Section 9(2) in The Petroleum and Natural Gas Regulatory Board (Technical Standards and Specifications including Safety Standards for City or Local Natural Gas Distribution Networks) Regulations, 2008

(2)If any disputes arises with regards to the interpretation of any of the provisions of these regulations, the decision of the Board shall be final. Further, the Board may at any time effect appropriate modifications in these regulations.Appendix-IList of Critical Activities in CGD Network[See regulation 7(3) (i)]
Sr. No. Critical infrastructure/ activity/ processes Time period for implementation Implementation plan
1 Pressure reduction skid CGS (active/ monitor combination)with a minimum 50% redundancy including slam shut valve for overpressure protection and creep relief valves. 1 year Modification of CGS skid
2 On line odorisation equipment designed to minimize fugitiveemissions during loading, operation and maintenance. 1 year Automated odorisation systems to be used
3 Height of the vent shall be minimum 3 meters above workinglevel 6 months Increase height of vent
4 Gas detectors shall be installed at critical locations 1 year Install gas detectors in the CGS and District PressureRegulating Station.
5 Pressure reduction for DRS (active/ monitor combination) skidwith minimum 50% redundancy including two safety devices at leastone of them shall be a slam shut valve for over pressureprotection/under-pressure and inlet and outlet isolation valves. 2 years Modification/ replacement
6 Steel reinforced rubber hose conforming to IS 9573 Type IV 6 months * Replacement of all rubber hoses @ fifty thousand per year
7 Pipeline test record and joint radiography and cover in theform of pipe book 3 months Can be submitted in stages
8 HSSE Management System 6 months To be implemented
9 Emergency Response Plan, Disaster Management Plan and writtenemergency procedures. Also, provide for an Emergency ControlRoom, manned round the clock and equipped with effectivecommunication system and emergency vehicles fitted withcommunication facilities, first aid equipment, fireextinguishers, gas detectors, repair kits and tools, maps, plans,material safety data sheets etc. at its disposal. 6 months To be implemented