Section 7(4) in Central Electricity Regulatory Commission (Terms and Conditions of Tariff) Regulations, 2014

(4)The generating company or the transmission licensee, as the case may be, shall make an application as per Annexure-I of these regulations, for determination of tariff based on capital expenditure incurred duly certified by the auditors or projected to be incurred up to the date of commercial operation and additional capital expenditure incurred duly certified by the auditors or projected to be incurred during the tariff period of the generating station or the transmission system as the case may be:Provided that the petition shall contain details of underlying assumptions for the projected capital cost and additional capital expenditure, wherever applicable.