Section 7 in Central Electricity Regulatory Commission (Terms and Conditions of Tariff) Regulations, 2014

7. Application for determination of tariff.

(1)The generating company may make an application for determination of tariff for new generating station or unit thereof in accordance with the Procedure Regulations, in respect of the generating station or generating units thereof within 180 days of the anticipated date of commercial operation.
(2)The transmission licensee may make an application for determination of tariff for new transmission system including communication system or element thereof as the case may be in accordance with the Procedure Regulations, in respect of the transmission system or elements thereof anticipated to be commissioned within 180 days from the date of filing of the petition.
(3)In case of an existing generating station or transmission system including communication system or element thereof, the application shall be made not later than 180 days from the date of notification of these regulations based on admitted capital cost including any additional capital expenditure already admitted up to 31.3.2014 (either based on actual or projected additional capital expenditure) and estimated additional capital expenditure for the respective years of the tariff period 2014-15 to 2018-19.
(4)The generating company or the transmission licensee, as the case may be, shall make an application as per Annexure-I of these regulations, for determination of tariff based on capital expenditure incurred duly certified by the auditors or projected to be incurred up to the date of commercial operation and additional capital expenditure incurred duly certified by the auditors or projected to be incurred during the tariff period of the generating station or the transmission system as the case may be:Provided that the petition shall contain details of underlying assumptions for the projected capital cost and additional capital expenditure, wherever applicable.
(5)If the petition is inadequate in any respect as required under Annexure-I of these regulations, the application shall be returned to the generating company or transmission licensee as the case may be, for resubmission of the petition within one month after rectifying the deficiencies as may be pointed out by the staff of the Commission.
(6)If the information furnished in the petition is in accordance with the regulations and is adequate for carrying out prudence check of the claims made, the Commission shall consider the suggestions and objections, if any, received from the respondents within one month from the date of filing of the petition and any other person including the consumers or consumer associations. The Commission shall issue the tariff order after hearing the petitioner, the respondents and any other person specifically permitted by the Commission.
(7)In case of the new projects, the generating company or the transmission licensee, as the case may be, may be allowed tariff by the Commission based on the projected capital expenditure from the anticipated COD in accordance with Regulation 6 of these regulations:Provided that :
(i)the Commission may grant tariff upto 90% of the annual fixed charges claimed in respect of the transmission system or element thereof based on the management certificate regarding the capital cost for the purpose of inclusion in the POC charges in accordance with the CERC (Sharing of Inter State Transmission charges and losses), Regulation, 2010 as amended from time to time:
(ii)if the date of commercial operation is delayed beyond 180 days from the date of issue of tariff order in terms of clause (6) of this regulation, the tariff granted shall be deemed to have been withdrawn and the generating company or the transmission licensee shall be required to file a fresh application for determination of tariff after the date of commercial operation of the project:
(iii)where the capital cost considered in tariff by the Commission on the basis of projected capital cost as on COD or the projected additional capital expenditure exceeds the actual capital cost incurred on year to year basis by more than 5%, the generating company or the transmission licensee shall refund to the beneficiaries or the long term transmission customers /DICs as the case may be, the excess tariff recovered corresponding to excess capital cost, as approved by the Commission alongwith interest at 1.20 times of the bank rate as prevalent on 1st April of respective year:
(iv)where the capital cost considered in tariff by the Commission on the basis of projected capital cost as on COD or the projected additional capital expenditure falls short of the actual capital cost incurred on year to year basis by more than 5%, the generating company or the transmission licensee shall be entitled to recover from the beneficiaries or the long term transmission customers /DICs as the case may be, the shortfall in tariff corresponding to reduction in capital cost, as approved by the Commission alongwith interest at 0.80 times of bank rate as prevalent on 1st April of respective year.
(8)In case of the existing projects, the generating company or the transmission licensee, as the case may be, may be allowed tariff by the Commission based on the admitted capital cost as on 1.4.2014 and projected additional capital expenditure for the respective years of the tariff period 2014-15 to 2018-19 in accordance with the Regulation 6:Provided that:
(i)the generating company or the transmission licensee, as the case may be, shall continue to bill the beneficiaries or the transmission customers / DICs at the tariff approved by the Commission and applicable as on 31.3.2014 for the period starting from 1.4.2014 till approval of tariff by the Commission in accordance with these regulations:
(ii)where the capital cost considered in tariff by the Commission on the basis of projected capital cost as on COD or the projected additional capital expenditure submitted by the generating company or the transmission licensee, as the case may be, exceeds the actual capital cost incurred on year to year basis by more than 5%, the generating company or the transmission licensee shall refund to the beneficiaries or the long term transmission customers /DICs as the case may be, the excess tariff recovered corresponding to excess capital cost, ,as approved by the Commission alongwith interest at 1.20 times of the bank rate as prevalent on April 1 of respective year:
(iii)where the capital cost considered in tariff by the Commission on the basis of projected capital cost as on COD or the projected additional capital expenditure submitted by the generating company or the transmission licensee, as the case may be, falls short of the actual capital cost incurred on year to year basis by more than 5%, the generating company or the transmission licensee shall be entitled to recover from the beneficiaries or the long term transmission customers /DICs as the case may be, the shortfall in tariff corresponding to reduction in capital cost, as approved by the Commission alongwith interest at 0.80 times of bank rate as prevalent on April 1 of respective year.