Section 30(4) in Central Electricity Regulatory Commission (Grant of Connectivity, Long-term Access and Medium-term Open Access in inter-State Transmission and related matters) Regulations, 2009

(4)Any mismatch between the scheduled and the actual drawal at drawal points and scheduled and the actual injection at injection points for the intra-State entities shall be determined by the concerned State Load Despatch Centre and covered in the intra-State Unscheduled Interchanges accounting scheme.