Section 19(1)(c) in Himachal Pradesh Electricity Regulatory Commission (Promotion of Generation from the Renewable Energy Sources and Terms and Conditions for Tariff Determination) Regulations, 2017
(c)the detailed project report outlining technical, operational data, capacity utilisation factor, site specific aspects, premise for capital cost and financing plan and in case of small hydro projects hydrological data for 75% dependable year;