Section 6(b) in The Central Electricity Regulatory Commission (Open Access in Inter-State Transmission) Regulations, 2004

(b)in case the nodal Regional load Despatch Centre does not anticipate congestion on any of the transmission corridors involved, the applicants shall be granted short-term access for the quantum and duration sought, latest by the twenty-fifth day of the month.