Section 10 in Rajasthan Electricity Regulatory Commission (Distribution Licensees Standards of Performance) Regulations, 2003
10. Release of New Electric Connection.
| S.No.1 | Item/Activity2 | Time Limit (Within)3 |
| 1. | Loads up to 60 HP | |
| Issue of Demand Notice | Within 21 days of receipt of application | |
| Release of connection. | Within 30 days after compliance of formalities/demand notice,if no augmentation is required otherwise 45 days. | |
| 2. | Loads up to 60 HP and up to 300 KW | |
| Issue of Demand Notice | Within 30 days of receipt of application. | |
| Release of connection. | Within 60 days after compliance of Demand Notice. | |
| 3. | Loads above 300 KW and up to 3000 KW. | |
| Issue of feasibility clearance. | Within 45 days of receipt of application. | |
| Issue of Demand Notice | Within 60 days of receipt of application. | |
| Release of connection | Within 75 days after compliance of Demand Notice/formalitiesby prospective consumers. | |
| 4. | Loads above 3000 KW and up to 33 KV Supply. | |
| Issue of feasibility clearance. | Within 45 days of receipt of application. | |
| Issue of Demand Notice | Within 60 days of receipt of application | |
| Release of connection. | Within 90 days after completion of Demand Notice/formalitiesby prospective consumers. | |
| 5. | 132 KV and higher voltage supply. | |
| Issue of feasibility clearance. | Within 90 days of receipt of application. | |
| Issue of Demand Notice | Within 120 days of receipt of application. | |
| Release of connection. | Within 90 days after completion of Demand Notice/formalitiesby the applicant if no forest clearance is involved. |