Legal Document View

Unlock Advanced Research with PRISMAI

- Know your Kanoon - Doc Gen Hub - Counter Argument - Case Predict AI - Talk with IK Doc - ...
Upgrade to Premium
[Cites 8, Cited by 1]

Calcutta High Court

Heavy Engineering Corporation Limited vs Standard Chartered Bank & Anr on 8 May, 2019

Author: Soumen Sen

Bench: Soumen Sen, Ravi Krishan Kapur

                                     1



               IN THE HIGH COURT AT CALCUTTA
                        Original Civil Jurisdiction
                             ORIGINAL SIDE

BEFORE:
The Hon'ble Justice Soumen Sen
           and
The Hon'ble Justice Ravi Krishan Kapur


                           A.P.D. No. 198 of 2016
                                    With
                            C.S. No. 38 of 2000

                 Heavy Engineering Corporation Limited
                                  Vs.
                    Standard Chartered Bank & Anr.


For the Appellant             : Mr. Utpal Bose, Adv.
                                Mr. Reetobrata Mitra, Adv.
                                Ms. Bithika Mandal, Adv.

For the Respondent No. 1      : Mr. S.P. Sarkar, Sr. Adv.
                                Mr. K. V. Viswanathan, Adv.

For the Respondent No. 2      : Mr. Pramod Kumar Drolia, Adv. Official
                              Liquidator

Hearing concluded on           : 24.04.2019

Judgment on                   : 08.05.2019

      Soumen Sen J.,:- The appeal is directed against dismissal of the suit

filed by the appellant for encashment of the bank guarantee.

      A bank guarantee is a special contract and it has to be enforced

according to its terms. If the bank guarantee is unconditional and payment

should be made on demand, then the bank is under no obligation to find out

whether any default is committed or whether any amount is due by the

person at whose instance, the guarantee was issued and once the

beneficiary invokes the bank guarantee and makes the demand the bank is
                                        2


obliged to make the payment. The bank guarantee is a standalone

agreement between the bank and beneficiary and if the terms of the

guarantee are unconditional and payable on demand, the bank cannot deny

its obligation on a specious plea that there is a dispute between the

constituent and the beneficiary. The bank is not concerned with the

underlying contract between the parties to the contract. Bank guarantee is

an independent document. Unless the execution of the bank guarantee is

vitiated by fraud or there are instances of irretrievable injustice or prejudice

likely to result from the invocation of the bank guarantee, the court would

not insulate the bank from discharging its liability under a bank guarantee.

However, what is of seminal importance is that the invocation of the bank

guarantee has to be in accordance with the terms of the bank guarantee. If

the invocation is not in accordance with the terms of the guarantee, the

bank, on demand, is not required to make payment.          When a dispute is

raised as to whether the bank is justified in refusing to release the amount

covered under the bank guarantee, the court is required to scrutinize if the

invocation of the bank guarantee is in terms on the bank guarantee. The

terms of the bank guarantees are to be strictly construed. It is the bank

guarantee document which alone is important and no amount of oral

evidence can be permitted to dilute and/or explain the terms of the

guarantee which may be at variance with the agreed terms. The letter of

invocation must speak for itself.

      This discussion is essential having regard to the nature of the dispute

with which the plaintiff and the defendant had approached the trial seeking
                                          3


adjudication with regard to their respective rights in relation to an

unconditional bank guarantee payable on demand.

      The dispute arose with regard to two bank guarantees furnished on

behalf of the defendant no.2 by the defendant no.1 in favour of the plaintiff

"as advance against supply of plant and equipment" by the plaintiff to the

defendant no.2. In terms of two letters of intent, HEC-CS-1502-81 dated

19th May 1981 and HEC-CS-1502-81 dated 19th May 1981, two bank

guarantees for Rs.71,35,100 and for Rs.20,32,500 were issued. The two

bank guarantees are on identical terms, the only differences being in the

dates and amounts. The said guarantees were furnished for and on behalf

of the defendant no.2 towards advance payment of Rs.71,35,100 and

Rs.20,32,500 respectively as "advance against supply of plant and

equipment by the plaintiff to the defendant no.2" in terms of the two several

letters of intent mentioned aforesaid.

Both the letter of intent is divided into 4 sections namely:

      1. Gas Cleaning

      2. Gas Compression & Dehydration

      3. Utilities and services including telecommunication and unit

      substation.

      4. Tar distillation plant including liquor treatment & effluent

      treatment plants.

      The plaintiff intended to place an order for the complete work on a

turnkey basis of the aforesaid four sections of the LTC plant at Dankuni at a

total price of Rs.21.10 crores. The letter of intent dated 19th May, 1981 after

describing the 4 sections of the LTC plant at Dankuni stated:
                                        4


     "The above price covers the complete design, supply of both indigeneous
     and imported equipment, erection and commissioning with requisite civil
     and structural works complete in all respects except land filling upto
     4.00 M level, railways siding, roads & outside drawing and perphorial
     lighting which will only be outside your scope or work.
     The break up of the total price of Rs.21.10 crores for purpose of billing is
     enclosed.
     We have noted the terms of payment proposed by you in your letter
     dated 18.05.81.    As we have indicated about the terms of payment
     agreed to by us, it will not be possible to consider you proposal for
     relaxation of the same. However, attempts will be made to consider
     some softening of payment terms later depending our own cash flows
     on this project.
     Kindly let us have your detailed technical specifications etc to enable us
     to draw up a detailed contract for the work.
     Kindly communicate your acceptance of this letter of intent and furnish
     us a bank guarantee on approved proforma to release the initial
     advance of Rs.15.64 lakhs to you".
     In pursuance of the letter of intent two bank guarantees have been
     furnished by the defendant no.1 on behalf of the defendant no.2 "as
     advance against the supply of plant and equipment". (emphasis
     supplied)



     As stated above, the terms of the bank guarantees are identical and

the obligation of the bank to pay under the guarantee is stated in Clause 2

of both the guarantee document which are on identical terms. Clause 2 of

bank guarantee number 10001/83/108/G is reproduced below:

     "We, Grindlays Bank P.L.C., 19 Netaji Subhas Road, Kolkata - 1
     undertake the indemnify and keep the CORPORATION indemnified to
     the extent of Rs.71,35,100/- (Rupees seventy one lakhs thirty five
     thousand and one hundred only) against any loss or damage caused to
                                      5


      or suffered by the CORPORATION by reason or any breach or failure by
      the said SUPPLIER, in due performance of the aforesaid contract, we
      shall forthwith on demand pay to the CORPORATION any sum or sums
      not exceeding Rs.71,35,100/- (Rupees seventy one lakhs thirty five
      thousand and one hundred only) without making prior reference to the
      said SUPPLIER with an exclusion of any action in court by SUPPLIER."
      (emphasis supplied)



      On a plain reading of the said clause it appears that the bank would

indemnify and keep the plaintiff indemnified for the sums cover under the

said guarantee "against any loss or damage caused to or suffered by the

corporation by reason of any breach or failure by the said supplier in due

performance of the aforesaid contract."(emphasis supplied).

      These facts are indisputed.

      Keeping these facts in mind let us now examine the letter of invocation

dated 6th November, 1998. The said letter is reproduced below:

        "Dated the 6th November '1998


        To
        The Chief Manager
        ANZ, Grindlays Bank Ltd.
        19, Netaji Subhas Road
        P.B. No. 2781 Cal- 700 001

                       Kind attention:           Mr.      Harish
                  Jhurani(Operations                     Officer
                  International Services)

                       Sub:- Request for encashment of
                  D.G. No.      G1001/83/108G dt. 16.2.83
                  for    Rs.71,35,100/-    and    DG  No.
                  G/1001/84/608     dt.     29.2.84   for
                  Rs.20,32,500/-

            Dear Sir,
                                       6


                Since a substantial amount is to be
        recovered from M/s. SCIL India Limited on
        account of contractual settlement of Dankuni
        Coal Complex Project, we hereby instruct you to
        proceed   for  encashment   of  the   B.G.  No.
        G1001/83/108G dt. 16.2.83 for Rs.71,35,100/-
        and DG No. G/1001/84/608 dt. 29.2.84 for
        Rs.20,32,500/- and remit the proceeds of
        encashment to us within 7 (seven) days from the
        date of receipt of this letter.

                Kindly   expedite  the   remittance   of
        encashment proceeds through demand draft to be
        issued in favour of M/s. HEAVY ENGINEERING
        CORPORATION LIMITED, on S.B.I. Hatia, Panchi.

                   Kindly treat the matter as Most Urgent.

                   Thanking you,

                                             Yours faithfully,

                                           (S.K. CHAKRABORTY)
                                      MANAGER (FINANCE) I/C."
                                             (emphasis supplied)

      The defendant no.1 immediately upon receipt of the said letter denied

its obligation to pay on the ground that the said guarantees specifically

cover the advance to be made by the plaintiff to the defendant no.2 for

supply of plant and equipment whereas the letter of invocation is on the

ground that "a substantial amount is to be required from SCIL India Ltd. on

account of contractual settlement of Dankuni Coal Complex Project."

(emphasis added)

      Mr. Utpal Bose the learned Senior Counsel appearing on behalf of the

appellant while admitting that the said letter of invocation is defective has

submitted that by the subsequent letters dated 19th December, 1998 and

28th December, 1998 the earlier defects were cured and the said two letters

are in terms of the bank guarantee.
                                          7


        Accordingly the contention of the appellant that the bank had

wrongfully or in breach of the terms of the guarantee has refused to encash

the said bank guarantee is unsustainable and the case made out in

paragraph 12 and 13 of the plaint is rejected.         The said two paragraphs

read:

        "12. By its letter dated 6th November, 1998 to the defendant and
        received by the defendant on 13th November, 1998 the plaintiff, in the
        premises demanded the encashment of the said guarantees within
        seven days of receipt of the said letter by the defendant.
        13. Wrongfully and in breach of the terms of the said guarantees by its
        letter dated 18th November, 1998 the defendant Bank refused to encash
        the same, purporting to contended that the claim of the plaintiff was not
        within the said guarantees."



        The content of the letter dated 19th December, 1998 is reproduced

below:

        "No.HDC/Proj/Fin/98-343
                               Dated the 19th December 1998


    To
    The Chief Manager
    Corporate Banking
    ANZ Grindlays Bank
    19, Netaji Subhas Road
    Post Box No. 2645
    Calcutta - 700001


    Dear Sir,

          With reference to your St. Relationship
    Manager's letter dtd. 7.12.98 regarding encahment
    of B.Gs issued by you on behalf of M/s. SCIL for a
    total value of Rs.91.68 lakhs you are very much
    aware that M/s. SCIL owes to H.E.C. Rs.139.90 lakhs
    due to defective supply of Plant & Equipment as
    well as non-supply of Plant & Equipment and also
                           8


other contractual deficiencies which has caused
loss as reflected in the handing over/taking over
report of the DCC Project by CIL.     You are also
aware that HEC has gone out of the way in
supporting SCIL and getting the Plant completed
with minimum damage.      It is within HEC's full
rights to invoke the BG as per Clause No. 2 of the
BG's     which    is    reproduced   below;    (BG
No.G1001/83/1084 dt. 16.8.83 for Rs.71,35,100.00
and    BG    No.G1001/84/608   dt.   29.8.84   for
Rs.20,32,500.00).

      "WE GRINDLAYS BANK PLC 19, Netaji Subhas
Road, Calcutta - 700001 do hereby undertake the
Indemnity of Rs.     (RUPEES .................................) against
any loss or damage caused to or suffered by the
CORPORATION by reason or any breach or failure by
the said SUPPLIER, in due performance of the
aforesaid contract, we shall forthwith on demand
pay to the CORPORATION any sum or sums not
exceeding Rs.             (RUPEES
without making any prior reference to the said
SUPPLIER with an exclusion of any action in court
by SUPPLIER.
      The failure of M/s. SCIL in fulfilling the
contractual obligation which includes performance
Guarantees of Plant & Equipment are very well
documented by HEC & CIL. In fact, the unadjusted
advance of SCIL on account of Plant & Equipment is
far in excess of the loss suffered by HEC.      The
same has been brought down to Rs.139.90 lakhs after
allowing credit for contractual settlement.

      Although as per terms of BG we are not bound
to explain you all these things but the above
details are furnished so that good sense will
prevail and we expect you to live up to your
reputation and honour the beneficiaries claim for
encashment.

      Thanking you,
                                              Yours
                                        faithfully,
                                       T.L.N. SOURI
                  GENERAL MANAGER (PROJECTS & MNTG)

                                  (emphasis supplied)
                                        9


    This was followed by the letter dated 28th December, 1998

    which is also reproduced below :

        "No. GGM(CM)/ /98
                                                28th Dec., 1998

        To,
        The Chief Manager,
        ANZ GRINDLAYS Bank,
        CALCUTTA.

        (Attn: Shri Vasudeo Kundu)

                         Fax No. 033-2211196

           Sub: Encashment of two Bank Guarantees Nos.
              1) G/1001/83/108G for rs. 71,35,100/-
               2) G/1001/84/608 for Rs. 20,32,500/-

        Ref: Our letter dated 19.11.98

        Dear Sir,

                We have intimated vide our above letter
        to encash the above two Bank Guarantees issued
        by you on behalf of SCIL India Ltd., to HEC.

                You are requested to encash the above
        Bank Guarantees and send the proceeds amounting
        to Rs.91,67,600/- within 3 days time.    Kindly
        treat this as most urgent and failing on the
        part of the Bank to honour the beneficiaries
        demand will be viewed seriously.

                 Thanking you,


                                                          Yours
                                                    faithfully,

                                                 (L.M. Prasad)"


     In the letter dated 19th December, 1998 the plaintiff alleged that the

defendant no.2 owes to plaintiff Rs.139.90 lakhs due to defective supply of

plant and equipment as well as non-supply of plant and equipment and also
                                       10


other contractual deficiencies which had caused loss as reflected in the

handing over/taken over report of the DCC project by CIL. It further states

that the defendant no.2 has failed to fulfil the contractual obligation which

includes performance guarantee of plant and equipment.           In its earlier

communication dated 28th November, 1998 the quantification of claim of

Rs.139.90 lakhs is on the premise that the defendant no. 2 did not perform

the contract in full as is evident from clauses A(7) and B(2), which read:

      "A-7. Taking into consideration the final contract value of SCIL including
      claims as settled by CIL as well as the total payment made to SCIL
      including amount of advance directly paid to SCIL and SCIL vendor and
      contractor's payment for their portion of work, and the amount of
      deduction imposed by CIL on SCIL's A/s, HEC will receive from SCIL to
      the extent of Rs.139.90 lakhs as on date.
      Since the advance paid to SCIL was remaining unadjusted due to non
      performance of the contract in full, HEC has suffered a loss of
      Rs.139.90 lakhs as on date.     To recover the said amount from M/s.
      SCIL, we have no other alternative but to proceed for encashment of BG
      immediately.


      B-2. Clause no.5 of your BG stipulates that bank undertakes not to
      revoke this guarantee during its currency except with the previous
      consent from us in writing.
      Therefore your unilateral decision as to cancellation of BG, during its
      currency despite our enforcement of claim for encashment is a clear
      violation of the terms of BG.
      It is, therefore, appears that you are deliberately avoiding your
      responsibility for accepting our valid claim for encashment although the
      same is binding to bank as per terms of BG and you are taking decision
      as per your own desire not to invoke the BG violating the above clauses.
      As per above terms of BG, you are not even empowered to justify the
      reasons for encashment of the same as it is beyond the jurisdiction of
                                        11


      Bank. The decision for enforcing the claim for encashment is resting
      only with the beneficiary and not with the Bank as per clause No. 3 and
      5. Bank will only act as per instruction of beneficiary of BG (HEC) as the
      BG was executed by the Bank to protect any losses or damaged caused
      to or suffered by the beneficiary by reasons of any breach or failure by
      M/S. SCIL as per clause 2 of BG.
      Here M/S. HEC has suffered a loss of Rs. 139.90 lakhs by paying
      advances to M/S. SCIL for which no value of work was executed by
      M/S. SCIL and performance as stipulated in contract was not complied
      with.
      Considering the above, breach/failure by your client to execute the
      contract and the substantial damage or loss suffered by HEC arising
      there from Bank is bound to accept the beneficiary's claim for
      encashment of BG and there is no reason on the part of Bank either to
      reject the valid claim or to cancel the valid BG during its currency.
      We have explained the above fact to your Bank several times at the
      time of seeking extension for validity period of BG. Now, we further
      firmly instruct you to proceed for encashment of the above two Bank
      guarantees and remit the encashment proceeds to us without any
      further delay otherwise we will be forced to take up the matter in the
      court of law and to the Reserve Bank of India for redressal." (emphasis
      supplied)



      For the averments in support of subsequent invocation, Mr. Bose has

referred to paragraphs 14 and 15 of the plaint, which read:

      "14. In spite of several reminders thereafter from the plaintiff and the
      clear and unambiguous terms of said guarantees and the subsequent
      demands of the plaintiff, inter alia by letters dated December 19 and
      December 28 1998 the defendant bank has wrongfully not encashed
      the said guarantees for their respective sums or for any portion thereof,
      though the plaintiff was and still is absolutely entitled to the full
      amounts of the said guarantees.
                                        12


      15. The plaintiff thereafter, by its letter dated 22nd February, 1999
      complained to the Banking Ombudsman Calcutta in respect of the
      wrongful conduct of the defendant Bank. However, by a letter dated
      17th September, 1999 the plaintiff was informed that the Banking
      Ombudsman had rejected the plaintiff's case, such rejection is
      unwarranted and/or arbitrary in the facts of the case."


      Per Contra Mr. Sarkar, learned Senior Counsel appearing on behalf of

the defendant no. 1 has referred to the deposition of the witness of the

plaintiff and submitted that it would be clearly evident from the evidence of

the plaintiff that the enforcement was on account of alleged loss and

damages arising out of contractual obligations not covered under the

aforesaid two letters of intent. In this regard, the learned senior counsel has

relied upon answer to Question Nos. 30, 36, 37, 76 and 77 of the plaintiff's

witness. On the construction of Bank guarantee, the learned senior counsel

has referred to the decisions of the Queen's Bench Division in Perrylease

Ltd. v. Imecar AG and Ors. reported at [1987] 2 All ER 373 at page 378,

where the statement made in Volume 20 of Halsbury's Laws of England (4th

Edition) para 143 is relied upon and quoted with approval. The said

paragraph reads:

            "The principles of construction governing contracts in general
      apply equally to contracts of guarantee. Dealing with a guarantee as a
      mercantile contract, the court does not apply to it merely technical rules,
      but construes it so as to reflect what may fairly be inferred to have been
      the parties' real intention and understanding as expressed by them in
      writing, and so as to give effect to it rather than not..."
                                        13


      Mr. Sarkar submits that when the plaintiff initially invoked the bank

guarantee, it did not allege that there is non-supply of the equipments under

the aforesaid letters of intent but it is on account of "contractual

settlement". The perception of the letter of invocation at the time of trial is

immaterial. In this regard, reliance has been placed on the observation in

Perrylease (supra), which quoted with approval Prenn v. Simmonds

reported at [1971] 3 All ER 237 (at 241), where Lord Wilberforce said that

when construing a written contract -

               "evidence should be restricted to evidence of the factual
      background known to the parties at or before the date of a contract,
      including evidence of the "genesis" and objectively the "aim" of the
      transaction."


      This brings us to the issue of construction of the bank guarantee. The

principles of construction governing contracts in general apply equally to

contracts of guarantee. Dealing with a guarantee as a mercantile contract,

the court does not apply to it merely technical rules, but construes it so as

to reflect what may fairly be inferred to have been the parties' real intention

and understanding as expressed by them in writing, and so as to give effect

to it rather than not. As Steyn J said in Phillips v Dorintal Insurance

Ltd.; (1987) 1 Lloyd's Rep 482 at 485, to determine the meaning of a

contract the person construing the contract cannot simply 'turn to a

dictionary'.   Similarly, Lord Hoffmann said in Investors Compensation

Scheme Ltd v. West Bromwich Building Society; (1998) 1 WLR 896 at

913, that the 'meaning of words is a matter of dictionaries...; the meaning of
                                         14


the document is what the parties using those words against the relevant

background would reasonably have been understood to mean'.

        In Utica City Nat Bank v Gunn; 222 NY 204 at 207, Cardozo J had

no doubt that processes in construction are not affected by the mere fact

that the contract is one of guarantee. From the perspective of construction

principles in general, a contract of guarantee is no different from any other

contract. (See Perrylease (supra). The contract must be construed as a

whole, applying the perspective rule. (See Australian Joint Stock Bank

Ltd. v. Bailey [1989] AC 396 at 399)

        The strict application of contracts of guarantee is expressed in the

strictissimi juris rule.   That rule is usually traced back to the somewhat

ambiguous statement of Lord Ellenborough in Bacon v Chesney [(1816) 1

Stark 192: 171 ER 443].           He said that a claim against a surety is

'strictissimi juris, and it is incumbent on the plaintiff to shew that the terms

of the guarantee have been strictly complied with'. In ST Microelectronics

NV v Condor Insurance Ltd.; (2006) 2 Lloyd's Rep 525 at 530

Christopher Clarke J cited cases on both rules in reaching the conclusion

that the 'principle underlying' the cases is one of 'strict application'.

        In Ankar Pty Ltd v National Westminster Finance (Australia)

Ltd.; (1987) 162 CLR 549 Mason ACJ, Wilson, Brennan and Dawson JJ

said:

              "At law, as in equity, the traditional view is that the liability of
        the surety is strictissimi juris and that ambiguous contractual
        provisions should be construed in favour of the surety. The doctrine of
        strictissimi juris provides a counterpoise to the law's preference for a
        construction that reads a provision otherwise than a condition. A doubt
                                         15


       as to the status of a provision in a guarantee should therefore be
       resolved in favour of the surety."
       Because it posits ambiguity, the first sentence suggests that the

strictissimi juris rule is an analogous to the contra proferentem rule. (See

Wardens and Commonalty of the Mystery of Mercers of the City of

London v New Hampshire Insurance Co. [1992] 2 Lloyd's Rep 365 at

368)

       One particular situation where the strict rub of construction may

apply is in respect of the interpretation of clauses (like exclusion clauses)

which are designed to preserve the liability of the guarantor when he would

otherwise be discharged under the general law.

       The fact that the guarantee is given for a commercial purpose ought to

be a sufficient basis for use of a commercial standard of application where it

is necessary to infer the parties' intention. It is surely within the competence

of the court to adopt a construction of a document of a kind which is

frequently abused, which may lessen that abuse, provided of course that the

document is indeed not clear in its wording. The guarantee should be

interpreted "as a whole as a commercial document" [Barclays Bank Plc v.

Kingston 2006 (2) LLR 59]. In the instant matter the wordings of the bank

guarantees are clear.

       Given the nature of the risk undertaken by a guarantor, it is a

reasonable inference that the parties intend requirements which directly

qualify the creditor's right to call upon the guarantor to be met exactly. In

other words, the contract should be applied literally.
                                          16


      The modern theory of interpretation and construction of contracts

subscribes to an objective theory of contract interpretation. This means that

the subjective intentions of the parties are generally irrelevant as evidence of

the meaning of the agreement as are details of their negotiations.

      Lord Hoffmann gave his speech in Investors Compensation Scheme

v West Bromwich Building Society, [1998] 1 W.L.R. 896. In what became

the starting point for disputes about contractual interpretation he said:

            "I do not think that the fundamental change which has

      overtaken this branch of the law, particularly as a result of the

      speeches of Lord Wilberforce in Prenn v Simmonds and Reardon

      Smith Line Ltd v Hansen-Tangen, Hansen-Tangen v Sanko

      Steamship      Co,   [1976]    1   W.L.R.   989,   is   always   sufficiently

      appreciated. The result has been, subject to one important exception,

      to assimilate the way in which such documents are interpreted by

      judges to the common sense principles by which any serious

      utterance would be interpreted in ordinary life. Almost all the old

      intellectual baggage of 'legal' interpretation has been discarded. The

      principles may be summarized as follows.

              i.    Interpretation is the ascertainment of the meaning which
                    the document would convey to a reasonable person
                    having all the background knowledge which would
                    reasonably have been available to the parties in the
                    situation in which they were at the time of the contract.

              ii.   The background was famously referred to by Lord
                    Wilberforce as the 'matrix of fact', but this phrase is, if
                    anything,   an   understated    description   of   what    the
                             17


       background may include. Subject to the requirement that
       it should have been reasonably available to the parties
       and to the exception to be mentioned next, it includes
       absolutely anything which would have affected the way in
       which the language of the document would have been
       understood by a reasonable man.

iii.   The law excludes from the admissible background the
       previous negotiations of the parties and their declarations
       of subjective intent. They are admissible only in an action
       for rectification.   The law makes this distinction for
       reasons of practical policy and, in this respect only, legal
       interpretation differs from the way we would interpret
       utterances in ordinary life.     The boundaries of this
       exception are in some respects unclear. But this is not
       the occasion on which to explore them.

iv.    The meaning which is a document (or any other
       utterance) would convey to a reasonable man is not the
       same thing as the meaning of its words. The meaning of
       words is a matter of dictionaries and grammars; the
       meaning of the document is what the parties using those
       words against the relevant background would reasonably
       have been understood to mean. The background may not
       merely enable the reasonable man to choose between the
       possible meanings of words which are ambiguous but
       even between the possible meanings of words which are
       ambiguous but even (as occasionally happens in ordinary
       life) to conclude that the parties must, for whatever
       reason, have used the wrong words or syntax (See Manai
       Investment Co Ltd v Eagle Star Life Assurance Co Ltd).

 v.    The 'rule' that words should be given their 'natural and
       ordinary meaning' reflects the commonsense proposition
                                        18


                   that we do not easily accept that people have made
                   linguistic mistakes, particular in formal documents. On
                   the other hand, if one would nevertheless conclude from
                   the background that something must have gone wrong
                   with the language, the law does not require judges to
                   attribute to the parties an intention which they plainly
                   could not have had. Lord Diplock made this point more
                   vigorously when he said in Antaios Cia Naviera SA v Salen
                   Rederierna AB, the Antaios:

                         '...if detailed semantic and syntactical analysis of
                         words in a commercial contract is going to lead to a
                         conclusion that flouts business common sense, it
                         must be made to yield to business common sense.'"



      To these five principles, a sixth should now be added. In Re Sigma

Finance Corp, [2009] UKSC 2, Lord Mance, approving Lord Neuberger's

dissenting judgment in the Court of Appeal, said at page 12:

            "Lord Neuberger was right to observe that the resolution of an
      issue of interpretation in a case like the present is an iterative process,
      involving 'checking each of the rival meanings against other provisions
      of the document and investigating its commercial consequences."


      The court will construe the words used by the parties in their

agreement giving those words their natural and ordinary meaning.              In

Investors Compensation Scheme Ltd (supra), it was said that on occasion

it may be possible to conclude that the parties must, for whatever reason,

have used the wrong words or syntax, or something has gone wrong with the

language.   In broad terms this conclusion can be reached either because

commercial common sense suggests it, or because of some further evidence
                                      19


in the surrounding circumstances.     However, in most cases, as the UK

Supreme Court has reiterated, the language of the contract itself will be of

paramount importance:-

            "the reliance placed in some cases on commercial common sense
      and surrounding circumstances (eg in Chartbrook, paras 16-26) should
      not be invoked to undervalue the importance of the language of the
      provision which is to be construed. The exercise of interpreting a
      provision involves identifying what the parties meant through the eyes
      of a reasonable reader, and, save perhaps in a very unusual case, that
      meaning is most obviously to be gleaned from the language of the
      provision. Unlike commercial common sense and the surrounding
      circumstances, the parties have control over the language they use in a
      contract. And, again save perhaps in a very unusual case, the parties
      must have been specifically focussing on the issue covered by the
      provision when agreeing the wording of that provision." [Arnold v
      Britton (2015) UKSC 36]

            The principles by which contractual documents are construed

are summarised in Investors' Compensation Scheme Ltd. (supra) at 114,

applied in the context of guarantees in Static Control Components

(Europe) Ltd. v. Egan reported at [2004] 2 Lloyd's Rep 429.



      Lord Diplock in Pioneer Shipping Ltd. v. BTP Tioxide Ltd. reported

at [1981] 2 All ER 1030 (at 1035) stated that:



      "The object sought to be achieved in construing any commercial
      contract is to ascertain what were the mutual intentions of the parties
      as to the legal obligations each assumed by the contractual words in
      which they ... choose to express them; or, perhaps more accurately,
      what each would have led the other reasonably to assume were the
                                       20


      acts that he was promising to do or to refrain from doing by the words
      in which the promises on his part were expressed."


      The modern approach of the courts is to use all the available aids for

the construction of written documents to seek out from the words used what

they believe to have been the true intention of the parties when the

guarantee was executed and not to be over-constrained by an interpretation

based purely on internal linguistic considerations.



      Extrinsic evidence may assist in this process in two distinct ways.

First, extrinsic evidence of the factual situation is admissible and not

necessary for the purpose of ascertaining whether particular words in the

guarantee apply to that factual situation or whether that factual situation

comes within particular words. Second, extrinsic evidence of the context in

which the contract was made is admissible in order to construe the terms of

the contract. A mercantile contract such as a guarantee is particularly

susceptible of explanation by reference to the circumstances existing at the

time it was made. (Halsbury's Laws of England (Volume 49, Fifth Edition,

2008, Page 473).


      Interpretation is intended to establish what the parties agreed, not to

amend the words actually used by the parties to record what they both

intended to record in their agreement.      Indeed, rectification is available

"where words of the document were purposefully used but it was mistakenly

considered that they have a different meaning from their correct meaning as

a matter of construction". Despite this the courts have used interpretation
                                        21


as a tool to identify the practical commercial meaning that the parties,

objectively speaking, must have intended despite how ordinarily those words

would be read. (See Antaios v Salen Rederierna AB (The Antaios) [1985]

A.C. 191).

      In BCCI v Ali [2002] 1 A.C. 251, Lord Bingham of Cornhill

summarized the principles as follows:

             "To ascertain the intention of the parties the court reads the terms
      of the contract as a whole, giving the words used their natural and
      ordinary meaning in the context of the agreement, the parties'
      relationship and all the relevant facts surrounding the transaction so far
      as known to the parties. To ascertain the parties' intentions the court
      does not of course inquire into the parties' subjective states of mind but
      makes an objective judgment based on the materials already
      identified."



      As long ago as 1905, Wigmore described the history of the law of

interpretation as "a progress from a stiff and superstitious formalism to a

flexible rationalisim". [Wigmore on Evidence, Volume 4, para 2462] Lord

Hoffmann's summary of principle has been seen by some judges, including

himself, as no more than a step along the same road.

      Lord Bingham, speaking extra-judicially, has commented that Lord

Hoffman's five principles are more a change of emphasis than a fundamental

change.

      In Chartbrook Ltd v Persimmon Homes Ltd [2009] A.C. 1101, Lord

Hoffman himself said:

             "As Lord Bingham pointed out, there was little in that statement
      of principle which could not be found in earlier authorities. The only
                                         22


        points it decided that might have been thought in the least controversial
        were, first, that it was not necessary to find an 'ambiguity' before one
        could have any regard to background and, secondly, that the meaning
        which the parties would reasonably be taken to have intended could be
        given effect despite the fact that it was not, according to conventional
        usage, an 'available' meaning of the words or syntax which they had
        actually used."



        Lord Hoffman's five principles have been adopted by the courts in

Scotland, Ireland (with some qualification), Hong Kong, New Zealand and

Singapore, although the High Court of Australia has taken a more cautious

view.

        In ICDL GCC Foundation FZ LLC v European Computer Driving

Licence Foundation Ltd [2012 IESC 55], the Supreme Court of Ireland,

while approving Lord Hoffmann's five principles, has stressed that although

evidence of surrounding circumstances is admissible it "will not normally be

allowed to alter the plain meaning of words." In addition the court said that

the fourth principle:

                    "should not be misunderstood as advocating a loose and
              unpredictable path to interpretation.      A court will always
              commence with an examination of the words used in the
              contract."
        In Equitable Life Assurance Society v Hyman [2000] 3 All E.R.

961, Lord Steyn said:

                    "The purpose of interpretation is to assign to the language
              of the text the most appropriate meaning which the words can
              legitimately bear."
                                            23


      (See     Hudson's    Building    and      Engineering    Contracts,   Atkin
Chambers, 13th Edition;        Lewson on The Interpretation of Contracts,
6th Edition)
      Jack on Documentary Credits (4th Edition) has discussed the legal

nature of an independent guarantee in paragraph 12.53. It reads:

      "12.53      Independent guarantees are an autonomous obligation of the

guarantor    to   pay   against   stipulated    documents.    In   Edward   Owen

Engineering Ltd. v. Barclays Bank International ltd.(1) Lord Denning

MR stated (2):

               'All this leads to the conclusion that the performance guarantee

               stands on a similar footing to a letter of credit. A bank which

               gives a performance guarantee must honour that guarantee

               according to its terms. It is not concerned in the least with the

               relations between the supplier and the customer; nor with the

               question whether the supplier is in default or not. The bank must

               pay according to its guarantee, on demand, if so stipulated,

               without proof or conditions. They only exception is where there is

               a clear case of fraud of which the bank has notice.'

      The position of fraud as the 'only exception' has come under challenge

in recent years from the doctrines of unconscionability (see para 9.26 et seq)

and illegality (see para 13.106 et seq).

      1. 1978 QB 159

      2. 1978 QB 159 at 171"

      Mr. Sarkar has referred to Hindusthan Construction Co. Ltd. Vs.

State of Bihar & Ors. reported in AIR 1999 SC 3710: (1999) 8 SCC 436

for the proposition that if the letter of invocation is not in terms of the bank
                                       24


guarantee, the bank is under no obligation to honour the said bank

guarantee.

      In Hindusthan Construction (supra), the Hon'ble Supreme Court

referred to Clause 9 of the principal contract between the parties in order to

come to a conclusion that the bank guarantee specifically refers to an

original contract and postulates that if the obligations, expressed in the

contract, are not fulfilled by HCCL giving to the defendants the right to claim

recovery of the whole or part of the "Advance Mobilisation Loan", then the

Bank would pay the amount due under the Guarantee to the Executive

Engineer. It was found that the bank guarantee specifically refers to Clause

9 of the principal agreement and it is under those circumstances, the

Hon'ble Apex Court had arrived at a conclusion that the amount covered by

the bank guarantee becomes payable and the same could be invoked only in

circumstances referred to in Clause 9 of the Principal Agreement. In the

instant case, the bank guarantee refers to two letters of intent and the

purpose of issuing the bank guarantee is to indemnify the plaintiff against

any loss or damage caused to was suffered by the Corporation by reason of

any breach or failure by the said supplier in due performance of the said

contract (meaning thereby the breach has to occur in relation to the letter of

intent specifically mentioned in the bank guarantee). The said two letters of

intent as we observed earlier contains various matters which, inter alia

include supply of plant and equipment and the bank guarantee is limited to

any loss or damage caused to or suffered by the Corporation by reason of

any breach or failure by the supplier in due performance of the said

contract. The bank guarantee also unequivocally say that the bank shall
                                       25


forthwith 'on demand' pay the Corporation any sum or sums not exceeding

the amounts mentioned in the bank guarantee without making any prior

reference to the supplier. In my view, the bank guarantee is unconditional

to the extent that on a communication received from the plaintiff that the

plaintiff has suffered loss or damage by reason of any breach or failure by

the supplier in due performance to the contract, namely supply of plant and

equipment, specified in the two letters of intent, the bank is obliged to pay

on demand the said sum without any prior reference to the defendant No.2

and without any proof of any actual loss or damage suffered by the plaintiff

due to non-performance of the aforesaid contracts. However, in the letter of

invocation, it has to state that it has suffered loss or damage by reason of

breach or failure in due performance of the said contracts, namely non-

supply or defective supply of plant and machinery, without which the bank

is not obliged to remit the amount.

      There cannot be any doubt that the first letter of invocation suffers

from defect and is not in accordance with the terms of the bank guarantee

as mentioned earlier. This has been accepted by Mr. Bose during his

argument.   However, it needs to be seen whether two subsequent letters

could be construed as a letter of invocation in terms of the bank guarantee.

I have in the earlier part of this judgment referred to the two subsequent

letters by which demand was made by the plaintiff for release of the fund

covered under the two several bank guarantees.

      I have already discussed the approach of the court in interpretation of

commercial contracts and the bank guarantee is no less than a commercial

document to be understood in the commercial sense. The intentions of the
                                         26


parties are of paramount consideration. The learned Single Judge, in our

view, has restricted its examination to Annexure U being the first letter of

invocation and has disregarded the subsequent letters and the evidence

adduced in relation to the said subsequent correspondence exchanged by

and between the parties. While I agree that contents of Annexure 'U' being

the letter of invocation of the bank guarantee was not in terms of the bank

guarantee but the subsequent invocation letters issued during the validity

period of the bank guarantees would unmistakably show that those letters

were in terms of the bank guarantees.

      After 6th November, 1998 and before 19th December, 1998, the

respondent by a letter dated 7th November, 1998 extended both the

guarantees up to 31st December, 1998 with a claim expiry date upto 30th

June, 1999, all the letters invoking the bank guarantees were within the

extended period of the bank guarantees. The said letters, in our view, need

to be read with the answer to question No. 41 in examination-in-chief and

answers Nos. 75, 76 and 77 during cross-examination.            The answers are

stated below:-

                     "41. Can you tell before My Lord, whether did the plaintiff

            invoke the Bank Guarantees?/Actually the contractor M/s. Simon

            Carves Ltd., was interested to complete of the job for the supply

            of equipment erection and commissioning and other contractual

            obligation. They have not performed as per the requirement of the

            contract. They have failed to supply the equipment. They have

            failed    to   discharge   civil   structural   works   erection   and

            commissioning and other areas of contractual obligations. They
                             27


have totally failed. Ultimately, they have left the job and left the

site also. It was taking up by the plaintiff for completion of work

and ultimately it was completed by the plaintiff and handed over

to Coal India Limited. The defendant no. 2, Simon Carves Ltd,

failed to do the job.     Due to continuous wrongful, illegal and

repeated refusal by ANZ Grindlays Bank for the claim of

encashment of bank guarantee by the plaintiff. Plaintiff had no

other alternative but to file the suit in this Court for recovery of the

dues from the bank.

         75. I am showing you clause-I of the bank guarantee being

Exbt. - 'D' kindly you have a look at paragraph 1 - it is guarantee

of performed, it is only supply of plant and machinery - is it

correct?/ This has been clarified in paragraph 2.         It is in due

performance of the contract in 6th lines of the same.

         76. I put it to you that this guarantee is only against

securing advance granted by you to Simon Carves India Ltd. for

supply of plant and machinery not for performance?/ I do not

agree.

         77. Can this guarantee by any stretch of imagination cover

the performance not relating to supply of plant and machinery?/

It must relates to performance because it is expected that the

supplier will supply the right plant and equipment as stipulated

in the contract.    But here what has happened that they have

supplied the plant and equipment, but they have not completed

their supply of plant and equipment.            Whatever they have
                                        28


            supplied,   some    of   the    plant   and   equipment   have   also

            subsequently detected as defective and the those defective

            equipment they have not replaced. So on the one hand they have

            not completed the supply on the other hand they have not

            replaced the defective plant and equipment so I consider their

            performance is not as per the stipulation of the contract."

      The learned Single Judge relied upon answer to question nos.76 and

77 and the evidence stated by the defendant in Paragraph 5 of the Written

Statement which reads:-

                   "5. The defendant states that the aforesaid two guarantees

            are not at all unconditional guarantees and can be invoked by the

            plaintiff only on the ground of loss and/or damage suffered by

            the plaintiff on account of non-supply of the plant and equipment

            by SCIL and in no other circumstances the aforesaid guarantees

            could be invoked by the plaintiff."

      However, the learned Single Judge has overlooked the other evidence

where, in our view, the plaintiff has clearly stated that the claim, inter alia,

includes a claim due to non-supply of the materials. This statement is

insufficient. The learned Single Judge has misconstrued the evidence on

record and did not take into consideration the other letters of demand where

the initial defect was cured.

      Lord Denning once has said that bank guarantee is as good as cash.

It is life blood of commerce.        The law relating to invocation of bank

guarantee is now well-settled. When in the course of commercial dealings

and unconditional bank guarantee is given the beneficiary is entitled to
                                       29


realize the amounts covered under the bank guarantee in terms thereof

irrespective of any pending dispute.       The bank giving such guarantee is

bound to honour it as per its terms irrespective of any dispute raised by its

customer. The very purpose of giving such a bank guarantee would

otherwise be defeated. The only two exceptions when the bank may refuse

encashment of the said bank guarantee are fraud and irretrievable injury.

The fraud must be of an egregious nature such has to vitiate the entire

underlying transactions.     The exceptional circumstances would include a

case where it is proved to the satisfaction of the court that the bank knows

that any demand for payment already made or which thereafter be made

would be clearly fraudulent. However, in such an event, the evidence must

be clear both as to the fact of fraud and as to the bank's knowledge. (See

Adani Agri Fresh Limited vs. Mahaboob Sharif & Ors.) reported at

(2016)14 SCC 517). The exceptional circumstance has been discussed by

one of us (Soumen Sen J.) in Rahee GPT (JV) & Ors. Vs. Union of India &

Ors. reported at 2017 SCC Online Cal 17244 in paragraphs 14 to 18 of the

said decision which read:-

              "14. There cannot be any doubt that the bank guarantee is
              unconditional in terms and on demand the bank is obliged to
              pay the aforesaid sum.        However, the special equity would
              come in since it appears prima facie that injustice would be
              caused at this stage without the issue being decided as to
              whether the contract was impossible to perform by allowing the
              defendant no.1 to appropriate the said amount during the
              pendency of the suit. The Courts in India exercise jurisdiction
              both in equity as well as at law but exercise of equity
              jurisdiction is always subject to the provisions of law. Equity
                         30


jurisdiction can be exercised only when no law operates in the
field.   Injunction is a discretionary and equitable remedy
intended to prevent injustice. The exercise of the jurisdiction
must be principled, but the criterion is injustice (see Mercedes-
Benz AG Vs. Leiduck, 1996 (1) A.C. 284)


15. The bank giving a guarantee is bound to honour it as per its
terms irrespective of any dispute raised by its customer. The
very purpose of use a bank guarantee is otherwise be
defeated.    The Courts, therefore, are extremely cautious and
slow in granting an injunction to restrain the realization of a
bank guarantee.    The Courts, however, have carved out two
exceptions, namely, fraud and irretrievable harm or injustice as
grounds on which the encashment and/or enforcement of bank
guarantee may be refused. A fraud in connection with a bank
guarantee would vitiate the very foundation of such bank
guarantee and, accordingly, if there is such a fraud of which
the beneficiary seeks to take advantage, he can be restrained
from doing so. Since in most cases payment of money under
such a bank guarantee would adversely affect the bank and its
customer at whose instance the guarantee is given, the harm or
injustice contemplated under the head of irretrievable harm or
injustice must be of such an exceptional and irretrievable
nature as would override the terms of the bank guarantee and
the adverse effect of such an injunction on commercial dealings
in the country. The two grounds are not necessarily connected,
though both may co-exist in some cases. (See Uttar Pradesh
State Sugar Corpn. Vs. Sumac International Ltd., (1997)
1 SCC 568)


16. The third exception which is of recent origin is special
circumstances or special equity which may at times overlap
                         31


with the irretrievable harm or injustice on which encashment
may be refused.


17. The limited categories on which the Court may refuse
encashment of a bank guarantee or a performance guarantee
are summarized below:-
(i)   If there is a fraud in connection with the bank guarantee
which would vitiate the very foundation of such guarantee and
the beneficiary seeks to take advantage of such fraud.
(ii) The applicant, in the facts and circumstances of the case,
clearly   establishes   a    case   of   irretrievable   injustice     or
irreparable damage.
(iii) The applicant is able to establish exceptional or special
equities of the kind which would prick the judicial conscience of
the Court.
(iv) When the bank guarantee is not invoked strictly in its
terms and by the person empowered to invoke under the terms
of the guarantee. In other words, the letter of invocation is in
apparent violation to the specific terms of the bank guarantee.


18. The exceptional cases would be few but it could never be
stated as an absolute proposition of law that under no
circumstances the Court would injunct encashment/invocation
of a bank guarantee which might have been furnished by a
party as an independent contract. A beneficiary is not vested
with an unquestionable or unequivocal legal right to encash the
bank guarantee on demand.            The obligation of the bank
furnishing the bank guarantee to pay would be subject to a
limited exceptional circumstance aforenoticed. As a matter of
rule, the bank would be under obligation to encash the bank
guarantee, once it is invoked in its terms.          The exceptions
aforenoticed are merely indicative of the kind of cases where
the Court may injunct encashment of a bank guarantee.                It is
                                       32


               neither possible nor permissible to exhaustively classify the
               cases where the Court would not interfere and where the Court
               would judicially intervene in such matters."


      The bank guarantee is an independent and separate contract and is

absolute in nature and the existence of any dispute between the parties to

the contract is of no consequence. (See Himadri Chemicals Industries

Ltd. Vs. Coal Tar Refining Co.) reported at (2007) 8 SCC 110, Mahatma

Gandhi Sahakra Sakkare Karkhane Vs. National Heavy Engg. Coop.

Ltd. & Anr. reported at (2007) 6 SCC 470), BSES Ltd. (Now Reliance

Energy Ltd.) Vs. Fenner India Ltd. & Anr. reported at (2006)2 SCC 728

and Gangotri Enterprises Limited Vs. Union of India & Ors. reported at

(2016)11 SCC 720.

      On consideration of the evidence on record and the judicial decisions

with regard to the interpretation of the bank guarantee, I am of the opinion,

that the bank guarantees were properly invoked in law and the judgment

needs to be set aside.

      Accordingly, the judgment and decree passed on 15th October, 2016 is

set aside.   There shall be a decree for Rs.1,10,33,207.00/- as claimed in

Paragraph 18 of the Plaint together with interest at rate of 8 per cent per

annum on and from the date of institution of the suit till payment.

      Urgent Photostat certified copy of this judgment, if applied for, be

given to the parties on usual undertaking.



                                                         (Soumen Sen, J.)
                                  33




Ravi Krishan Kapur, J.

1. I have had the advantage of reading the draft judgment of my Learned Brother Justice Sen. Though I am in full agreement with the conclusion arrived at by my Learned Brother, I would add a few reasons of my own.

2. This is one of those rare cases where a suit for enforcement of a bank guarantee has ultimately gone to trial.

3. The instant appeal has been preferred against the judgment and decree dated 16.09.2015 ("the impugned decree") passed in CS 38 of 2000 by a Learned Judge of this Court. By the impugned decree the Learned Judge has inter alia dismissed the suit as against the defendants. The suit is filed for recovery of money arising out of two separate bank guarantees.

4. The facts of the case are more or less indisputable and uncontested and the only question that arises for consideration is one of interpretation and construction. The case of the plaintiff as alleged in the plaint is that, the plaintiff is engaged in effecting design, supply and construction of industrial plants. In the course of business, the plaintiff was awarded a contract for, design, engineering supply erection and commission of the Dankuni Coal Complex by Coal India Ltd. By a letter dated 19.05.1981, the plaintiff placed an order on SCIL India Ltd. (formerly known as Simon Carves India Ltd. and hereinafter referred to as "SCIL") for 34 the complete design, supply erection and commissioning of requisite civil and construction works with a few minor exceptions. Pursuant to the letter of the intent, a formal Memorandum of Agreement dated 08.08.1985 was executed by and between SCIL. Thereafter, the plaintiff from time to time advanced an aggregate sum of Rs.3,44,56,600 for the said works against several bank guarantees furnished by SCIL. The instant suit pertains to two written guarantees being guarantee No.1001/83/108/G dated 16.02.1983 and guarantee No.G/1001/84/608 dated 29.08.1984 (hereinafter referred to as "the said guarantees") for the sums of Rs.71,35,100 and Rs.20,32,500 respectively which were advanced to SCIL. The said guarantees furnished by the defendant bank were extended from time to time and revalidated. It is alleged in that plaint that, in breach of contract with the plaintiff, SCIL failed and neglected to duly complete the supply of equipment and the erection and commission of the same and further supplied defective equipment. Subsequently, the work had to be abandoned. In the premises, the plaintiff suffered huge losses and damages. Ultimately, a sum of Rs.139.90 lakhs was deducted from the plaintiff's final bill which pertained to the apportioned work handed over to SCIL.

5. In view of the aforesaid, by a letter dated 06.11.1998, the plaintiff demanded encashment of both the said guarantees. The defendant bank refused to honour the said guarantees and diverse 35 correspondence was exchanged by and between the plaintiff and the defendant bank. The plaintiff made subsequent demands for encashment of the guarantee by letters dated 19.12.1998 and 28.12.1998 respectively. The plaintiff also complained by way of a letter 22.02.1999 to the Banking Ombudsman, Calcutta. Ultimately, the plaintiff was constrained to file the instant said suit for a decree of Rs.1,10,33,2207.07 along with interest being the aggregate sum of both the said guarantees.

6. The defendant bank filed its written statement and primarily took the defence that the invocation of the plaintiff of both the guarantees was not in accordance with either of the said guarantees and contrary to the terms thereof. Accordingly, the defendant bank was not liable to make payment to the plaintiff under either of the said guarantees. In paragraph 5 of the written statement, it is particularly alleged by the defendant bank that the said guarantees are not unconditional and could be invoked only on the ground of loss or damage suffered by the plaintiff on account of non-supply of plant and equipment by SCIL and under no other circumstances. The defendant bank also referred to the diverse correspondence exchanged between the plaintiff and the defendant bank. In brief, the primary defence of the defendant bank was that the invocation of the said bank guarantees was contrary to their terms or not in terms thereof.

36

7. In the above mentioned background, the following issues were framed by the Trial Court:

i.) Is the plaintiff entitled to invoke two bank guarantees being no.1001/83/108/G dated 16.02.1983 and G/1001/84/608 dated 29.08.1984?
ii.) Is the plaintiff entitled to a decree for Rs.1,10,33,207 against the defendant no.1?
iii.) Is the defendant no.1 entitled to challenge the validity of the invocation of the two bank guarantees?
iv.) Is the plaintiff entitled to a decree for further interest pendent lite and interest upon judgment as claimed?
v.) What relief, if any, is the plaintiff entitled to?

8. There was only one witness examined on behalf of the plaintiff. The defendant chose not to adduce any evidence at all. One Mr. Shankar Kumar Chakraborty, who was the General Manager, Finance of the plaintiff company came to depose on behalf of the plaintiff. He deposed that the contractor SCIL failed to perform its job and did not supply equipment for erection and commission and was also in breach of diverse other contractual obligation (Q. 41). He exhibited most of the letters which had been exchanged by the plaintiff and the defendant bank pertaining to invocation of both the bank guarantees. In cross-examination, he deposed that the said bank guarantees covered not only supply of plant and machinery but also their performance (Q. 75). He deposed that 37 though SCIL supplied some of the plant and equipment the same were detected to be defective and SCIL had not replaced the same (Q. 77). He denied the suggestions that the bank guarantee could only be invoked for failure to supply the plant and machinery and in respect of their performance (Q.78).

9. By the impugned decree, the Learned Judge held that on a perusal of the contents of the letter dated 06.11.1998 bank (Exhibit U), the invocation of the bank guarantees by the plaintiff was not in terms of either of the said guarantees. The Learned Judge further held that the plaintiff had failed to make out a case against the defendant bank upon notice of the defence as stated in the paragraph 5 of the written statement. In view of the above, the Learned Judge found issue no.1 in favour of the plaintiff, issue no.3 in favour of the defendant bank and issue nos.4, 2 and 5 against the plaintiff. In the circumstances, the Learned Judge dismissed the suit filed against the defendant no.1 and with costs against the defendant no.2. It is pertinent to mention that the defendant no.2, SCIL was in liquidation and was represented by the Official Liquidator.

10. During the pendency of the suit, in an application for summary decree, conditional leave was granted to the defendant bank to defend the suit subject to the defendant bank making payment of the amount covered under the aforesaid two guarantees to the plaintiff. Furthermore, the plaintiff was directed to make a fixed 38 deposit in its name with the defendant bank in a long term suitable interest bearing deposit to be renewed from time to time. The original receipts of these fixed deposits were to be submitted to the Registrar Original Side of this Hon'ble Court.

11. Counsel on behalf of the appellant argued that the impugned decree was liable to be set aside on the ground that the Learned Judge erred in passing the impugned decree both in law and on facts. He submitted that in passing the impugned decree the Learned Judge erred in his appreciation of the law on bank guarantees. He submitted that the Learned Judge gave no reasons in passing the impugned decree. He further submitted that on a construction of the correspondence exchanged by and between the parties pertaining to invocation of the said bank guarantees read along with the letters dated 06.11.1998, 07.11.1998, 18.11.1998, 28.11.1998, 07.12.1998 and 19.12.1998, it would be evident that the invocation of the said bank guarantees was in terms thereof and that the plaintiff was entitled to a decree as prayed for.

12. Counsel on behalf of the defendant bank, submitted that the impugned decree was justified both in law and on facts and the instant appeal was liable to be dismissed. He submitted that the invocation of either of the said bank guarantees by the plaintiff was not in terms thereof and the bank was fully justified in not honouring the same. He placed reliance on the decision reported in Hindustan Construction Ltd. vs. State of Bihar AIR 1999 SC 39 3710 and PerryLease Ltd. vs. ImeCar AG and Others [1987] 2 ALL.E.R 373. He submitted that the principles of construction covering contracts in general are equally applicable to contracts of guarantee. He submitted that as a proposition of law, an invocation of a bank guarantee has to be in accordance with the terms thereof otherwise the invocation was bad in the law.

13. The primary issue raised in this appeal pertains to the construction of the said bank guarantees and the correspondence exchanged by and between the parties pertaining to invocation of the same. In this background, it is important to set out clause 1 and 2 of the said bank guarantees which are identical in nature. Clauses 1 and 2 which are similar (except for the amounts) in the said bank guarantees provide as follows:

i) In consideration of Messrs Heavy Engineering Corporation Limited a Government of India Enterprise, a Company registered under the Companies Act (hereinafter called the Corporation) having agreed to accept a Bank Guarantee from Messrs Simon Carves India Limited, Simon House, Transport Depot Road, Calcutta 700027 (hereinafter called the Supplier) on account of Advance Payment of a sum of Rs.71,35,100/- (Rupees Seventy One Lakhs Thirty Five Thousand and One Hundred Only) as advance against Supply of Plant and Equipment by the Corporation to Messrs Simon Carves India Limited in terms of Letter of Intent No.HEC/CS/1502/81 dated 19.05.1981.
ii) We, Grindlays Bank P.L.C., 19, Netaji Subhas Road, Calcutta-700001 do hereby undertake the Indemnity and keep the Corporation indemnified to the extent of Rs.20.32,500/- (Rupees Twenty Lakhs Thirty Two Thousand Five Hundred Only) against any loss or damage caused to or suffered by the Corporation by reason or any breach or failure by the said Supplier, in due performance of the aforesaid contract, we shall 40 forthwith on demand pay to the Corporation any sum or sums not exceeding Rs.20,32,500/- (Rupees Twenty Lakhs Thirty Two Thousand Five Hundred Only) without making any prior reference to the said Supplier with an exclusion of any action in Court by Supplier.

14. The principles applicable to bank guarantees are well settled. The aim of the bank guarantee is to secure payment by substituting a "reliable pay master". A contract of guarantee, in its true sense, is a contract whereby the guarantor promises the creditor to be responsible, in addition to the principal for the due performance by the principal of his existing or future obligations to the creditor, if the principal fails to perform those obligations. In Halsbury's Laws of England : it has been defined that "a guarantee is an accessory contract by which the promisor undertakes to be answerable to the promissee for the debt, default or miscarriage of another person, whose primary liability to the promissee must exist or be contemplated." (5th Edition, Para 1013).

15. There are various kinds of bank guarantees which cover a great deal of contingencies. There are bipartite and tripartite guarantees. There are continuing and limited guarantees. Although it is common for a guarantee to be limited in operation, a guarantee may also be entered into for an indefinite period. A continuing guarantee is one which extends to a series of transactions, whether or not over a limited period. A guarantee may in terms refer only to 41 the obligations arising under an identified contract or even to a specific obligation. Then, there are guarantees payable on demand. A guarantee may contain an express stipulation that the surety is liable to make payment to the creditor "on demand". In such an event, the obligation of the guarantor to pay does not arise until the demand has been made on him though his underlying liability arises on the date of the principal's default. The demand is usually construed as a procedural requirement included for the guarantor's protection. Then, there are guarantees which are limited in amount. The limitation may take effect in one or two different ways. The guarantee may be in respect of the whole of the liability, but with a limitation on the amount for which the surety is to be liable. Alternatively, it may cover only part of the total liability, co- extensive for the amount of guarantee. It is a question of construction in each case which form a guarantee takes. (Law of Guarantees, Geraldine Andrews & Richard Millett, 7th Edition).

16. In practice, demand guarantees, performance bonds, performance guarantees and standby letters of credits have a similar legal character and resemble documentary credits in that they are primary in form, and generally conditional upon presentation of a written demand for payment together with any other stipulated documents. It is well settled that the issuing bank is not concerned as to whether there has been any actual default or fault on the part of its principal. In the classic words of Hirst, J in 42 the decision reported in Sitorex Trade SA vs. Banque Indosuez [1986] 2 Lloyd's Law Reports 146 the Learned Judge held that "the whole commercial purpose of a performance bond is to provide a security which is to be readily, and promptly and shortly available when the prescribed events occurred". It was Donaldson L.J, who had said "irrecoverable letters of credit and bank guarantees given in circumstances such that they are equivalent to an irrecoverable letter of credit had been said to be the life blood of commerce(emphasis supplied). Thrombosis will occur if, unless fraud is involved the courts intervene and thereby disturb the mercantile practice of treating rights thereunder as being equivalent to cash in hand". (Intraco Ltd. vs. Notis Shipping Corporation of lybraria :the Bhoja Trader [1981] 2 Lloyd's Rep at 257).

17. There are various other considerations which apply to bank guarantees. In particular, the principles of the autonomy of the bank's undertakings (mandate) and the application of doctrine of strict compliance was considered in IE Contractors Ltd. Vs. Lloyd's bank PLC[1989] 2 Lloyd's Report in 205 at 207 where Leggatt J, stated that "the demand must conform strictly in the terms of bond in the same way that the documents tendered under a letter of credit must conform strictly with the terms of the credit". However, it has been repeatedly reiterated that the application of the principle of strict compliance depends in each case upon the construction of the guarantee or the bond and that 43 the condition specified in each case must be strictly adhered to. There are also the well-known exceptions to the rule that the bank must honour its undertakings subject to the exception of fraud and special equity which have been discussed in a catena of decisions.

18. In Blest v Brown (1862) 4 De G.F. & J. 367 at 376, Lord Campbell stated: "It must always be recollected in what manner a surety is bound. You bind him to the letter of his engagement. Beyond the proper interpretation of that engagement you have no hold upon him. He receives no benefit and no consideration. He is bound, therefore, according to the proper meaning and effect of the written agreement he has entered into." Subsequently, Stanley Burnton, J in the case of Barclays Bank v Kingston [2006]2 Llyods Report 59 held that "a guarantee should be construed as a whole as a commercial document to give it a sensible meaning." The more recent cases adopt a business common sense approach whilst interpreting a guarantee. In Investors Compensation case and Chartbrook Ltd v Persimmon Homes Ltd [2009] UKHL 38 it was held that "...the ultimate aim of interpreting a provision in a contract, especially a commercial contract, is to determine what the parties meant by the language used, which involves ascertaining what a reasonable person would have understood the parties to have meant...[T]he relevant reasonable person is one who has all the background knowledge which would have reasonably have been 44 available to the parties in the situation in which they were at the time of the contract."

19. In India, the law relating to bank guarantees has been repeatedly reiterated by all the Courts including the Hon'ble Supreme Court. In National Highway Authority of India vs. Ganga Enterprises and Another (2003)7 SCC 410 it has been held at paragraph 10 as follows:

The law regarding enforcement of an "on-demand bank guarantee" is very clear. If the enforcement is in terms of the guarantee, then courts must not interfere with the enforcement of bank guarantee. The court can only interfere if the invocation is against the terms of the guarantee or if there is any fraud. Courts cannot restrain invocation of an 'on-demand guarantee" in accordance with its terms by looking at the terms of the underlying contract. The existence or non-existence of an underlying contract becomes irrelevant when the invocation is in terms of the bank guarantee.

20. In U.P State Sugar Corporation vs. Sumac International Ltd. (1997)1 SCC 568 it has been held at paragraph 12 as follows:

The law relating to invocation of such bank guarantees is by now well settled. When in the course of commercial dealings an unconditional bank guarantee is given or accepted, the beneficiary is entitled to realize such a bank guarantee in terms thereof irrespective of any pending disputes. The bank giving such a guarantee is bound to honour it as per its terms irrespective of any dispute raised by its customer. The very purpose of giving such a bank guarantee would otherwise be defeated. The courts should, therefore, be slow in granting an injunction to restrain the realization of such a bank guarantee. The courts have carved out only two exceptions. A fraud in connection with such a bank guarantee would vitiate the very foundation of such a bank guarantee. Hence if there is such a fraud of which the beneficiary seeks to take advantage, he can be restrained from doing so. The second exception relates to cases where allowing the encashment of an unconditional bank guarantee would result in 45 irretrievable harm or injustice to one of the parties concerned. Since in most cases payment of money under such a bank guarantee would adversely affect the bank and its customer at whose instance the guarantee is given, the harm or injustice contemplated under this head must be of such an exceptional and irretrievable nature as would override the terms of the guarantee and the adverse effect of such an injunction on commercial dealings in the country.

21. In General Electric Technical Services Co. Inc. v. Punj Sons (P) Ltd. [(1991) 4 SCC 230] it has also been held that:

"[T]he Bank must honour the bank guarantee free from interference by the courts. Otherwise, trust in commerce internal and international would be irreparably damaged. It is only in exceptional cases that is to say in case of fraud or in case of irretrievable injustice, the court should interfere. ... The nature of the fraud that the courts talk about is fraud of an 'egregious nature as to vitiate the entire underlying transaction'. It is fraud of the beneficiary, not the fraud of somebody else."

22. The aforesaid principles have been repeatedly recognized and followed in numerous decisions of the High Courts as well as the Supreme Court.

23. The main contention of the defendant bank was that the letter of invocation did not stipulate that the loss or damage had occurred pertaining to the supply of plant and equipment. Moreover, it was contended on behalf of the defendant bank that the guarantee did not extend to the obligation of performance under the contract for supply of plant and equipment.

24. In the light of the aforesaid principles, the only question which arises for consideration is whether the plaintiff had invoked the guarantee in terms thereof. On a bare perusal of either of the 46 guarantees as a whole, it appears that the same covered advance against supply of plant and equipment. Moreover, Clause 2 of the guarantee clearly and categorically contemplates loss or damage caused or suffered by the plaintiff by reason of any breach or failure by SCIL in due performance of the aforesaid contract. The nature of guarantee given by SCIL, the defendant no.2 is peculiar, inasmuch as the said guarantees were given to the plaintiff to indemnify the plaintiff to the extent of the amount of advance which had been paid by the plaintiff to the defendant no.2.

25. As a proposition of law, I am of the view that the entire correspondence exchanged by and between the plaintiff and the defendant bank has to be construed as a whole to ascertain the real intention and understanding of the parties as expressed by them in writing. Moreover, in interpreting the contract of guarantee and the letters exchanged by and between the parties in invoking the guarantee, a business common sense approach ought to be adopted.

26. I am also of the view that, the guarantees in the instant case were conditional guarantees, specific in nature and limited in amount. The terms of the guarantee categorically covered money which the plaintiff had advanced against supply of the plant and equipment by SCIL. Moreover, the said guarantees covered any loss and damage caused to or suffered by the plaintiff in due performance of the contract for supply of plant and equipment. 47

27. I am of the view that reading the guarantee document as a whole and in particular, Clauses 1 and 2 of the guarantee document, it would be evident that the guarantees were to cover the advance which had been paid by the plaintiff against supply of plant and equipment to SCIL. The said guarantees also covered loss or damage caused to or suffered by the plaintiff by reason of any breach or failure by SCIL in due performance of the aforesaid contracts i.e. against the contract for supply of plant and equipment.

28. In order to examine the invocation by the plaintiff of the said guarantees, it is important to ascertain the intention of the parties from the correspondence that has been exchanged by and between them pertaining to invocation of the said guarantee. The initial letter of invocation was written by the plaintiff dated 6.11.1998 (Exhibit U). This letter per se was inadequate and did not enumerate any condition for invocation of the said guarantees save and except a reference to "a substantial amount to be recovered from SCIL". However, what is important is the correspondence that was thereafter exchanged between the parties. By a letter dated 18.11.1998 (Exhibit W), the defendant bank categorically informed the plaintiff that the guarantees were specifically issued covering the advance made by the plaintiff to SCIL "for supply of plant and equipment." Accordingly, since the guarantee has not been invoked on account of non-supply of plant and equipment, the defendant bank was not liable to make payment under the said guarantee. 48 Thereafter, by an elaborate letter dated 28.11.1998 (Exhibit X), the plaintiff spelt out in detail the ground for encashment of the bank guarantee, the terms of the bank guarantee and the fact that loss and damage had been suffered by the plaintiff by SCIL not discharging its contractual obligations.

29. By a further letter dated 7.12.1998 (Exhibit Y), the defendant bank reiterated that the guarantee was limited only against failure by SCIL to supply plant and equipment and did not cover performance of the contract. This was followed by a letter dated 19.12.1998 (Exhibit Z), by the plaintiff, inter alia, informing the defendant bank that due to defective supply of plant and equipment as well as non-supply of plant and equipment and also other contractual deficiencies of SCIL, losses had been suffered by the plaintiff.

30. In the deposition adduced on behalf of the plaintiff, the sole witness of the plaintiff categorically deposed in examination-in- chief that since SCIL had failed to supply equipment, erection and commissioning and other contractual obligations as per the contract, the plaintiff had suffered loss and damages (Question 41). In cross-examination, the witness further deposed that there was failure on the part of SCIL in supplying the plant and equipment and that SCIL had not completed the supply of plant and equipment under the contract. Moreover, the plant and equipment supplied by SCIL was detected as defective and this was not replaced by SCIL. Thus, the plaintiff had duly informed the 49 defendant bank that losses had been incurred both on account of supply of plant and equipment and on account of performance of the supply of plant and equipment.

31. I am of the view that, on a proper reading of the letters exchanged by and between the plaintiff and the defendant bank pertaining to invocation of the said guarantees, the conditions of the guarantee had been duly complied with and I find that there was proper and lawful invocation of the said guarantees by the plaintiff. Moreover, the oral evidence given on behalf of the sole witness of the plaintiff categorically confirmed that the said guarantees were invoked on the ground of non-supply of plant and equipment and this covered not only failure to supply but also performance of such plant and equipment.

32. Accordingly, I find that the Trial Court erred in passing the impugned judgment and decree. I also find that the defendant bank was not entitled to challenge the validity of the invocation of the said guarantees and the defendant bank should have made payment of the said amounts covered under the two guarantees in terms of the letters exchanged between the parties.

33. I am of the view, that the fact that defendant no.3 had gone into liquidation and the defendant bank was most probably not covered are oblique and extraneous reasons for the defendant bank not honouring either of the said guarantees. I am of the view that on adopting a proper business and commonsense approach, it would be evident from the correspondence exchanged by and between the 50 plaintiff and the defendant bank pertaining to invocation of the two guarantees and the evidence adduced on behalf of the plaintiff that any reasonable person would appreciate what the parties meant both at the time of entering into of the contract and at the time of invocation of the said guarantees.

34. I find no merit in the submission made on behalf of the defendant bank that save and except the letter of invocation dated 6.11.1998 being Exhibit 'U' to the proceeding, the subsequent correspondence exchanged between the parties pertaining to the invocation of the said guarantee could not have been looked into. It is now well-settled that merely because the exact words about loss or damage were not employed in the first invocation, a party is not precluded from re-invoking the bank guarantee by way of subsequent correspondence. ('H. Mitra Pvt. Limited &Anr. vs. United Bank of India & Ors.' 2010 SCC Online Cal 138).

35. I also find merit in the argument of the appellant that the learned Judge in passing the impugned judgment and decree did not assign any reasons whatsoever. It is now well-settled that judicial orders need to meet the twin tests of "why" and "what". It is the "why" that sustains the "what". Reasons are the safeguard against the ipsi dixit of the decision making process. They discuss how the judicial mind has been applied to the matter in issue and convey the nexus between the matters that have been considered and the conclusion based thereon. The justification and the reasonableness of a conclusion depend on the reasons given in 51 support thereof ('Uniworth Resorts Limited vs. Ashok Mittal & Anr.' (2007) 4 CHN 712). I am of the view that the impugned judgment and decree has no element of "why" for the "what" therein to stand on.

36. For the foregoing reasons I concur with the conclusions of Justice Sen.

(Ravi Krishan Kapur, J.)