6. Tariff determination.

(1)Tariff in respect of a generating station may be determined for the whole of the generating station or stage or generating unit or block thereof, and tariff in respect of a transmission system may be determined for the whole of the transmission system or transmission line or sub-station or communication system forming part of transmission system:Provided that:
(i)where all the generating units of a stage of a generating station or all elements of a transmission system have been declared under commercial operation prior to 1.4.2014, the generating company or the transmission licensee, as the case may be, shall file consolidated petition in respect of the entire generating station or transmissions system for the purpose of determination of tariff for the period 2014-15 to 2018-19:
(ii)in case of commercial operation of the generating station or transmission system including communication system on or after 1.4.2014, the generating company or transmission licensee shall file a consolidated petition combining all the units of the generating station or file appropriate petition for transmission elements of the transmission system which are likely to be commissioned during next six months from the date of application:
(iii)the tariff of the existing communication system forming part of transmission system shall be as per the methodology followed by the Commission prior to 1.4.2014.
(2)For the purpose of determination of tariff, the capital cost of a project may be broken up into stages, blocks, units, transmission lines and sub-stations, forming part of the project, if required:Provided that where break-up of the capital cost of the project for different stages or units or blocks and for transmission lines or sub-stations is not available and in case of on-going projects, the common facilities shall be apportioned on the basis of the installed capacity of the units, line length and number of bays:Provided further that in relation to multi-purpose hydro schemes, with irrigation, flood control and power components, the capital cost chargeable to the power component of the scheme only shall be considered for determination of tariff.
(3)Where an existing transmission project has been granted licence under section 14 of the Act read with Regulation 6(c) of the Central Electricity Regulatory Commission (Terms and Conditions of grant of Transmission Licence for inter-State Transmission of electricity and related matters) Regulations, 2009, the tariff of such project shall be applicable from the date of grant of transmission licence or from the date as indicated in the transmission licence, as the case may be. In such cases, the applicant shall file petition as per Annexure-I, clearly demarcating the assets which form the part of regulated business of generation and transmission, the value of such assets, source of funding etc. duly certified by an auditor.
(4)In case of multi-purpose hydro generation scheme with irrigation, flood control and power components, the capital cost chargeable to the power component of the scheme only shall be considered for determination of tariff.
(5)Where only a part of the generation capacity of a generating station is tied up for supplying power to the beneficiaries through long term power purchase agreement and the balance part of the generation capacity have not been tied up for supplying power to the beneficiaries, the tariff of the generating station shall be determined with reference to the capital cost of the entire project, but the tariff so determined shall be applicable corresponding to the capacity contracted for supply to the beneficiaries.