Section 15(1)(c) in Himachal Pradesh Electricity Regulatory Commission (Promotion of Generation from the Renewable Energy Sources and Terms and Conditions for Tariff Determination) Regulations, 2017
(c)in a situation not covered under clauses (a) and (b), the Commission may allow the additional cost, not exceeding 50% of the net additional cost incurred due to time over run: