disconnect the service connection in case I utilise the energy above 40 W.
5. In case I sell or otherwise dispose of the hut, I agree to give one Calendar month notice in writing and pay all the arrears to the Licensee.
6. I will make arrangements to make the single point wiring for lighting in my hut in accordance with the Code provisions and the safety rules prescribed by the Authority . I request the Licensee to provide single point wiring for lighting in my hut and the necessary payment will be made by me.
7. Self Declaration
The service connection applied for the hut is owned by me and(a)it is built in my patta land (Land Tax Receipt is enclosed)(b)it is built in the private land and No Objection Certificate obtained from the landowner is enclosed.(c)it is built in the poromboke land and No Objection Certificate obtained from the Officer (not below the rank of Deputy Tahsildar) is enclosed.(d)[ It is built in the poromboke land and I furnish the following undertaking, - [Inserted by Commission's Notification No. TNERC/DC/8-3 dated 31/05/2006 (w.e.f.21.6.2006).]8. Description of the premises
1. Name of Electricity supply Licensee and registered address:
2. Name of consumer and registered address
3. Address of consumer's premises at which supply is required
4. Nature of service
5. Voltage rating at which H.T. supply is required.
6. Data on consumers load
| Notified connected load in H.P. | |
| Description | |
| As on date | |
| Subsequent additional sanction | |
| Estimated requirement now applied | |
| Total | |
| Brief details of industry to be served | |
| No. of shifts | |
| Probable date of load maturing | |
| Remark if any regarding essentiality of supply |
7. Data to be furnished by Licensee
| Estimated increase in M.D. of theundertaking ifany, the application is recommended | Capacity of existing services if any | Nature of supply DC/AC voltage or low voltageetc. | Brief list of materials required i.e. cabletransformer switch gear etc. | Approximate cost of giving service | Any other remarks affecting the supplyundertaking with particular ref. to plant site location ofconsumer installation |
| Materials in stock | Materials to be ordered | ||||
| 1 | 2 | 3 | 4 | 5 | 5 |
8. Information regarding priority whether there is any prior H.T. applications in the connected area awaiting supply of power
Note: For the purpose of priority, the area served by the sub-station feeder will be taken into account.Signature of Licensee's EngineerForm 5Owner Consent Letter For Getting New Supply.(Refer clause 27(4)ToThe Designated Engineer(Address of the Licensee)Owner's Consent LetterI.............................have...................being the legal owner...................of the premises No............................. hereby agree as follows-I consent to the installation by you at the above mentioned premises tenanted by Thiru / Thirumathy.................................of electric service cables, meters, wiring, fittings and other equipments for the supply of electricity (hereinafter called "The Installation") under the terms of an agreement between you and the tenant of the above said premises.In the event of the above said tenant vacating the aforesaid premises, I shall give you due notice fifteen days advance to enable you to arrange for the termination of your contract with the aforesaid tenant failing which I shall be responsible for any loss that may accrue on that account.Signed by the said...................................the presence of ................Witness Name............................Address.................................Form 6(To be obtained in a stamped paper).(Refer clause 27(4)Indemnity Bond from the occupier when there is no consent letter from owner.Indemnity Bond to be furnished by an intending consumer who is not the owner of the premises and applies without the consent of the owner.Deed of IndemnityThis Deed of Indemnity Executed on This, The ................Day of .............. Two Thousand by Thiru/Tmt .......................... S/o. D/o W/o..................................... residing at ............ having office / workshop at .................. hereinafter called the indemnifier (which terms shall mean and include executors, administrators, heirs, successors and assigns) to and in favour of the (name of Licensee and address), a body corporate, hereinafter called the Licensee (which terms shall mean and include its successors in office and assigns).Whereas the consumer has taken on lease the premises in Door No...........for the purpose of.........................from Thiru/Tmty......................S/o D/oW/o...................residing at.................who is the owner of the above said premises.And Whereas the consumer has approached the said owner of the premises to give his /her consent in writing to avail of a service connection in his/her name for the purpose of his / her business.And Whereas the said owner is not available/has refused to give his/her consent in writing for the purpose.And Whereas the indemnifier has requested the Licensee to give a service connection in his/her name subject to execution of an indemnity bond by him/her indemnifying the Licensee against any damage or loss caused to the Licensee in respect of the service connection in his/her name.And Whereas in consideration of the acceptance of the above for a service connection in his/her name, the indemnifier hereby agrees to indemnify the Licensee against all proceedings, claims, demands, costs, damages, expenses which the Licensee may incur by reason of a fresh service connection given to the indemnifier without the consent of the owner of the premises. The indemnifier further undertakes to make good any sum that may be found to be and become payable to the Licensee with regard to all liabilities and claims personally as well as by means of both movable and immovable properties. The indemnifier agrees 'that the enhanced Security Deposit paid by him shall be adjusted against the arrears of current consumption charges but also against any claim that may arise in the event of termination of the agreement prior to the expiry of the contracted period. The indemnifier further undertakes that the Licensee shall be at liberty to disconnect the service connection given to him/her and also for loading the dues remaining unpaid by him/her to other service connection (s) that may stand in his/her name.Now the Condition of the above written bond is such that if the indemnifier shall duly and faithfully observe and perform the above said conditions, then the above written bond shall be void, otherwise the same shall remain in full force.In Witness Where of Thiru/ Tmt....................................the indemnifier has signed this deed on the day month and year herein before first mentioned.Signed and Delivered ByIn the presence ofWitness (Name and Address)-1. ......................................................
2. ......................................................
Form 7L.T. Agreement For Industrial / Agricultural Services(Refer clause 33(1)(Licensee Name)L.T. Agreement Form1. Conditions of Supply. - The Licensee shall furnish to the Consumer and the Consumer shall accept at the premises mentioned in the Schedule hereto on and from the date on which the said premises shall be connected with the Licensee's distributing main a constant supply of electrical energy for the purpose and up to the maximum specified and under the conditions laid down in the Distribution and Supply Code. But the Licensee or its employees, servants or agents will not be responsible for any interruption or diminution of the supply due to lockouts, strikes of the employees of the Licensee, breakdown of machinery or plant, flood or other force majeure or any other cause beyond the control of the Licensee.
The conditions if any imposed by the licensee based on the directions of the Commission shall bind the consumer.The Consumers shall commence to take supply within a month from the date of receipt of intimation from the officers of the Licensee that supply is available unless the consumer, in the opinion of the Engineer, is unable to do so for causes reasonably beyond control. Where the supply is not availed of within one month from the date of intimation as aforementioned, the sanction for the load shall lapse and this agreement also shall stand cancelled.[***] [[Words 'The energy shall be utilized within the premises mentioned in the schedule hereto or outside the premises for the bonafide use of the Consumer. In case of difference of opinion as to whether any utilisation of energy outside the premises is for the bonafide use of the consumer, the matter shall be referred to the Engineer,whose decision shall be final.' omitted by Notification No. TNERC/DC/8-19, dated 01-07-2014.]]The consumer shall permit the Licensee free of cost to erect the posts, transmission line, structures and other apparatus necessary for the supply of electrical energy under this agreement over the land belonging to the Consumer and the Consumer shall have no claim whatsoever on account of any damage to his/her, property by reason of such erection of, or any other work on the posts transmission lines, structures and other apparatus.The Consumer agrees to take supply under any conditions of restrictions of load and time that may be fixed by the Licensee from time to time and to pay the minimum under this agreement in full notwithstanding such restrictions.Supply is liable to be restricted, staggered or cut off altogether, as the case may be, if the power position or any other emergency warrants such a course of action.Tire Licensee reserves the right to periodical shut down as and when required for purposes of routine maintenance after giving reasonable notice to the Consumer.2. Payment For Service Lines Etc., - The consumer shall pay to the Licensee on demand the cost of any service lines in respect of which requisition has been made.
3. Meters. - The supply shall be measured and registered by a meter or meters in or upon the said premises to be provided, fixed and kept in proper order by the Licensee and such meter or meters shall remain the property of the Licensee. The consumer shall pay to the Licensee for each meter on hire the monthly rent as specified by the Commission from time to time. [In the event of any meter ceasing to register or being found defective, the consumption during the period of such cessation or the existence of such defect shall be based on the average consumption of the preceding or succeeding four months, as the case may be as stipulated in the supply code.] [[Substituted by Commission's Notification No. TNERC/DC/8-8 dated 8.2.2008 (w.e.f.27.2.2008) before substitution it reads as under:
'In the event of any meter ceasing to register or being found defective, the readings during the pei iod of such cessation or the power consumed during the period the meter was defective shall be based on the average consumption of the previous four months.']] No meter rent shall be collected from the consumer who opts for providing his/her own meter.4. Reading of Meters. - Readings of the meter or meters will be taken by the employees of the Licensee once in each month or at such other intervals or times, as it shall think expedient and such meter readers shall have access to the Consumer's premises at all reasonable times, for the purpose of taking such readings.
[The reading of each meter shall be entered by such reader in the Meter Card supplied to the consumer, which shall be open to the inspection of the Consumer] [[Substituted as per Commission's Notification No. TNERC/DC/8-8 dated 8.2.2008 (w.e.f.27.2.2008) before substitution it was as under:'The reading of each meter shall be entered by such reader in the consumer meter card to be attached to such meter, which shall be open to the inspection of the Consumer.']]. Payment for energy supplied shall be made by the consumer according to the reading referred to above of each meter and the charges recorded in the card by the Licensee.The Licensee shall be entitled to discontinue supply if the consumer fails to give the employees of the Licensee reasonable facilities to enter the premises for the inspection, testing or removal of its supply lines meters, fitting works and apparatus and the Licensee has given in writing 24 hours notice of its intention so to discontinue.5. Faults In Meters. - If the consumer shall at any time consider that any such meter is not in proper order and does not correctly register the quantity of the supply, the Engineer will on receipt of a representation in writing in that behalf from the consumer take necessary steps to have the same tested. If upon such test, it be found that the meter registers the supply within the limits of error as per applicable rules etc., the Consumer shall pay to the Licensee on demand all costs of and incidental to such test. If, however, upon such test it shall be found that the meter registers the supply in-excess of the limits of error, all costs of and incidental to such test shall be borne by the Licensee. If, however, the mean error be found to be more than that specified above, the Engineer will deduct from or add to the account for the preceding period of four months an amount equivalent to the error.
[6. Tariff and Payment. - For all Electrical energy so supplied, the Consumer shall pay to the Licensee at the tariff/minimum rates that may be decided by the Commission from time to time] [[Substituted by Commission's Notification No. TNERC/DC/8-8 dated 8.2.2008 (w.e.f. 27.2.2008) before substitution stood as under:6.
Tar1ff And Payment:'For all Electrical energy so supplied, the Consumer shall pay to the Licensee at the rates given below and in accordance with the terms contained, in this agreement, provided that the minimum rates at least specified herein shall be paid irrespective of whether energy to that extent has been consumed or not.'NOTE: The above tariff and the minimum are subject to any revision and or levy of surcharge that may be decided by the Commission from time to time.]]7. Consequences of Non-Payment. - If the amount of such bill remains unpaid on the expiry of the due date the Licensee may give the consumers [Fifteen days Notice] [Substituted for the expression 'Fifteen Notice' by Commission's Notification No. TNERC/DC/8-8 dated 8.2.2008 (w.e.f. 27.2.2008).] of his/her intention to discontinue the supply of electrical energy and at the expiry of such period if payment has not been received, may forthwith disconnect the supply and keep the same disconnected until payment of all moneys due under this agreement and the charges for the work of disconnection and reconnection has been made.
If the consumer fails to pay the amount of such bill due under this agreement within the notice period for payment as per the supply code, he shall in addition and without prejudice to the other rights and remedies of the Licensee, pay a surcharge of one and half percent per month.Such disconnection of the supply of electrical energy shall not relieve the Consumer of his/her liability to pay the minimum charge and the guaranteed revenue provided for herein, nor shall it affect any right, claim demand or power which may have accrued to the Licensee hereunder.8. Security Deposit. - [***] [The consumer The word 'shall' omitted by Commission's Notification No. TNERC/DC/8-8 dated 8.2.2008 (w.e.f. 27.2.2008).] on being there unto required in writing by the [Licensee shall] [Substituted for the expression 'Licensee' by Commission's Notification No. TNERC/DC/8-8 dated 8.2.2008 (w.e.f. 27.2.2008)] deposit with the designated Officer of the Licensee the sum of Rs......(Rupees as security for the purpose next herein after mentioned and shall on a similar requisition from the Designated Officer from time to time renew or replenish such security in the event of the same becoming exhausted or insufficient. Interest shall be paid on deposits at the [rates] [Substituted for the expression 'rate of' as per Commission's Notification No. TNERC/DC/8-8 dated 8.2.2008 (w.e.f. 27.2.2008).] notified by the Commission from time to time. Full calendar months shall be taken for the purpose of calculating interest, which shall be calculated to the nearest rupee. The interest accruing to the credit, of the Consumer shall be adjusted as provided for in the supply code. The designated Officer, shall be at liberty at any time and from time to time to appropriate and [adjust] [Substituted for the expression 'apply' as per Commission's Notification No. TNERC/DC/8-8 dated 8.2.2008 (w.e.f 27.2.2008)] the Security so deposited as aforesaid in or towards payment or satisfaction of all or any money which shall become due or owing by the Consumer to the Licensee in respect of the supply of energy or otherwise under this agreement but the provisions contained in this clause shall not prejudice any other remedy to which the Licensee may be entitled for the recovery of such money.
9. Termination of Agreement. - The agreement can be terminated by the consumer at any time by giving one-month notice in writing to the Licensee expressing his intension to do so. In such case the consumer shall pay to the licensee, from the date commencement of supply till the agreement is terminated, [***] [Words 'security deposit' omitted as per Commission's Notification No. TNERC/DC/8-8 dated 8.2.2008 (w.e.f. 27.2.2008)], minimum monthly charges, fixed charges, if any and other charges. The Licensee can terminate agreement at any time by giving one month notice if the consumer has violated the terms of the agreement or the terms and conditions of the Distribution Code or provision of any law relating to the agreement including the applicable Acts and Rules and other orders [issued by the Commission from time to time] [Inserted as per Commission's Notification No. TNERC/DC/8-8 dated 8.2.2008 (w.e.f. 27.2.2008).]. The Licensee shall inform the consumers the grounds for such termination:
Provided always the consumer may at any time with the previous consent of the Engineer transfer his rights under this agreement to any other person approved by the Engineer and upon acceptance by such transferee of a valid assignment of these presents, this agreement shall become binding on the transferee and licensee as from date of acceptance and take effect in all respect as if the transferee had originally been [party] [Substituted for the expression 'partly' as per Commission's Notification No. TNERC/D/8-8 dated 8.2.2008 (w.e.f. 27.2.2008).] hereto, in place of the [consumer] [Substituted for the expression 'customer' by Commission's Notification No. TNERC/DC/8-8 dated 8.2.2008 (w.e.f 27.2.2008).], who shall thenceforth be discharged from any further liabilities under or in respect hereof, without prejudice, however, to any claim by the licensee against the consumer in respect of any prior breach of this agreement by the consumer.10. Sale or Transfer of Premises. - If the consumer shall, at any time during the continuance of this agreement intend to sell or otherwise dispose of the properties to vacate the premises to which electric supply is given or contracted for, he shall give [prior] [The word 'previous' omitted by Commission's Notification No.TNERC/DC/8-8 dated 8.2.2008 (w.e.f. 27.2.2008).] intimation to Engineer of his intention to do so and clear off all the dues to the Licensee up to that date. Upon receipt of such intimation and with effect from the date specified in such intimation the agreement in so far as the consumer is concerned shall cease to operate but without prejudice to any claim or right which may have accrued to the parties there under.
If the consumer fails to give intimation as mentioned above he shall continue to be liable to pay the charges for consumption and other charges as under this agreement even beyond the date on which the premises is sold / vacated.11. Applicability of Acts and Regulations. - This agreement shall be read and construed as subject in all respects to the provision of the applicable Act and Regulations as noted in Distribution Code and Supply Code and of any modification or re-enactment thereof for the time being in force and the regulations for the time being in force there under so far as the same respectively may be applicable and subject to the conditions of supply approved from time to time [by the Commission] [Inserted by Commission's Notification No.TNERC/DC/8-8 dated 8.2.2008 (w.e.f. 27.2.2008).].
12. Savings As To Clerical Error - (a) In the event of any clerical errors or mistakes in the amount levied, demanded or charged by the Licensee then in the case of undercharging, the Licensee shall have a right to demand an additional amount and in the case of over charging the consumer shall have the right to get refund of the excess amount provided at that time such claims were not barred by limitation under the Act.
[***] [The word 'provision' omitted by Commission's Notification No. TNERC/DC/8-8 dated 8.2.2008 (w.e.f. 27.2.2008)]13. General. - The other conditions of supply in this agreement are also subject to any revision that may be decided by the Licensee as per the directions of the Commission from time to time.
Description of the Premises at which Supply is to be given[l. (a) District [Substituted by Commission's Notification No. TNERC/D/8-8 dated 8.2.2008 (w.e.f. 27.2.2008).](b)Taluk.(c)Town/Village(d)Door No./Survey No./ Street(e)Street name / area1.
2.
[***] [The words 'Postal Address' omitted as per Commission's Notification No. TNERC/DC/8-8 dated 8.2.2008(w.e.f. 27.2.2008)]Signature of the ConsumerForm 8H.T. Agreement Form(Refer clause 33(1)This Agreement made this .................................... day of .............................. between. (Name of the Licensee) a body corporate for distribution of electricity in the area, called Licensee (which expression shall include its legal representatives and assigns) of the one partAnd ...................................................... hereinafter called the 'consumer' (which expression shall include its successors, legal representatives and assigns) of the other part.Whereas the consumer has requested the Licensee to supply electrical energy for a maximum demand of ........... KVA at H.T. / E.H.T. for the purpose of light and power and the Licensee has agreed to afford such supply to the consumer in Ref. No...........on the terms and conditions of the Distribution Code, Supply Code and Grid Code wherever applicable and those hereinafter contained and whereas the consumer availed the supply on......Whereas an additional load of................................KVA was sanctioned to the consumer in Ref. No. .......................totaling in all to a Maximum demand of...................KVA.Whereas the consumer has on..........................given an under-taking to execute an agreement with the Licensee. Now it is hereby declared and agreed as follows:1. Load Maximum Demand. - Subject to the provisions hereinafter contained, the Licensee shall supply and the consumer shall take from the Licensee electrical energy for a maximum demand not exceeding......................KVA which shall be its contracted demand for its exclusive use for the purpose above mentioned at the premises of its Factory/ Mills, at........................
The connected load shall be..............KVA / KW / HP............The consumer shall not effect any change in the maximum demand or connected load.2. Date of coming into force of the agreement - The Consumer shall begin to take electrical energy from the Licensee subject to the conditions of this agreement within three months from the date on which intimation is sent in writing to the consumer by the Licensee that supply of electrical energy is available. The provisions of this agreement shall be deemed to come into force from the date of commencement of supply of energy or the date of issue of first three month's notice of availability of supply whichever is earlier. [If the consumer fails to avail the supply within 3 months, a further three months extension will be granted by the Licensee, after collecting the monthly minimum for the extended period in advance. [Inserted by Commission's Notification No.TNERC/DC/8-8 dated 8.2.2008 (w.e.f.27.2.2008).]
If the intending consumer fails to avail the supply, within the notice period or within the extended period granted thereof, the application will be treated as cancelled and the agreement will be terminated forfeiting all the amount paid by the consumer except meter security deposit as per the provisions of the Distribution Code]3. Resale of Energy. - The consumer shall not sell the electrical energy obtained under this agreement without the sanction in writing of the Licensee.
4. To comply with requirements of Act and Terms and Conditions of Distribution Code and Supply Code. - The consumer hereby undertakes to comply with all the requirements of the applicable Acts, Regulations etc, and Grid code, Distribution code and Supply Code and of any amendments, modifications or reenactment thereof or of any other enactment to be passed in relation to supply made under this agreement from time to time and the rules, regulations or orders etc. made thereunder from time to time, provisions of the Tariffs, Scale of Miscellaneous and other charges and the terms and conditions of supply prescribed from time to time, and the consumer hereby agrees not to dispute their applicability to this agreement.
5. Design and Maintenance of equipment of consumer. - All transformers switchgear and other electrical equipment belonging to the consumer and directly connected to the feeders or lines of the Licensee shall be of suitable Design and be maintained to the reasonable satisfaction of the Engineer/ .......... The ratings of the fuses and setting of the relays on the consumer's control gear as well as the rupturing capacities of the consumer's circuit breakers, if any, shall be subject to the approval of the said Engineer.
6. Obligation of consumer to pay all charges levied by Licensee. - From the date this agreement comes into force the consumer shall be bound by and shall pay the Licensee, maximum demand charges, energy charges, surcharges, meter rents and other charges, if any, in accordance with the tariffs applicable and the terms and conditions of supply notified from time to time for the appropriate class of consumers to [which such consumer belongs] [Substituted for 'which it belongs' by Commission's Notification No. TNERC/B dated 8.2.2008 (w.e.f.27.2.2008).].
7. Licensee's right to vary terms of agreement.- The consumer agrees that the Licensee shall have the right to vary, from time to time, tariffs, general and miscellaneous charges and the terms and conditions of supply under the directions / regulations or by special or general proceedings of Tamil Nadu Electricity Regulatory Commission. The consumer, in particular, agrees that the Licensee shall have the right to enhance the rates etc. chargeable for supply of electricity according to exigencies again with the approval of Tamil Nadu Electricity Regulatory Commission. It is also open to Licensee to restrict or impose power cuts totally or partially at any time as it deems fit.
8. Minimum Monthly Charges. - The consumer agrees to pay minimum charges every month as prescribed in the tariff and supply code even if no electricity is consumed for any reasons whatsoever, and also if the charges for electricity actually consumed are less than the minimum charges. The minimum shall be payable even if electricity is not consumed because of disconnection of supply by the Licensee due to non-payment of electricity charges, pilferage or other mal-practices or for any other valid reason.
9. Surcharge. - The tariffs charged by the Licensee are subject to any surcharge that may be levied by the Licensee from time to time as per approval of the Commission.
10. Period of Agreement. - This agreement shall remain in force till it is terminated by either party as provided in Distribution code and Supply code
In Witness Where of Thiru .................... Engineer,............. acting for and on behalf of the Licensee and Thiru.....................for and on behalf of the consumer have hereunto set their signatures, and the common seal of M/s................has hereunto been affixed.[Signed in the presence of Engineer1.
2.
The common seal ofM/s...................Partner Managing DirectorWitnesses with Address:1.
2.
]Abbreviations| 1. | AC | - Alternating Current |
| 2. | CERC | - Central Electricity Regulatory Commission |
| 3. | CMDA | - Chennai Metropolitan Development Authority |
| 4. | DC | - Direct Current |
| 5. | FMB | - Field Measurement Book |
| 6. | HP | - Horse Power |
| 7. | HV | - High Voltage |
| 8. | HZ | - Hertz |
| 9 | KVA | - Kilo Volts Ampere |
| 10. | KVP | - Kilo Volt Peak |
| 11. | KW | - Kilo Watt |
| 12. | LV | - Low Voltage |
| 13. | MCOV | - Maximum Continuous Operating Voltage |
| 14. | MV | - Medium Voltage |
| 15. | MVA | - Mega Volt Ampere |
| 16. | MVAR | - Mega Volt Ampere Reactive |
| 17. | MW | - Mega Watt |
| 18. | OCB | - Oil Circuit Breaker |
| 19. | OMCB | - Oil Minimum Circuit Breaker |
| 20. | OH | - Overhead |
| 21. | R & C | - Restriction and Control |
| 22. | RCC | - Reinforced Cement Concrete |
| 23. | R&D | - Research and Development |
| 24. | SC | - Service Connection |
| 25. | SLDC | - State Load Dispatch Centre |
| 26. | SS | - Sub-station |
| 27. | UG | - Underground |
| 28. | UF | - Under Frequency |
| 29 | UPS | - Uninterrupted Power Supply |
| 30. | VAR | - Volt Ampere Reactive |