Section 7(2)(iv) in Central Electricity Regulatory Commission (Deviation Settlement Mechanism and Related Matters) Regulations, 2014
(iv)Any infirm injection of power by a generating station prior to COD of a unit during testing and commissioning activities shall be exempted from the volume limit specified above for a period not exceeding 6 months or the extended time allowed by the Commission in accordance with Connectivity Regulations.