State of Bihar - Subsection

Section 14(e) in Bihar Electricity Regulatory Commission (Multi Year Distribution Tariff) Regulations, 2015

(e)Notwithstanding anything contained in regulation 4 of these Regulations, the Revenue gap/surplus arising out of Truing up shall be considered by the Commission while determining the ARR of ensuing year(s).While approving adjustments towards revenue/expenses in future years, arising out of Truing up exercises, the Commission may allow the carrying costs as determined by the Commission of such expenses/revenues. However the revised estimated gap/surplus as a result of APR shall not be passed in the ARR of ensuing year.