Union of India - Subsection

Section 6(5) in Central Electricity Regulatory Commission (Terms and Conditions of Tariff) Regulations, 2014

(5)Where only a part of the generation capacity of a generating station is tied up for supplying power to the beneficiaries through long term power purchase agreement and the balance part of the generation capacity have not been tied up for supplying power to the beneficiaries, the tariff of the generating station shall be determined with reference to the capital cost of the entire project, but the tariff so determined shall be applicable corresponding to the capacity contracted for supply to the beneficiaries.