Madras High Court
Rasi Tex (In) P Ltd Htsc No.192 vs Tamil Nadu Generation And on 14 September, 2018
Author: S.M.Subramaniam
Bench: S.M.Subramaniam
1
IN THE HIGH COURT OF JUDICATURE AT MADRAS
DATED: 14.09.2018
CORAM
THE HON'BLE Mr.JUSTICE S.M.SUBRAMANIAM
W.P.Nos.5916 to 5918, 6709, 7350, 8379, 10571 to 10573, 12631, 17997
& 17998, 18568 & 18574 , 18725 to 18731, 20318 to 20320, 20522 &
20523, 20901, 21057 to 21059, 29577 & 29578, 29627, 30828, 33359 to
33361, 33371 of 2014, 807 of 2015, 3041 of 2015, 29700 of 2014, 31081 &
31082 of 2014, 13514 of 2015, 29167 & 29168 of 2015, 28258 & 28259,
35997, 37403 to 37405 of 2015, 38704 to 38706, 40299, 40840 of 2015,
2288 of 2016, 3380 to 3382 of 2016, 6036 of 2016, 15319 to 15318 of
2014, 39591 of 2015, 2285 of 2016, 33150 of 2016, 19273 & 19274,
23926, 17843 of 2016, 21930 of 2015, 9255 & 9256 of 2015, 610 of 2017,
28256 to 28259 of 2013, 25833 of 2013, 31159, 31166 & 33460, 31313,
26395 & 26396, 31728, 33557, 34174 & 34175 of 2013, 32466, 30942 of
2016, 23409 of 2014, 6994, 7038, 8148 of 2015, 926 of 2017, 13870 of
2016, 6909 of 2017, 4131 of 2016, 22369 of 2015, 52 of 2016 and
Connected M.Ps.
WP.No. 5916 of 2014
Rasi Tex (In) P Ltd HTSC No.192,
Cuddalore Main Road,
Manivillunthan South (PO), Attur (TK)
Salem 636 121
rep by its
Authorised Signature V.Manohar ... Petitioners
http://www.judis.nic.in
2
Vs
1. Tamil Nadu Generation and
Distribution Corporation Limited
(TANGEDCO)
144, Anna Salai,
Chennai 600 002.
2. Chief Financial Controller/Revenue
TANGEDCO (Accounts Branch)
144, Anna Salai,
Chennai – 600 002.
3. Tamil Nadu Electricity Regulatory Commission
Through its Secretary,
No.19A, Rukmini Lakshmipathy Salai,
Egmore, Chennai 600 008.
4. The Superintending Engineer,
Salem Electricity Distribution Circle,
Tamil Nadu Generation and Distribution
Corporation Limited (TANGEDCO) ... Respondents
PRAYER IN W.P.NO. 5916 OF 2014 : Writ petitions filed under Article 226 of
the Constitution of India praying for issuance of Writ of Certiorari calling for
the records of the second respondent contained in impugned letter
CFC/FC/DFC/AAO.HT/AS.3/REV/D.N.115/13 dated 29.07.2013 and quash the
same as arbitrary, illegal and violative of the provisions of the Electricity Act,
2003 and the orders of the TNERC
WP No.5916 to 5918 of 2014
For Petitioner : Mr.AR.L.Sundaresan,
Senior Counsel
for Mr.R.S.Pandiyaraj
http://www.judis.nic.in
3
For Respondents : Mr.C.Mani Shankar
Additional Advocate General
Asst.by Mr.S.K.Raameshwar
for R1, R2 & R4
No appearance for R3
WP.No. 6709 of 2014
For Petitioner : Mr. AR.L.Sundaresan
Senior Counsel
for Mr.R.S.Pandiyaraj
For Respondents : Mr.C.Mani Shankar, AAG
Asst.By
Mr.S.K.Raameshwar for R1, R2 &, R4
No appearance for R3
WP.No. 7350 of 2014
For Petitioner : Mr. AR.L.Sundaresan
Senior Counsel
for Mr.R.S.Pandiyaraj
For Respondents : Mr.C.Mani Shankar, AAG
Asst.By
Mr.S.K.Raameshwar for R1, R2 & R4
No appearance for R3
WP.No. 8379 of 2014
For Petitioner : Mr. AR.L.Sundaresan
Senior Counsel
for Mr.R.S.Pandiyaraj
For Respondents : Mr.C.Mani Shankar, AAG
Asst.By
Mr.S.K.Raameshwar for R1, R2 &, R4
No appearance for R3
http://www.judis.nic.in
4
WP.No. 10571 to 10573 of 2014
For Petitioner : Mr. AR.L.Sundaresan
Senior Counsel
for Mr.R.S.Pandiyaraj
For Respondents : Mr.C.Mani Shankar, AAG
Asst.By
Mr.S.K.Raameshwar for R1, R2 & R4
No appearance for R3
WP.No. 12631 of 2014
For Petitioner : Mr. S.Karunakar
For Respondents : Mr.C.Mani Shankar, AAG
Asst.By
Mr.P.Guna Raj R2 to R4
No appearance for R5
Mr.R.S.Selvam for R1
WP.No. 17997 & 17998 of 2014
For Petitioner : Mr. AR.L.Sundaresan
Senior Counsel
for Mr.R.S.Pandiyaraj
For Respondents : Mr.C.Mani Shankar, AAG
Asst.By
Mr.S.K.Raameshwar for R1, R2 & R4
No appearance for R3
http://www.judis.nic.in
5
WP.No. 18568 to 18574 of 2014
For Petitioner : Mr. AR.L.Sundaresan
Senior Counsel
for Mr.R.S.Pandiyaraj
For Respondents : Mr.C.Mani Shankar, AAG
Asst.By
Mr.S.K.Raameshwar
Standing Counsel
for R1 to R3
No appearance for R4
WP.No. 18725 to 18731 of 2014
For Petitioner : Mr.AR.L.Sundaresan
Senior Counsel
for Mr.R.S.Pandiyaraj
For Respondents : Mr.C.Mani Shankar
Additional Advocate General
Asst.by
Mr.S.K.Raameshwar
for R1 to R3
No appearance for R4
WP.No. 20318 to 20320 of 2014
For Petitioner : Mr.AR.L.Sundaresan
Senior Counsel
for Mr.R.S.Pandiyaraj
For Respondents : Mr.C.Mani Shankar
Additional Advocate General
Asst.by
Mr.S.K.Raameshwar
Standing Counsel for R1 to R3
No appearance for R4
http://www.judis.nic.in
6
WP.No. 20522 & 20523 of 2014
For Petitioner : Mr.AR.L.Sundaresan
Senior Counsel
for Mr.R.S.Pandiyaraj
For Respondents : Mr.C.Mani Shankar
Additional Advocate General
Asst.by
Mr.S.K.Raameshwar
Standing Counsel
for R1 to R3
No appearance for R4
WP.No. 20901 of 2014
For Petitioner : Mr.AR.L.Sundaresan
Senior Counsel
for Mr.R.S.Pandiyaraj
For Respondents : Mr.C.Mani Shankar
Additional Advocate General
Asst.by
Mr.S.K.Raameshwar
for R1 to R3
No appearance for R4
WP.No. 21057 to 21059 of 2014
For Petitioner : Mr.AR.L.Sundaresan
Senior Counsel
for Mr.R.S.Pandiyaraj
For Respondents : Mr.C.Mani Shankar
Additional Advocate General
http://www.judis.nic.in
7
Asst.by
Mr.S.K.Raameshwar
for R1 to R3
No appearance for R4
WP.No. 29577 & 29578 of 2014
For Petitioner : Mr.AR.L.Sundaresan
Senior Counsel
for Mr.K.Seshadri
For Respondents : Mr.C.Mani Shankar
Additional Advocate General
Asst.by
Mr.P.R.Dilip Kumar
for R1, R2 & R4
No appearance for R3
WP.No.29627 of 2014
For Petitioner : Mr.AR.L.Sundaresan
Senior Counsel
for Mr.K.Seshadri
For Respondents : Mr.C.Mani Shankar
Additional Advocate General
Asst.by
Mr.P.R.Dhilip Kumar
for R1, R2 & R4
No appearance for R3
WP.No.30828 of 2014
For Petitioner : Mr. : Mr.AR.L.Sundaresan
Senior Counsel
for Mr.K.Seshadri
http://www.judis.nic.in
8
For Respondents : Mr.C.Mani Shankar
Additional Advocate General
Asst.by
Mr.S.K.Raameshwar
Standing Counsel for R1, R2 & R4
No appearance for R3
WP.No.33359 to 33361 of 2014
For Petitioner : : Mr.AR.L.Sundaresan
Senior Counsel
for Mr.K.Seshadri
For Respondents : Mr.C.Mani Shankar
Additional Advocate General
Asst.by
Mr.P.R.Dhilip Kumar
for R1, R2 & R4
No appearance for R3
WP.No.33371 of 2014
For Petitioner : : Mr.AR.L.Sundaresan
Senior Counsel
for Mr.K.Seshadri
For Respondents : Mr.C.Mani Shankar
Additional Advocate General
Asst.by
Mr.P.R.Dhilip Kumar
for R1, R2 & R4
No appearance for R3
WP.No.807 of 2015
For Petitioner : : Mr.AR.L.Sundaresan
Senior Counsel
for Mr.K.Seshadri
http://www.judis.nic.in
9
For Respondents : Mr.C.Mani Shankar
Additional Advocate General
Asst.by
Mr.P.R.Dhilip Kumar
for R1, R2 & R4
No appearance for R3
WP.No.3041 of 2015
For Petitioner : Mr.AR.L.Sundaresan
Senior Counsel
for Mr.K.Seshadri
For Respondents : Mr.C.Mani Shankar
Additional Advocate General
Asst.by
Mr.S.K.Raameshwar
for R1, R2 & R4
No appearance for R3
WP.No.29700 of 2014
For Petitioner : Mr.AR.L.Sundaresan
Senior Counsel
for Mr.K.Seshadri
For Respondents : Mr.C.Mani Shankar
Additional Advocate General
Asst.by
Mr.P.R.Dhilip Kumar
for R1, R2 & R4
No appearance for R3
WP.No.31081 & 31082 of 2014
For Petitioner : Mr.AR.L.Sundaresan,
Senior Counsel
http://www.judis.nic.in
10
for Mr.K.Seshadri
For Respondents : Mr.C.Mani Shankar
Additional Advocate General
Asst.by
Mr.P.R.Dilip Kumar
Standing counsel for R1, R2 & R4
No appearance for R3
WP.No.13514 of 2015
For Petitioner : Mr.AR.L.Sundaresan,
Senior Counsel
for Mr.R.S.Pandiyaraj
For Respondents : Mr.C.Mani Shankar
Additional Advocate General
Asst.by
Mr.S.K.Raameshwar
Standing counsel for R1 to R3
No appearance for R4
WP.No.29167 & 29168 of 2015
For Petitioner : Mr.AR.L.Sundaresan,
Senior Counsel
for Mr.R.S.Pandiyaraj
For Respondents : Mr.C.Mani Shankar
Additional Advocate General
Asst.by
Mr.S.K.Raameshwar
Standing counsel for R1 to R3
No appearance for R4
http://www.judis.nic.in
11
WP.No.28258 & 28259 of 2015
For Petitioner : Mr.AR.L.Sundaresan,
Senior Counsel
for Mr.R.S.Pandiyaraj
For Respondents : Mr.C.Mani Shankar
Additional Advocate General
Asst.by
Mr.S.K.Raameshwar
Standing counsel for R1 to R3
No appearance for R4
WP.No.35997 of 2015
For Petitioner : Mr.Satish Parasaran
Senior Counsel for
Mr.R.Parthasarathy
For Respondents : Mr.C.Mani Shankar
Additional Advocate General
Asst.by
Mr.S.K.Raameshwar for R1 to R4 & R6
No appearance for R5
WP.No.37403 to 37405 of 2015
For Petitioner : Mr. AR.L.Sundaresan
Senior Counsel
for Mr.R.S.Pandiyaraj
For Respondents : Mr.C.Mani Shankar, AAG
Asst.By
Mr.S.K.Raameshwar for R1 to R3
No appearance for R4
http://www.judis.nic.in
12
WP.No.38704 to 38706 of 2015
For Petitioner : Mr. AR.L.Sundaresan
Senior Counsel
for Mr.R.S.Pandiyaraj
For Respondents : Mr.C.Mani Shankar, AAG
Asst.By
Mr.S.K.Raameshwar for R1 to R3
No appearance for R4
WP.No.40299 of 2015
For Petitioner : Mr.Satish Parasaran
Senior Counsel for
Mr.R.Parthasarathy
For Respondents : Mr.C.Mani Shankar
Additional Advocate General
Asst.by
Mr.P.GunaRaj for R1 to R5 & R7
Mr.Abdul Saleem for R6
WP.No.40840 of 2015
For Petitioner : Mr. AR.L.Sundaresan
Senior Counsel
for Mr.K.Seshadri
For Respondents : Mr.C.Mani Shankar, AAG
Asst.By
Mr.S.K.Raameshwar for R1, R2,
R4 & R5
http://www.judis.nic.in
13
No appearance for R3
WP.No.2288 of 2016
For Petitioner : Mr.Satish Parasaran
Senior Counsel for
Mr.R.Parthasarathy
For Respondents : Mr.C.Mani Shankar
Additional Advocate General
Asst.by
Mr.S.K.Raameshwar
Standing Counsel for R1 to R4 & R6
WP.No.3380 to 3382 of 2016
For Petitioner : Mr. AR.L.Sundaresan
Senior Counsel
for Mr.R.S.Pandiyaraj
For Respondents : Mr.C.Mani Shankar, AAG
Asst.By
Mr.S.K.Raameshwar for R1 to R3
No appearance for R4
WP.No.6036 of 2016
For Petitioner : Mr. K.Seshadri
For Respondents : Mr.C.Mani Shankar, AAG
Asst.By
Mr.S.K.Raameshwar for R1, R2 & R4
No appearance for R3
http://www.judis.nic.in
14
WP.No.15316 to 15318 of 2014
For Petitioner : Mr. AR.L.Sundaresan
Senior Counsel
for Mr.R.S.Pandiyaraj
For Respondents : Mr.C.Mani Shankar, AAG
Asst.By
Mr.S.K.Raameshwar for R1, R2, R4
No appearance for R3
WP.No.39591 of 2015
For Petitioner : Mr.Satish Parasaran
Senior Counsel for
Mr.R.Parthasarathy
For Respondents : Mr.C.Mani Shankar
Additional Advocate General
Asst.by
Mr.M.Varun Kumar for R1 to R5 & R7
Mr.Abdul Saleem for R6
No appearance for R8
WP.No.2285 of 2016
For Petitioner : Mr.K.Seshadri
For Respondents : Mr.C.Mani Shankar
Additional Advocate General
Asst.by
Mr.S.K.Raameshwar
Standing Counsel
for R1, R2 & R4
http://www.judis.nic.in
15
No appearance for R3
WP.No.33150 of 2016
For Petitioner : Mr.K.Seshadri
For Respondents : Mr.C.Mani Shankar
Additional Advocate General
Asst.by
Mr.P.R.Dhilip Kumar
for R1, R2 & R4
No appearance for R3
WP.No.19273 & 19274 of 2016
For Petitioner : Mr.K.Seshadri
For Respondents : Mr.C.Mani Shankar
Additional Advocate General
Asst.by
Mr.P.R.Dhilip Kumar
for R1, R2 & R4
No appearance for R3
WP.No.23926 of 2016
For Petitioner : Mr.K.Seshadri
For Respondents : Mr.C.Mani Shankar
Additional Advocate General
Asst.by
Mr.S.K.Raameshwar
for R1, R2 & R4
No appearance for R3
http://www.judis.nic.in
16
WP.No.17843 of 2016
For Petitioner : Mr.K.Seshadri
For Respondents : Mr.C.Mani Shankar
Additional Advocate General
Asst.by
Mr.P.R.Dhilip Kumar
for R1, R2 & R4
No appearance for R3
WP.No.21930 of 2015
For Petitioner : Mr.K.Seshadri
For Respondents : Mr.C.Mani Shankar
Additional Advocate General
Asst.by
Mr.P.R.Dhilip Kumar
for R1, R2 & R4
No appearance for R3
WP.No.9255 & 9256 of 2015
For Petitioner : Mr.K.Seshadri
For Respondents : Mr.C.Mani Shankar
Additional Advocate General
Asst.by
Mr.P.R.Dhilip Kumar
for R1, R2 & R4
No appearance for R3
http://www.judis.nic.in
17
WP.No.610 of 2017
For Petitioner : Mr. Mr.K.Seshadri
For Respondents : Mr.C.Mani Shankar
Additional Advocate General
Asst.by
Mr.P.R.Dhilip Kumar
for R1, R2 & R4
No appearance for R3
WP.No.28256 to 28259 of 2013
For Petitioner : Mr. AR.L.Sundaresan
Senior Counsel
for Mr.R.S.Pandiyaraj
For Respondents : Mr.C.Mani Shankar, AAG
Asst.By
Mr.S.K.Raameshwar for R1, R2, & R4
Mr.Vijaya Mahanath for R3
WP.No.25833 of 2013
For Petitioner : Mr.Satish Parasaran
Senior Counsel for
Mr.R.Parthasarathy
For Respondents : Mr.C.Mani Shankar
Additional Advocate General
Asst.by
Mr.M.Varun Kumar
Standing Counsel for R1 & R2
No appearance for R3
http://www.judis.nic.in
18
WP.No.31159 of 2013
For Petitioner : Mr.Satish Parasaran
Senior Counsel for
Mr.R.Parthasarathy
For Respondents : Mr.C.Mani Shankar
Additional Advocate General
Asst.by
Mr.M.Varun Kumar
Standing Counsel for R1 & R2
No appearance for R3
WP.No.31166 & 33460 of 2013
For Petitioner : Mr.Satish Parasaran
Senior Counsel for
Mr.R.Parthasarathy
For Respondents : Mr.C.Mani Shankar
Additional Advocate General
Asst.by
Mr.S.K.Raamashwar
for R1 & R2 – W.P.No.31166 of 2013
for R1 to R3 – W.P.No.33460 of 2013
No appearance for R3 –
W.P.No.31166 of 2013
No appearance for R4
– W.P.No.33460 of 2013
WP.No.31313 of 2013
For Petitioner : Mr. AR.L.Sundaresan
Senior Counsel for
http://www.judis.nic.in
19
Mr.R.S.Pandiyaraj
For Respondents : Mr.C.Mani Shankar
Additional Advocate General
Asst.by
Mr.S.K.Raamashwar
for R1, R2 & R4
No appearance for R3
WP.No.26395 & 26396 of 2013
For Petitioner : Mr. AR.L.Sundaresan
Senior Counsel for
Mr.R.S.Pandiyaraj
For Respondents : Mr.C.Mani Shankar
Additional Advocate General
Asst.by
Mr.S.K.Raamashwar
for R1, R2 & R4
No appearance for R3
WP.No.31728 of 2013
For Petitioner : Mr. AR.L.Sundaresan
Senior Counsel for
Mr.R.S.Pandiyaraj
For Respondents : Mr.C.Mani Shankar
Additional Advocate General
Asst.by
Mr.S.K.Raameshwar
for R1, R2 & R4
No appearance for R3
WP.No.33557 of 2013
For Petitioner : Mr. AR.L.Sundaresan
http://www.judis.nic.in
20
Senior Counsel for
Mr.R.S.Pandiyaraj
For Respondents : Mr.C.Mani Shankar
Additional Advocate General
Asst.by
Mr.S.K.Raameshwar
for R1, R2 & R4
No appearance for R3
WP.No.34174 & 34175 of 2013
For Petitioner : Mr.K.Jayachandran
For Respondents : Mr.C.Mani Shankar
Additional Advocate General
Asst.by
Mr.S.K.Raameshwar
for R2 to R4
No appearance for R1
WP.No.32466 of 2016
For Petitioner : Mr.Rahul Balaji
For Respondents : Mr.C.Mani Shankar
Additional Advocate General
Asst.by
Mr.M.Varun Kumar
for R1 to R4
WP.No.30942 of 2016
For Petitioner : Mr.Rahul Balaji
For Respondents : Mr.C.Mani Shankar
Additional Advocate General
Asst.by
http://www.judis.nic.in
21
Mr.S.K.Raameshwar
for R1 to R4
WP.No.23409 of 2014
For Petitioner : Mr.Satish Parasaran
Senior Counsel for
Mr.R.Parthasarathy
For Respondents : Mr.C.Mani Shankar
Additional Advocate General
Asst.by
Mr.P.Gunaraj
for R1 to R3
No appearance for R4
WP.No.6994 of 2015
For Petitioner : Mr.Satish Parasaran
Senior Counsel for
Mr.R.Parthasarathy
For Respondents : Mr.C.Mani Shankar
Additional Advocate General
Asst.by
Mr.P.Gunaraj
for R1 to R3
No appearance for R4
WP.No.7038 of 2015
For Petitioner : Mr.Satish Parasaran
Senior Counsel for
Mr.R.Parthasarathy
For Respondents : Mr.C.Mani Shankar
Additional Advocate General
Asst.by
http://www.judis.nic.in
22
Mr.P.Gunaraj
for R1 to R3
No appearance for R4
WP.No.8148 of 2015
For Petitioner : Mr.Satish Parasaran
Senior Counsel for
Mr.R.Parthasarathy
For Respondents : Mr.C.Mani Shankar
Additional Advocate General
Asst.by
Mr.P.GunaRaj for R1 to R6
No appearance for R7
WP.No.926 of 2017
For Petitioner : Mr.Rahul Balaji
For Respondents : Mr.C.Mani Shankar
Additional Advocate General
Asst.by
Mr.Dilip Kumar
for R1 to R4
No appearance for R5
WP.No.13870 of 2016
For Petitioner : Mr.Rahul Balaji
For Respondents : Mr.C.Mani Shankar
Additional Advocate General
Asst.by
Mr.Raameshwar
Standing Counsel for R1 to R7
http://www.judis.nic.in
23
WP.No.6909 of 2017
For Petitioner : Mr.AR.L.Sundaresan,
Senior Counsel
for Mr.R.S.Pandiyaraj
For Respondents : Mr.C.Mani Shankar
Additional Advocate General
Asst.by
Mr.S.K.Raameshwar
standing counsel for R1 to R4
WP.No.4131 of 2016
For Petitioner : Mr. Vijayan
for M/s.King & Patridge
For Respondents : Mr.C.Mani Shankar
Additional Advocate General
Asst.by
Mr.S.K.Raameshwar
Standing Counsel for R1 to R3
No appearance for R4
WP.No.22369 of 2015
For Petitioner : Mr.K.Harishankar
For Respondents : Mr.C.Mani Shankar
Additional Advocate General
Asst.by
Mr.P.Guna Raj
for R1 to R6
Mr.Abdul Saleem for R7
http://www.judis.nic.in
24
WP.No.52 of 2016
For Petitioner : Mr.AR.L.Sundaresan,
Senior Counsel
for Mr.R.S.Pandiyaraj
For Respondents : Mr.C.Mani Shankar
Additional Advocate General
Asst.by
Mr.S.K.Raameshwar
Standing counsel for R1 to R3
No appearance for R4
COMMON ORDER
The order of cancellation of the benefit of Deemed Demand Charges issued by the second respondent in proceedings dated 29.07.2013 is sought to be quashed in all these batch of writ petitions.
2. The writ petitioners are the High Tension Electricity Consumers and they are purchasing the electricity power from the third parties for generating power and adjusting the same for the benefit of petitioners establishments.
3. In this regard certain terms and agreements were agreed upon http://www.judis.nic.in 25 between the parties by way of adjudicative process before the Tamil Nadu Electricity Regulatory Commission.
4. The learned senior counsel appearing on behalf of the writ petitioner contented that the unilateral withdrawal of concession granted to the writ petitioners are arbitrary and unsustainable in view of the order dated 15.05.2006 in petition No.TP 1/05 by the Tamil Nadu Electricity Regulatory Commission. It is contended that the adjudicative process had been conducted statements, objections and suggestions were received from all stakeholders and thereafter a decision was taken by the Tamil Nadu Electricity Regulatory Commission, Chennai in petition No.T.P.1/2005 and an order was passed in order No.2 dated 15.05.2006. The preamble of the order stipulates as follows:-
Sub-section (2) of Section 42 of the Electricity Act, 2003, stipulates that the State Commission shall introduce open access in such phases and subject to such conditions as may be specified, within one year of the appointed date. Accordingly, the Commission has notified the Tamil Nadu Electricity Regulatory Commission – Intra State Open Access Regulations 2005 in the Tamil Nadu Government Gazette dated the 3rd August, 2005 so as to introduce open access in Tamil Nadu. As per Regulation 9 of the aforesaid Regulations, various charges payable to State Transmission Utility / Transmission Licensee and http://www.judis.nic.in 26 Distribution Licensee by an open access customer have to be determined by the Commission. As directed by the Commission, the TNEB filed a petition for determination of the above charges on 26.09.2005 and the Petition was registered and numbered as T.P. 1 of 2005.
In exercise of the powers conferred by section 42 of the Electricity Act, 2003 (Act 36 of 2003) and all other powers enabling it in this behalf, the Tamil Nadu Electricity Regulatory Commission (TNERC) after having considered the written objections, consulted the members of the State Advisory Committee, heard the issues raised by the stakeholders in a public hearing, the reply of the Tamil Nadu Electricity Board, the applicant herein, and having considered the relevant documents available on record, passes this order, fixing the transmission charges, wheeling charges and other charges specified under the aforesaid Open Access Regulations and payable by an open access customer.
Sd....... Sd..... Sd.....
B.Jeyaraman S.Thangarathnam A.Balraj
Member Member Chairman
5. The learned senior counsel relied on the preamble of the said order, which states that the Regulatory Commission considered the written objections, consulted the members of the State Advisory Committee, heard the http://www.judis.nic.in 27 issues raised by the stakeholders by way of public hearing and the reply from the Tamil Nadu Electricity Board and considered all the issues. Pursuant to the said order dated 15.05.2006 the applicability of Deemed Demand Charges has been stipulated and in respect of Deemed Demand Charges it is stated that the transmission losses in each voltage play a vital role in deciding the deemed demand. The loss levels at each voltage are given above. The loss factor depends on the voltage at which the power is injected and the voltage at which the open access user draws. Since various combinations are possible, a simple methodology is adopted to approximate the loss factor under various scenarios. Even though the power, in an interconnected grid, flows by displacement and does not actually traverse the whole distance from point of injection to the point of travel, the accepted principle, in general is, that the loss estimation shall be based on the theoretical route of flow. For example, even though the generated power is injected by a generator at 11 K V and is also drawn at the same voltage of 11 KV at a distant place, the power is supposed to have been transformed through the higher voltages of 33, 110,230 KV etc., again transformed into the lower levels and reach the point of drawal.
To emulate such scenarios it is assumed that the said power, flows in an upward and downward direction as indicated below, through various transformation levels and undergoes 50% of the loss, in each direction, in that level. The percentage of deemed demand supplied by the licensee for typical http://www.judis.nic.in 28 cases of injection and drawal and based on the loss factors and also considered by the Regulatory Commission. Considering the technical aspects the Regulatory Commission passed an order in respect of billing of monthly consumption which is segregated into two parts as under.
(i) Quantum of energy supplied by the generator at open access user end and;
(ii) Quantum of energy supplied by Distribution licensee to open access user.
The demand charges in a billing month are to be arrived at as detailed below;
(a) The maximum demand recorded in a month shall be segregated into demand supplied by the generator and the demand supplied by the licensee taking into account the actual energy consumed ini units, the actual energy in units supplied by the generator and average power factor maintained at the consumption poin tin the billing month.
(b) The demand charges payable by the open access customer will be calculated as below:
Case 1:
Injection Voltage 110 kV
Drawal Voltage 33 kV
Percentage of deemed demand as per the table = 41.28 Sanction Demand 1000 Kva Recorded Demand 855 Kva Units consumed 650000 units Power factor 0.95 Units supplied by generator (at consumption point) : 500000 units Demand supplied by generator =500000/720*0.95=659.72 Kva Demand supplied by the licensee =855-659.72=195.28 Kva http://www.judis.nic.in 29 Billable demand-supplied by licensee =900-659.72=240.28 (at 90% of the sanctioned demand) Demand charges payable =(659.72*0.4128*300)+(240.28*300) =81699.72+72084=153783.72 Case 2:
Injection Voltage 230kV
Drawal Voltage 22/11 kV
Percentage of deemed demand as per the table above = 40.04 Sanction Demand 1000 Kva Recorded Demand 950 Kva Units consumed 700000 units Power factor 0.92 Units supplied by generator (at consumption point) : 700000 units Demand supplied by generator =700000/720*0.92=894.44 Kva Demand supplied by the licensee =950-894.44=55.56 Kva Billable demand-supplied by licensee = 950-894.44=55.56 Kva Demand charges payable = (894.44*0.4004*300)+(55.56*300) = 107440.13+16668=124108.13
6. Importantly in paragraph No.5.24.2 the order passed by the Regulatory Commission itself categorically states that all the orders will take effect from the date of this order and till such time the charges are revised.
Further revision shall normally be along with the regular tariff petition by the licensee. The licensee may also approach the Commission for revision of these charges by filing a distinct revision petition without linkage to the regular tariff revision. Further the commission reserves the right to initiate suo-motu procedure for revision of the charges. Thus it is made clear that the licensee has got right to approach the Commission for revision of these charges by filing http://www.judis.nic.in 30 a distinct revision petition. The commission also shall initiate suo-motu procedure for revision of the charges. Thus both the licensee as well as the Commission are empowered to re-open the concession granted in respect of Deemed Demand charges. It is further made clear that re-opening of the concession of Deemed Demand Charges is payable either by way of revision petition by the licensee or by way of suo-motu revision by the Regulatory Commission. Thus the authorities of the board has no authority to cancel the concession granted unilaterally without reference to the order passed by the Regulatory Commission by invoking clause 5.24.2 of the order dated 15.05.2006 in petition No.T.P.1 of 2005.
7. The learned senior counsel is of the opinion that the Regulatory Commission has not passed any such order withdrawing the concession granted in respect of Deemed Demand Charges to the open access consumers/fosil fuel based generators. In the absence of any such order by the Regulatory Commission, it is not open to the authorities of the electricity board to cancel the concession unilaterally by passing the impugned order.
8. The learned Additional Advocate General appearing on behalf of the respondents 1, 2 & 4 opposed the contentions of the learned counsels appearing for the writ petitioners by stating that grant of Deemed Demand http://www.judis.nic.in 31 Charges is a concession extended by the Commission at the instance of the board. Such a concession was agreed to be granted by the board on certain terms and conditions. The concession was extended undoubtedly for many years, however on account of certain financial implications the board has decided to withdraw the concession of the Deemed Demand Charges and the competent authorities are empowered to do so. In view of the fact that in the subsequent order passed by the Regulatory Commission, the concession of Deemed Demand Charges were omitted. The omission of extending the concession of Deemed Demand Charges will provide an implied power to the authorities competent of the Electricity board to cancel the concession of the Deemed Demand Charges granted to open access consumer/fosil fuel based generators. Thus there is no irregularity or infirmity in respect of the impugned circular passed in this regard. It is further contended that the benefit extended is being a concession can never be claimed as a right by the writ petitioners. The concession is granted considering various other factors by the commission in the year 2012. On account of the changed circumstances the board by way of an order dated 30.03.2012 in order No.2/2012 the concept of grant of Deemed Demand Charges were dispensed with. However the learned Additional Advocate General admitted the fact that there is no specific clause withdrawing the concession or to dispense with the concession granted earlier. However such an order for withdrawal of concession was passed with reference http://www.judis.nic.in 32 to the wind mill energy case. However in respect of the open access customers/fosil fuel based generators no such order was passed by the Tamil Nadu Electricity Regulatory Commission. This being the factum of the case there is no irregularity or illegality in respect of the cancellation of concession of Deemed Demand Charges granted earlier to this writ petitioners. The learned Additional Advocate General further contended that in respect of Wind Mill Generators and bio-gas power generators the said concession has been withdrawn and the Regulatory Commission had passed orders to that effect. When such being the factum of the case the mere omission shall not be construed as an extension of the concession granted in all other cases. The concession has been withdrawn and the same cannot be continued in respect of the writ petitioners alone, who are all coming under the category of open access customers/fosil fuel based generators. Thus the writ petitions are liable to be rejected.
9. Considering the arguments advanced on both sides, this Court is of the opinion that admittedly the concession of Deemed Demand Charges were granted to all these writ petitioners by way of an order by the Tamil Nadu Electricity Regulatory Commission in T.P.1 of 2005 dated 15.05.2006. The preamble of the order categorically enumerates that an adjudicative process had been conducted and written objections, suggestions, consulted the http://www.judis.nic.in 33 members of the State Advisory Committee, heard the issues raised by the stakeholders by way of public hearing and were obtained before passing an order. This Court is of the opinion that such a process ought to have been conducted before withdrawing the concession granted to these writ petitioners. Concept of implied withdrawal can never be accepted. In view of the fact that through an agreement the concession was granted and it is contractual in nature. The petitioners are generating electricity power and keeping the same for their own usage. The service of the electricity board is also utilised by these petitioners for transmitting the electricity power. Thus the services ought to be compensated by the writ petitioners undoubtedly all these conditions were considered by providing opportunity to all the parties and a decision was taken by the Tamil Nadu Electricity Regulatory Commission. Such being the factum, while withdrawing the concession it is necessary on the part of the electricity board to approach the Electricity Regulatory Commission by filing a proper application or with a request to initiate suo-motu revision under clause 5.24.2 of the said order dated 15.05.2006 in respect of the open access customers/fosil fuel based generators. In respect of all other categories the Regulatory Commission had already passed orders withdrawing the concession of Deemed Demand Charges. Thus it is made clear that the electricity board has to approach the Tamil Nadu Electricity Regulatory Commission for the purpose of revision of all such concessions granted to this http://www.judis.nic.in 34 category.
10. This Court is of the considered opinion that when certain concession are granted for a clause/group of people by way of adjudicative process, the said concession can be withdrawn only by following the procedure. In the event of unilateral cancellation of such concession, certainly rights of the persons, who enjoyed the concession will be prejudiced. Even such a consultation process has been stipulated in the order passed by the Electricity Regulatory Commission dated 15.05.2006 in clause 5.24.2 which contemplates that the licensee may also approach the Commission for revision of these charges by filing a distinct revision petition without linkage to the regular tariff revision. Further the commission reserves the right to initiate suo-motu procedure for revision of the charges. When such a power has been provided under the very order, there is no impediment to the Regulatory Commission to initiate suo-motu revision to re-open the case of open access consumers/fosil fuel based generators. Electricity board is also competent to submit an application for revision of the charges before the Regulatory Commission.
11. On a perusal of the entire records it is made clear that no adjudicative process had been conducted before issuing the impugned order by the Tamil Nadu Regulatory Commission in respect of the category of open http://www.judis.nic.in 35 access consumers/fosil fuel based generators. When the concession is extended to this category withdrawal of the same must be done by providing an opportunity to the persons who are benefited from and out of the concession. Admittedly no such opportunity was provided to the writ petitioners before issuing impugned circular by the respondents. An opportunity to be provided is for the purpose of submitting the objections in respect of cancellation of such concession. Thus it is made clear that as per clause 5.24.2 the Electricity Board is at liberty to approach the Regulatory Commission if so advised.
12. The learned Additional Advocate General with reference to the counter affidavit filed by the third respondent Tamil Nadu Electricity Regulatory Commission contended that the concept of Deemed Demand benefit was introduced in Order No.3 of 2006 by the Commission. Though there was no regulation governing the said subject, it was introduced solely with a view to extend a concession to generators as the introduction of open access was in the initial stage. The deemed demand is a fiction, which was evolved to promote open access in the formative stages and rightly Commission has reviewed its own decision in the subsequent statutory order to dispense with the same. The concept of demand charges has found statutory sanction in the Electricity Act, 2003 which provides for recovery of fixed charges but the same is not the case in respect of deemed Demand charges which does not have http://www.judis.nic.in 36 statutory sanction. At best, the facility so far enjoyed cane be termed to be a concessional one to promote open access in the initial stages and any move to make such concessions to the generators a permanent affair would amount to unfair enrichment at the cost of the licensee/other consumers. Further, the demand charges being a component of tariff, the Commission has the power to revisit the same and revise subsequently as circumstances warrant.
13. Further it is contended in paragraph No.11 of the counter affidavit which reads as under.
11. The respondent Commission withdrew the Deemed Demand concept in respect of Wind Energy Generators, Biomass generators, Bagasse Based Co-generators in Orders No 6, 7 and 8 dated 31.07.2012. The following observations of the Commission in clause 8.2.5.3(b) (ii) of the Order No.8 of 2012 are re- produced for better appreciation of the facts of the case. “ii) Demand charges Demand charges are governed by the provisions of Supply Code, Distribution Code and the applicable Tariff Order issued by the Commission from time to time. Sections 9 and 42 of the Electricity Act, 2003, enables consumption of electricity from the captive generating plant. Proviso to Section 42 envisages that surcharge shall not be leviable in case open access is http://www.judis.nic.in 37 provided to a person who has established captive generation plant for carrying the electricity to the destination of his own use. This is also reflected in the note to Regulation 9 (2) which is reproduced below:-
“Provided that such surcharge shall not be levied in case transmission access is provided to a person who has established a captive generation plant for carrying the electricity to the destination of his own use.” In the Tariff Order issued by the Commission in 2006 and 2009 the concept of deemed demand was introduced with a view to reduce the demand charges. This is opposed by the TANGEDCO as they are unable to recover the full demand charges relating to providing all the infrastructure facilities as well as typing up of the generation capacity. This matter was examined in detail. The Commission observes that
a) When the captive power plant is not generating power, the licensee is obliged to provide power supply to the consumer.
During this period no wheeling charge is recoverable as the captive generator is not injecting any power. The fixed charges payable to other generating stations or procurement of power from the market to meet such contingency will devolve on the licensee.
http://www.judis.nic.in 38
b) If the captive generator is generating throughout the year, he could always reduce the sanctioned demand and control his demand charges for the supply to be made only by the licensee.
c) Since the open access regulation cast a duty on the licensee to provide electricity to all open access customers, whether captive or otherwise, in case of non-generation by such generator, the fixed charge is getting shifted to the licensee.
d) Keeping in view the above, the Commission decides to withdraw the deemed demand concept followed so far. The Commission also observes that such deemed demand concept is not prevalent in many other states in India.”
14. With reference to the submissions made by the respective learned counsels appearing on behalf of the parties to the lis on hand, this Court is of the opinion that the power to revisit the entire concession of Deemed Demand Charges is granted to the Tamil Nadu Electricity Regulatory Commission. The Commission is empowered to revise the order even by initiating suo-motu revision. The power of suo-motu revision has been contemplated in the order dated 15.05.2006 itself. Thus there is no impediment for the commission to initiate suo-motu revision for the purpose of revisiting the entire concession and to revise the same if necessary. The grievance of the writ petitioner is that such a suo-motu power had not been exercised by the Regulatory http://www.judis.nic.in 39 Commission nor the Commission had undertaken the process of adjudication by providing an opportunity to the stakeholders. Without undertaking any such process the unilateral decision has been taken by the respondent Electricity Board for the withdrawal of the concession granted earlier. In the absence of a specific order by the Regulatory Commission in this regard, the power of the Commission to revise the concession of Deemed Charges cannot be usurped by the authorities of the Electricity Board. Thus the impugned order is one where the respondents are not following the procedures contemplated nor the Commission exercised the suo-motu power of revision.
15. It is contended by the learned Additional Advocate General that the petitioners are attempting to take undue advantage of the omission made by the authorities in the impugned order. However, this Court cannot consider the same in view of the fact that the powers conferred on the Regulatory Commission had not been exercised admittedly by the respondents. Procedures to be followed also had not been adhered. Thus the very submission made that the omission on the part of the respondent is taken as an advantage by the writ petitioners deserves no merit. This apart this Court cannot draw an inference from and out of such omission made by the Electricity Board or by the Regulatory Commission. There cannot be any implied withdrawal of concession, which is permissible. The concession already granted and in force http://www.judis.nic.in 40 for long years can be withdrawn or taken away only by following the procedures contemplated and therefore the unilateral decision of the respondent Board can never be appreciated by this Court.
16. Paragraph No. 11 of the counter affidavit filed by the respondents enumerates that the Regulatory Commission had withdrawn the Deemed Demand Charges concept in respect of the Wind Energy Generators, Biomass generators, Bagasse Based Co-generators in Orders No.6, 7 & 8 dated 31.07.2012. However, the open category of the writ petitioners namely open access consumer/fosil fuel based generators has not been stated in the counter affidavit. Thus the reason for non-inclusion is not known to this Court. This Court cannot draw any factual inference in respect of the withdrawal of the concession granted to all other categories but it should be applied to the writ petitioners also who belongs to a different category. Such an inference is not only improbable, which cannot be made, in view of the fact that specific clause is available in the order of the Regulatory Commission dated 15.05.2006 for initiation of revision procedures even suo-motu. Thus it is made clear that the respondents in the event of passing an appropriate orders by following the procedures contemplated cannot withdraw or cancel the benefit of Deemed Demand Charges already extended to these writ petitioners. The said concession can be cancelled by invoking the power by Electricity Regulatory http://www.judis.nic.in 41 Commission. Accordingly these writ petitions are to be considered.
17. The learned counsel appearing for the writ petitioners has stated that such an adjudicative process in compliance with the principles of natural justice has been contemplated in the Tamil Nadu Electricity Regulatory Commission conduct of business regulations 2004 clause 16 1 & 2 reads as under :-
16 (1) The Commission may initiate any proceedings suo motu or on a petition filed by any affected or interested person.
(2) When the Commission initiates the proceedings, it shall be by a due notice issued by the Commission. The Commission may give such orders and directions as may be deemed necessary, for serving of notices to the affected parties; for the filing of replies and rejoinders against or in support of the petition in such form as the Commission may direct. The Commission may, if it considers appropriate, issue orders for publication of the petition inviting comments from the public or any class of persons on the issue involved in the proceedings in such form as the Commission may direct.
18. In view of the discussions made in the afore mentioned paragraphs, this Court is of the opinion that the Regulatory Commission has to under take http://www.judis.nic.in 42 the process of revision either suo-motu or through an application if any filed before the commission and conduct the adjudicative process by issuing notice to all the stakeholders and after hearing the parties aggrieved, decision shall be taken on merits and in accordance with law. The compliance of principles of natural justice has been contemplated in the business regulations, as stated supra. Thus Electricity Regulatory Commission is bound by that and they have to follow the procedures and thereafter take a decision and pass orders on merits and in accordance with law in respect of the withdrawal of the concession of the Deemed Demand Charges in respect of the writ petitioners. However, it is made clear that the observations made in this judgment will not affect the independent adjudication if any undertaken by the Electricity Regulatory Commission in accordance with the procedures contemplated. The Electricity Regulatory Commission is at liberty to decide the merits and de- merits independently and pass orders without causing undue delay in view of the fact that the concession has been already cancelled in respect of other categories. Accordingly the impugned order passed by the second respondent in letter No.CFC/FC/DFC/AAO.HT/AS.3/REV/D.N.115/13 dated 29.07.2013 is quashed and these writ petitions are allowed. No costs. Consequently connected miscellaneous petitions are also closed.
14.09.2018
http://www.judis.nic.in
43
Index : Yes / No
Internet : Yes/No
Speaking Order/Non-Speaking Order
dpq
http://www.judis.nic.in
44
S.M.SUBRAMANIAM, J.
dpq
1. Tamil Nadu Generation and
Distribution Corporation Limited
(TANGEDCO)
144, Anna Salai, Chennai 600 002.
2. Chief Financial Controller/Revenue
TANGEDCO (Accounts Branch)
144, Anna Salai, Chennai – 600 002.
3. Tamil Nadu Electricity Regulatory Commission Through its Secretary, No.19A, Rukmini Lakshmipathy Salai, Egmore, Chennai 600 008.
4. The Superintending Engineer, Salem Electricity Distribution Circle, Tamil Nadu Generation and Distribution Corporation Limited (TANGEDCO) W.P.Nos.5916 to 5918, 6709, 7350, 8379, 10571 to 10573, 12631, 17997 & 17998, 18568 & 18574 , 18725 to 18731, 20318 to 20320, 20522 & 20523, 20901, 21057 to 21059, 29577 & 29578, 29627, 30828, 33359 to 33361, 33371 of 2014, 807 of 2015, 3041 of 2015, 29700 of 2014, 31081 & 31082 of 2014, 13514 of 2015, 29167 & 29168 of 2015, 28258 & 28259, 35997, 37403 to 37405 of 2015, 38704 to 38706, 40299, 40840 of 2015, 2288 of 2016, 3380 to 3382 of 2016, 6036 of 2016, 15319 to 15318 of 2014, 39591 of 2015, 2285 of 2016, 33150 of 2016, 19273 & 19274, 23926, 17843 of 2016, 21930 of 2015, 9255 & 9256 of 2015, 610 of 2017, 28256 to 28259 of 2013, 25833 of 2013, 31159, 31166 & 33460, 31313, 26395 & 26396, 31728, 33557, 34174 & 34175 of 2013, 32466, 30942 of 2016, 23409 of 2014, 6994, 7038, 8148 of 2015, 926 of 2017, 13870 of http://www.judis.nic.in 45 2016, 6909 of 2017, 4131 of 2016, 22369 of 2015, 52 of 2016 and Connected M.Ps.
http://www.judis.nic.in