Legal Document View

Unlock Advanced Research with PRISMAI

- Know your Kanoon - Doc Gen Hub - Counter Argument - Case Predict AI - Talk with IK Doc - ...
Upgrade to Premium
[Cites 8, Cited by 2]

Allahabad High Court

Dhani Ram Memorial Shikshan Sewa ... vs State Of U.P. & Others on 1 March, 2012

Bench: Ashok Bhushan, Sunita Agarwal





HIGH COURT OF JUDICATURE AT ALLAHABAD
 
 

								     Reserved  on 24.1.2012
 
								     Delivered on  1.3. 2012
 
Case :- WRIT - C No. - 948 of 2010
 

 
Petitioner :- Dhani Ram Memorial Shikshan Sewa Sansthan & Ors.
 
Respondent :- State Of U.P. & Others
 
Petitioner Counsel :- Ram Krishna Yadav,A.K.Yadav,Bhola Nath Yadav,Harish Kr. Yadav
 
Respondent Counsel :- C.S.C.,M.C. Tripathi,Ramesh Upadhya.,Vivek Varma
 

 
		Connected with
 

 
Case :- WRIT - C No. - 65656 of 2008
 

 
Petitioner :- Dhani Ram Memorial Shikshan Sewa Sansthan And Others
 
Respondent :- State Of U.P. And Others
 
Petitioner Counsel :- Anil Kumar Singh
 
Respondent Counsel :- C.S.C.,N. Misra
 
		
 
Hon'ble Ashok Bhushan,J.
 

Hon'ble Mrs. Sunita Agarwal,J.

(Delivered by Hon. Mrs. Sunita Agarwal, J.) Heard Sri C.B. Yadav, learned  Senior  Advocate assisted  by  Sri  Bhola  Nath Yadav, learned  counsel for the petitioners and  Sri  M.C. Tripathi, learned  counsel for the respondents.

The  above two  writ petitions  raise the same  issue and have been  heard and are being decided together by a common judgment.

The  case of the petitioners is that petitioner no. 1 which is a registered society  under the provisions of  Societies Registration Act had  applied for allotment  of land  bearing plot no. S-2, area 4579.85  Sq. Meter in Ratanpur Extension Scheme vide application dated 17.8.2006 in pursuance of advertisement  dated  26.7.2006 issued by the respondent  Kanpur  Development  Authority in the newspaper.  The  concessional rate as applicable  at the relevant  point of time  was  Rs.1032/- per  sq. meter for  the educational institution.  A  sum of  Rs.1,50,000/- was deposited through  the  bankers cheque  dated 14.8.2006 alongwith the relevant papers.

The respondent Development  Authority  instead of allotting the plot  to the petitioner institution  readvertised it  by the advertisement dated 7.10.2007 which was challenged  by way of writ petition no. 15585 of  2008.   Again  the same plot was  advertised  vide  advertisement dated 16.11.2008 which was challenged by means of another writ petition no. 65656 of  2008 wherein an interim  mandamus  dated  19.12.2008 was  issued to the effect that  no   third  party interest shall be created.   Despite  the said  direction, the respondent  authority  again invited  applications for  allotment of plot  in question vide  advertisement dated  6.2.2009 and  25.5.2009.  Both   the  advertisement are under  challenge in  writ  petition no. 948 of  2010.  

In the meantime, as soon as the  advertisement  dated  6.2.2009 and  25.5.2009 were issued by the   Development Authority a  Contempt  Application no. 2198 of 2009 (O.P. Katiyar, Secretary, Dhani Ram Memorial Shikshan Sewa Sansthan vs. Ram Swaroop, Vice-Chairman, Kanpur  Development  Authority  & another) was filed  by the petitioners.  In the said  Contempt  Application order dated  3.7.2009 was passed  whereby the  notices were issued to both the opposite parties to file reply within three weeks.   The order  dated  3.7.2009 is quoted below:

"It is stated by Sri Anil Kumar Singh, learned counsel for the applicant that the applicant had applied for allotment of plot no. S-2 under the Scheme Ratanpur Awasiya Yojna in pursuance of advertisement issued by the Kanpur Development Authority. The applicant deposited Rs.1,50,000/-, but the authority again issued an advertisement inviting applications. The applicant filed a Writ Petition No. 65656 of 2008 (Dhani Ram Memorial Shikshan Sewa Sansthan and O.P. Katiyar Vs. State of U.P. & two others ) wherein by an interim order dated 19.12.2008 the Court directed that no third party's interest will be created. According to learned counsel a certified copy of the order was served on both the opposite parties on 19.1.2009. However on 6.2.2009 and 20.5.2009 they have again published an advertisement in the newspaper to allot the very same plot to other persons. As such the opposite parties by issuing the advertisement have disobeyed the interim order passed by this Court.
In view of the aforesaid circumstances, issue notice to the opposite parties no. 1 & 2 . Opposite parties no. 1 and 2 may file reply to this contempt petition within three weeks of receipt of notice."

After  receipt of notices  of the Contempt  Application  a letter dated  19.8.2009  issued by the  Development  Authority  was received by the petitioners   and  by means of  said  letter  for the first time the allotment   order  was  issued in favour  of the petitioners.  The said   allotment  order was issued  asking to deposit the allotment money at the rate of Rs.2288/-  per  sq. m. and it was stated that total  amount of land after adjustment of the   amount  already  deposited  shall be payable  in five  equal instalments  within a period of  five years.

The  case of the petitioners is that  the  respondent Development  Authority  is not  entitled  to  increase the rate  of the plot  allotted in favour of the petitioners. A writ of certiorari has been sought   quashing the order dated 19.8.2009 issued  by the respondent no. 3 to the extent  of   excess rate of Rs.2288/- per  sq. m. in place of  Rs.1032/- per  sq. m. of the plot in question.

The  Contempt  Application  filed  by the petitioners   was dismissed  on 4.9.2009 in  view of the fact that the allotment order was   passed  by the  Development  Authority.  The order dated  4.9.2009 passed  in the  Contempt  Application  is quoted  below.

Learned counsel for the applicant has pointed out that the respondents have already complied with the order passed by this Court. Therefore, there appears no justification to proceed further with the contempt proceeding. Accordingly the same is hereby dropped. Contempt application is dismissed.

Notices issued to the opposite parties are discharged.

Learned  counsel for the petitioners submits  that  petitioners  having  applied  for   allotment  as  early as  17.8.2006 alongwith the  bankers  cheque  of Rs.1,50,000/- and  all the papers  relevant for allotment, the  Development  Authority  acted  illegally   in readvertising  the plot in question  again and  again as a result of which  the petitioners  had  to   rush to this  Hon'ble  Court by filing  writ petitions  from time  to time.   No allotment order   whatsoever has been issued   prior to  19.8.2009 and  as such   the demand raised by the respondent Development  Authority  of  Rs.2288/- per  sq. m. rate is not permissible   in the eye of law.   In any case, the petitioners  cannot  be faulted and there was no delay on the part of the petitioners  in pursuing   their  case for allotment.  The delay  being on the part of the  Development  Authority,  it  cannot be allowed to take  benefit of its own wrong. 

While refuting the submissions of the learned  counsel for the petitioners,  Sri M.C. Tripathi, learned  counsel for the respondents no. 2 & 3  submits that  an application dated  17.8.2006 for allotment of the plot in question was  moved  by the petitioners just one  day prior to the cut of date in the advertisement  dated 26.7.2006.  In the application  moved by the petitioners  in  column no. 12 " details  with regard  to availability  of  fund  etc.  with the institution  (for running  schools)" only  mention   was made  "nku ,ao 'kqYd vkfn".  No certificate  giving  details of  the income of the institution was  enclosed alongwith the application form. As a result of which,  a letter dated  29.3.2007 was issued  to the petitioners   asking  them to supply  all the details alongwith the  certificates within a period of seven days.   It  was categorically informed that  the meeting of  High  Powered Committee  for  allotment of  land could not be  convened for the reasons  of incomplete information provided by the petitioners.  The petitioners were  further informed that  they may supply   all the documents   so that the  meeting may be convened for  consideration of allotment.  A  copy of the  letter dated  29.3.2007 has been filed  as  Annexure 3  to the counter affidavit and  finds place  at page  21.

Learned  counsel for  the Kanpur  Development  Authority  further submits that the petitioners  had  deposited only token  amount of Rs.1,50,000/- in the year  2006 claiming the property worth  more than  crore.  The  allotment  to the petitioners  was  to be done  by providing  subsidy  but the petitioners had failed to submit   their  credentials  regarding   their  financial status.    When the   petitioners  did not respond   in pursuance of the letter dated 29.3.2007 and   kept the matter pending, the  Authority was  constrained  to issue  fresh   advertisement for allotment of the plot in question.  

In the  writ petition no. 15585 of  2008, which was   filed  challenging the  advertisement  dated  7.10.2007 no order was passed  by this   Hon'ble  Court.  When  the  case  came up  before  the  Court on 25.3.2008 for admission, learned  counsel for the petitioners  was  asked  to explain   the latches.  Thereafter,  he  did not   pursue  the  matter and the writ petition was dismissed  for  default  vide order dated 26.11.2010.  No  restoration application whatsoever has  been filed by the petitioners for recall of the order and as such the writ petition no. 15585 of 2008 does not  survive.

Learned  counsel for Kanpur Development  Authority  further  submits that writ petition no. 65656 of 2008 challenging the  subsequent advertisement dated  16.11.2008 was filed   purely on distorted facts   in order to compel  Kanpur  Development  Authority  to allot the plot in  favour of the petitioners  at the subsidized  rate. The petitioners  themselves  were  at  fault  and  did not  submit   complete  information, on account of  which the   meeting of  High  Powered Committee could not  be  convened  for  consideration of  their  case  for allotment.   Further, the   Contempt  Application was filed in order to  pressurize  the  Kanpur  Development  Authority  and immediately after notice  of  Contempt  Petition was received  by the  Secretary, Kanpur Development  Authority, order dated  19.8.2009  was passed  allotting the   plot in question  at   the concessional  rate.  There was  no delay  or  reluctance  on the part of the Development  Authority  in allotment of the plot  in  question in favour of the petitioner institution.  The  delay is totally  attributable  to the  petitioner institution and the  rate of  Rs.2288/- per  sq. m.   has been rightly asked as the  allotment   order   was issued in the year  2009. 

In any case, the  rate of Rs.1032/-  per  sq. m.  as  applicable  in the year  2006 cannot be  made applicable in the year  2009.  The  cost of the  land is more than  Rs.2  crore and the petitioners  by instituting  petitions  one  after the other   succeeded in their  effort to scuttle  the advertisement and  eventually  succeeded  in getting the allotment   order in  favour of the petitioner  institution.   The  nominal  amount of  Rs.1,50,000/- as registration  amount   does not confer any right  for allotment  in  favour of the petitioner institution.  In any  view of the matter, the  Development   Authority  cannot be   faulted  in readvertising the   plots in question and  finally  asking  for  Rs.2288/-  per  sq. m. rate which is less than the  scheduled  rate.  The  advertisement  dated 26.7.2006 itself  provides that the   scheduled  rate  at the time of  allotment  shall be  applicable.

Reliance  has been placed  upon clause  4  of the  advertisement   dated 26.7.2006 which has been annexed as   Annexure  1  to the counter affidavit. 

The petitioners  never  challenged the condition of  Clause  4 of the  advertisement  dated  26.7.2006, thus  they  cannot be  allowed to challenge the order dated  19.8.2009 whereby the allotment has been made  by providing  60% rebate   to the   scheduled  rate  at the time of allotment of the plot strictly in accordance with Clause  4  of the  said  advertisement.

We have heard  learned  counsel for the parties and perused the  record.

Learned counsel for the petitioners vehemently argued that the petitioners are not liable to make payment as per rate given in the letter of allotment dated 19.8.2009 rather they are liable to make payment only at the rate of Rs.1032 per sq. m. prevailing at the time of advertisement dated 26.7.2006. He further argued that the allotment in favour of the petitioners having been made in pursuance of advertisement issued in 2006, the rate prevailing in the year 2009 cannot be made applicable by the respondent no. 4. Further submission is that the Authority is responsible for the delay in making allotment of the plot in question and having failed to make the allotment within a reasonable time, hence allottee petitioners cannot be compelled to pay the enhanced rate.

Reliance  has  been placed upon the judgment  of  the Apex  Court  in  Kanpur  Development  Authority  vs.  Smt.  Sheela Devi  &  others reported in 2004(1) AWC 739 (SC). Paragraphs  14, 15 & 16 of the  above  judgment  has  been  relied  upon in submitting that the  delay in  allotting the plot to the petitioners was  caused  due to lapse  on the part of the  Kanpur  Development  Authority and there  is no  justifiable  reason for  escalation  of the  price  as  such.  The  Kanpur  Development  Authority should  not be  allowed  to  determine the rate applicable in the year  2009 in an arbitrary  manner.

The  facts of the  case  relied  upon by the petitioners  in  the  above  judgment  were that  three schemes were floated by Kanpur Development Authority in September, 1978 for allotment of flats for economically weaker Section, Lower Income Group and Middle Income Group. Allotments on the basis of lottery was made on 25.10.1980. Middle Income Group were not allotted houses and their applications were kept pending for more than 18 years alongwith the applications under Middle Income Group, Kanpur Development Authority included the name of some more applicants after last date which gave rise to suit in the year 1981-82. The said suit was decreed and the applicants were directed to be allotted the flats. The Kanpur Development Authority instead of complying with the decree increased the cost of each house from 48000 to Rs.2,08,000 by notification dated 24.12.1994. The writ petitions were filed challenging the increase of price. The High Court allowed the writ petition holding that delay in allotting and delivery of possession was caused due to laches on the part of the Kanpur Development Authority. There was specific clause in the brochure mentioned about estimated cost of Rs.48,000/- which can also exceed up to 10% . The Apex Court in above decision has approved the finding that the delay was caused by the Development Authority and although escalation could not exceed 10% as provided in the brochure but the escalation of more than four times was contrary to the contents of the own brochure of the Kanpur Development Authority. Thus, the judgment of the Apex Court in Kanpur Development Authority was on its own facts where Kanpur Development Authority has delayed the allotment for 18 years and there was a specific clause permitting increase only up to 10%.

Another  judgment  relied upon by the learned  counsel for the petitioners is 2008(2) UPLBEC 1251 (Kanti  Devi(Smt.) and  39 others  vs. Kanpur  Development   Authority, Kanpur  &  others).  In the said case, the facts   as noticed by this Court  was  that there was no delay on the part of the petitioners and the delay was on the part of the  Authority in removing the unauthorised persons who had  illegally occupied  the  flats  and in view of the said facts the demand of enhanced price and the interest thereon made by the  Authority was set  aside.  The said case was also decided in its own  fact.  Moreover,  the allotment  under the scheme in the said case was for the persons  belonging  to  economically weaker  sections  floated in the year  1975.   The construction work  was completed in the year  1980 after  which  115  flats  were  allotted in the year  1985.  However, most of the remaining  flats  could not be allotted to the  applicants including  the petitioners in the said  case  who had applied  for  allotment  as the flats were  illegally occupied by the unauthorized person and the  Authority  could remove  them sometimes in the year 1984-85 and thereafter the flats had  been allotted to the applicants  by  lottery  in the year  1985.  Thus in the facts and  circumstances of the said  case, the Court  has come to the conclusion that the  authority should not   have  demanded  enhanced  price of flats in the year  1985.  The said   case having  been decided in its own facts and circumstances and is of no help to the petitioners.

In Prashant  Kumar  Shahi vs.  Ghaziabad   Development   Authority   reported in (2000)4 SCC 120 dispute raised  before the  Court was  totally different. The appellant  applied for allotment of  a plot and paid  registration amount in the year 1989. The appellant further  submitted that he was   made to believe that the  possession of the  plot would be  handed over to him by the year 1991.  He  was asked to deposit the  balance amount  vide letter  issued on 28.2.1985.  The appellant contended  that he had already  paid  a  substantial amount and the respondents  were illegally insisting for the payment of  additional  amount  before   delivery of possession of the plot. He  filed  complaint  under  Section 36-A, 36-B & (a) and  36-D of  Monopolies and  Restrictive  Trade  Practices  Act, 1969 which was registered as  unfair  trade practice  in 1997.  The   commission in  MRTP  Act concluded that no  case of  unfair  trade practices  on behalf  of the respondent  has  been made out  and no prejudice  seems to have been  caused to the appellant complainant  as a  consequence  thereof.  The  Apex  Court  refused to  interfere with the order of the   Commission in the appeal and the appeal was  dismissed.   The appellant  was held  liable to pay the amount  demanded from him  before the delivery of  possession of the plot.

From  the   analysis  of the  aforesaid  judgment   it  appears  that  reliance  placed by  the learned  counsel for the petitioners upon the same  is   misplaced  one.

Learned counsel for the petitioners  further  tried  to draw  our  attention on the  submissions  made  by  it in  supplementary  rejoinder affidavit  that the letter dated 29.3.2007 as relied upon by the  Kanpur  Development  Authority was never  served upon the  petitioners.  In support  of the said  submission reliance  has been placed upon the case of  State of  Maharashtra vs.  Rashid  Babubhai  Mulani reported in JT 2006(1) SC 76 in which  it has been held that 'Certificate of  Posting'  obtained  by  a sender is not  comparable  to receipt  for  sending   communication  by registered post.  The  said proposition  is  not applicable in the present  case.

Further  submission of the  learned  counsel for the petitioners  is that  it is  a settled law that  where  no time  limit is prescribed for  exercise of power,  such  power has to be  exercised within a reasonable period  in support  of the  said  submission. Reliance  has been placed upon  1997 (6) SCC 71 (Mohamad  Kavi Mohamad  Amin vs.  Fatmabai  Ibrahim) and  1994 Supp (3) SCC 494 ( Delhi  Development  Authority vs.  Pushpendra  Kumar   Jain).  The  contention of the petitioners   that the  scheme  does not prescribe any  time limit and as such the allotment ought  to have  been done  within a reasonable period. 

From the  facts of the instant  case  as has  been culled out above,  it is to be  noted  that  the  Kanpur  Development  Authority(hereinafter  referred to 'KDA') invited applications for allotment vide advertisement dated 26.7.2006.  The petitioners  had  submitted  application on 17.8.2006 with an amount of  Rs.1,50,000/- . As per the case of the Authority,  as the petitioners  failed to provide  complete information in their application, the meeting of High  Powered  Committee for  consideration of the  application for allotment   could  not be  convened.  The petitioners   were informed about discrepancy and   were  asked to submit the  documents.  The  petitioners, denied the receipt  of the said letter  relied  upon by the  KDA dated  29.3.2007.  However,  it is not disputed that the plot in question was never   allotted to the petitioners  till 19.8.2009 when the contempt notice  was served upon the  Secretary of the  KDA. 

On the other hand, the  Authority  proceeded to readvertise the  plot in question vide  advertisement  dated 7.10.2007 and  further  advertisement  dated 16.11.2008.  The petitioners  filed writ petition against the first  advertisement issued on 7.10.2007 but   failed to get any interim order.  In the  writ petition  filed  against  advertisement  dated  16.11.2008,   the interim order dated  19.12.2008 was  to the effect that the  Authority  shall  not  create  any  third  party interest. On the  basis of the said interim order, when the  KDA invited   applications  through   fresh  advertisement  dated  6.2.2009 and  25.5.2009, the   Contempt  Application was filed on 3.7.2009 and the notice was  issued  by this Court.  Upon  receipt of the notice of Contempt  Application,  on  19.8.2009 the letter of  allotment  was issued  and   the  plot was allotted   at the  rate of  Rs.2288/- per sq. m. on  concessional basis.

In the case of  Delhi  Development  Authority Vs. Pushpendra Kumar Jain (supra), the  the  Apex  Court  has held that  mere  identification or  selection of  allottee  does not clothe  the person  selected with   a legal right  to   allotment   at the   price  prevailing   on the  date of  draw of lots..   The  Apex  Court  has  further  held  that right  to  flat arises only  on the communication of allotment, and the price or rates  prevalent  on the date of  such  communication, is applicable.

Learned  counsel for the KDA while placing reliance upon the  said judgment of the  Apex  Court submitted   that the  condition as laid  down in  Clause  4 of the advertisement  dated  26.7.2006 clearly states that the scheduled  rates prevailing   at the time of  allotment would be the  basis for determination of the rate of plots  after  providing the  permissible  relaxation as per  Government  Order dated 1.2.1999. Relevant  Clause  4 of the  advertisement dated  26.7.2006 is quoted below:

"4-Hkw[k.M dh njksa dk fu/kkZj.k vkoaVu ds le; izHkkoh 'ksM;wy nj esa 'kklukns'k la[;k 231@9vk&1&99 fnukad 01-02-99 ds }kjk vuqeU; NwV ¼50@60 izfr'kr½ iznku djrs gq, fd;k tk;sxkA He further submits that  the proposition laid down by the  Apex Court   in Delhi Development Authority Vs. Pushpendra  Kumar  Jain(supra) infact squarely  covers the case of the  KDA in demanding the rates prevailing on the date of allotment  i.e. 19.8.2009. He further submits that  plots had  been  allotted on concessional rate by providing  concession of 60% in the  scheduled rate and the said action of the  Authority  is strictly in accordance with  the conditions  provided in the advertisement  dated 26.7.2006.  In view thereof,  the submission of the petitioners  that  there was delay on the part of the Authority  and they are not  entitled to make payment at the rate  of  Rs.2288/- per sq. m., is  clearly  misconceived and cannot  be  accepted  at all.  Further, reliance has  been placed  upon  the  Division  Bench  Judgement   of this  Court   in  Mrs.  Anjali Swaroop vs.  NOIDA and another  reported in 2009(4)  ADJ(1) wherein the  Court  while  relying upon the judgment of  Apex  Court in  DDA vs.  Pushpendra  Kumar  Jain ( supra)  has  refused to accept  the submission of the  petitioners that they are liable to  make payment  as per the rates  mentioned  in the  brochure scheme of  2004.  The   Court  took note of   Clause  6(1) of  residential plots   Scheme  2004(1)  which provides  that  in case  there is increase in allotment rates of  above  sectors  by the  Board of  NOIDA Authority, the same   will be  applicable  to the applicants/allottees.  Thus,  the premium of plots  as mentioned in  the  brochure of 2004(1) Scheme  was  subject  to  increase  in the   allotment  rate  of the   sector.  This   Court  has  held  as follows:-
"25. In view of the aforesaid, it is to be held that by virtue of note to clause 6(i), the Noida authority is entitled to charge the rates of land as prevalent on the date when letter of allotment was issued and the claim of the petitioners that they are entitled for allotment at the rate mentioned in the Brochure Scheme 2004(1), cannot be accepted."
"39. From the aforesaid discussions, it is found that no arbitrariness or malafide can be imputed on Noida authority for delay caused in holding the draw of lots on 8.11.2008 on the basis of which the petitioners can claim not to accept the increased rate of plots w.e. f. 1.5.2008."

In the present case also, though there was no period  prescribed for allotment,  however,  Clause  4  of the  advertisement  issued on 26.7.2006 is  clear and specific.  The  petitioners  having applied in pursuance of the  advertisement  had  accepted the terms and conditions   provided in the  advertisement  itself.   There  can be no  dispute to the fact that the   plot in question was allotted   on 19.8.2009 after the   contempt  notice was issued   by this  Court. The petitioners  only  moved application for allotment on 17.8.2006 alongwith the  amount of  Rs.1,50,000/-.  Thereafter petitioners were only pursuing  the writ petitions  challenging the advertisement  issued  by the  Authority.  There is nothing on record  to substantiate  that the petitioners  had  ever  come  forward  and approached the  Authority  at any point of time and wrote that they have completed  the entire formalities  required for  allotment  of the plot  and the  Authority  had failed to   convene  the meeting of the  High  Powered Committee.  No  application whatsoever has been made by the petitioners. In view of the same,  the  contention  of the  learned  counsel for the petitioners  cannot be  accepted that there  was   any  delay on the part of the  Authority  in making  allotment.  Infact, the first  advertisement dated  7.10.2007 issued by the KDA after  the application for allotment  was moved by the petitioners  clearly shows that the petitioners had  failed to fulfill all the formalities for the  purpose of allotment,  as  a result of which the Authority was  constrained  to issue   fresh  advertisement.  Moreover, mere  moving  application for allotment  alongwith  meager  amount of  Rs.1,50,000/-   did not accrue  any indefeasible   rights  whatsoever to the petitioners.  No  vested  right has  been  accrued to the petitioners by applying  against the  advertisement dated 26.7.2006 as has  been  held   by the  Apex  Court in  DDA vs.  Pushpendra  Kumar  Jain(supra).

The  KDA  cannot be  said to be   acted  illegally or arbitrarily in asking  the  rate of  Rs.2288/- per  sq. m. while  making the allotment  vide letter  dated  19.8.2009.  The  said  rate has been asked strictly in accordance  with the   terms and conditions provided in the  advertisement   giving  concession as per the  Government  Order. 

In view of the  aforesaid  discussions, We  do not  find  any good  ground to interfere  in the   action of the respondent  Authority. The  Kanpur  Development  Authority is  clearly  entitled to  demand  the rate  as  asked  vide letter dated  19.8.2009 at the time of allotment  of plot  no. S-2 Ratanpur  Extension  Scheme in favour of the  petitioners.

The  writ petition no. 15585 of  2008 has already been dismissed in default  vide order of this  Court dated 26.11.2010.  The  above two  writ petitions no. 65656 of 2008 and  948 of  2010 are hereby dismissed.

Order Date :- 1.3. 2012 P.P.