State of Himachal Pradesh - Subsection

Section 19(2) in Himachal Pradesh Electricity Regulatory Commission (Promotion of Generation from the Renewable Energy Sources and Terms and Conditions for Tariff Determination) Regulations, 2017

(2)The Commission may, during the pendency of the petition filed under sub-regulation (1), allow, on such terms and conditions as it may consider necessary, a provisional tariff not exceeding the generic levellised tariff, if any, applicable to the relevant category.