[Cites 0, Cited by 0]
[Entire Act]
State of Andhra Pradesh - Section
Section 5 in Andhra Pradesh Electricity Regulatory Commission (Transmission Standards of Performance) Regulation, 2007
5. Phasing of Implementation.
- 5.1 The performance standards excepting the Mandatory Standards, specified herein shall be implemented in a phased manner in three stages as follows:(a)Preliminary Stage (Level-1): The time period of two (2) years immediately after these standards come into force shall be considered as Preliminary State. During this preliminary stage, Standards marked as Level 1 shall be achieved, unless specified otherwise.(b)Transition State (Level-2): Time period spreading up to three (3) years after the Preliminary State shall be considered as Transition Stage. During this period, the licensee is expected to upgrade its systems. Standards marked as Level 2 shall be achieved during Transition State-, unless specified otherwise.(c)Final Stage (Level-3): Two years after expiry of the Transition State when substantial improvements should have been carried out and the system considered to be in satisfactory condition with necessary capability improvement. Standards marked as Level 3 shall be achieved during this Final State.| Nominal Voltage (kV) | Maximum Value (kV) | Minimum Value (kV) |
| 4002201323311* | 4202451453511.67 | 3602001203010 |
| % Availability of feeders =| (No of feeders X 8760 - Feeder Annual outages in feeder-hours) X 100Total availability in feeder-hours |
| % Availability of SS =| (Installed in MVA X 8760-Outages in MVA X Hours) X 100Installed capacity in MVA X 8760 |
| % Voltage Unbalance =| Max Deviation from Mean of {VRY, VYB, VBR}X 100{VRY, VYB, VBR} |
| Implementation Stage | Voltage Level | Limit of voltage Unbalance |
| PreliminaryState-Level 1Transition State-Level2Transition State-Level 2 | 220kV and Above132kV33 kV and 11 kV buses in EHV Substation | 2%3%3% |
| VVI = Square Root of {| ∑ (Vt-VN)/N²) X (1000/Vs)%} |
| Preliminary State-Level 1 | = 10 | To be achieved for more than 90% of buses |
| Transition stage Level 2 | = 6 | To be achieved for more than 90% of buses |
| Final Stage-Level 3 | = 4 | To be achieved for more than 90% of buses |
| Implementation Stage | Nos. of hours in year when system demand | Loss of Load Expectation | |
| can be fully met subject to generation availability (A) | can not fully met even with generation availability (B=8760-A) | (LOLE) in % of hours (C=B XI00/8760) | |
| PreliminaryState-Level 1TransitionStage-Level 2Final Stage-Level 3 | 744678848672.4 | 131487687.60 | 15%10%1% |
| Implementation Stage | System Security Level of "n-1" (SingleContingency) plus spinning reserve margin of: |
| Preliminary Stage-Level 1Transition Stage-Level 2Final Stage-Level 3 | No mandatoryrequirement0.5% of system peakload1% of system peak load |