Legal Document View

Unlock Advanced Research with PRISMAI

- Know your Kanoon - Doc Gen Hub - Counter Argument - Case Predict AI - Talk with IK Doc - ...
Upgrade to Premium
[Cites 15, Cited by 0]

Gujarat High Court

Oswal Machinery Ltd vs Pipavav Shipyard Ltd on 23 June, 2014

Author: S.R.Brahmbhatt

Bench: S.R.Brahmbhatt

           O/OJMCA/54/2014                                           ORDER




           IN THE HIGH COURT OF GUJARAT AT AHMEDABAD

                MISC. CIVIL APPLICATION  NO. 54 of 2014
                                  In
                 COMPANY PETITION NO.  170 of 2010

======================================
          OSWAL MACHINERY LTD....Applicant
                      Versus
         PIPAVAV SHIPYARD LTD....Respondent
======================================
Appearance:
MR ASHWIN L SHAH, ADVOCATE for the Applicant
NANAVATI ASSOCIATES, ADVOCATE for the Respondent
======================================

          CORAM: HONOURABLE MR.JUSTICE S.R.BRAHMBHATT
 
                               Date : 23/06/2014
 
                                   ORAL ORDER

1. Heard learned advocate for the  parties.   The applicant in  this application happens to be petitioner in Company Petition no.170 of  2010 and has prayed for winding­up of the opponent company.  On 9 th  March,   2012   learned   single   Judge   of   this   Court   passed   an   order   in  Company Petition No.170 of 2010, wherein in the operative part it was  observed   that   the   respondent  company   was  granted   four  weeks'   time  from the receipt of the order or until 25th  April, 2012 whichever was  earlier   for   depositing   the   invoice   amount   covered   by   three   invoices  raised by the petitioner.  Thus, while passing the said order, this Court  deferred on advertisement.  This order of learned single Judge dated 9 th  March, 2012 passed in Company Petition No.170 of 2010 was carried  into appeal being O.J. Appeal No.26 of 2012 and in initial stage of the  appeal, the order of learned single Judge was stayed.  However, as per  the record, the company deposited the invoice amount on 9 th  October,  2012 and recording these facts on 12 th March, 2014 the O.J. Appeal was  Page 1 of 16 O/OJMCA/54/2014 ORDER requested   to   be   disposed   of   as   having   become   infructuous   and  accordingly   the   said   appeal   came   to   be   disposed   of   as   become  infructuous   under   order   dated   12th  March,   2014.     The   present  application is taken­out by the original petitioner for withdrawal of the  said amount, which came to be deposited by the company respondent  hereinabove,   on   furnishing   appropriate   security   as   the   petitioner  happened to be in need of funds and on account of its poor financial  problem.

2. Learned counsel appearing for the applicant, relying upon  the   order   of   the   learned   single   Judge,   contended   that   the   amount  deposited under the order of learned single Judge may be permitted to  be withdrawn by the applicant on appropriate terms and conditions, as  the amount would otherwise be lying idle and would be of no help to  anyone.     Learned   counsel   relied   upon   the   facts   and   the   discussion  narrated under the order of the learned single Judge and contended that  the filing of  the  suit by the  present applicant was for  the  purpose  of  recovery of their dues and the same is pending, but this fact cannot be  said to be a valid ground for denying disbursement of the said amount in  favour of the applicant.   Learned counsel for the applicant, therefore,  submitted that the petition is pending and is also for seeking appropriate  relief including winding­up of the company and Court may therefore,  pass appropriate order atleast so far as the withdrawal is concerned in  this application.

3. Learned   advocate   appearing   for   the   opponent   ­   original  respondent   company   submitted   that   the   winding­up   petition   and  proceedings thereunder cannot be said to be proceedings so as to permit  the applicant to receive the amount deposited by the company.  

4. Learned   advocate   appearing   for   the   opponent,   contended  Page 2 of 16 O/OJMCA/54/2014 ORDER that the winding­up petition is still pending and the company has taken­ up appropriate pleadings qua existence of dispute, which was a result for  not releasing the amount in favour of the applicant.

5. Learned advocate appearing for the opponent, invited this  Court's attention to the observation of the learned single Judge made in  para no.17.1 of the order of the learned single judge dated 9 th  March,  2012 and submitted that the order of the learned single Judge was based  upon the record and proceedings available at that stage and therefore,  learned single Judge has observed in para no.17.1 that "The aforesaid  aspect is also evident from the fact that though the petitioner issued three   invoices   in   month   of   February   2008,   until   May   2010,   the   respondent   company never raised any grievance with reference to the said grievance and   never   objected   the   said   invoices   until   (the   petitioner's   third   intimation­ demand served after the service of three invoices) 4th  May, 2010 and it is   only on 4th May, 2010 the petitioner company came out with aforesaid reply.   (It should be respondent) The fact that the respondent has come­out with an   afterthought, dispute is also evident from the fact that the respondent has   availed CENVAT & VAT credit."

6. Learned counsel appearing for the opponent, relying upon  this   observation   submitted   that   after   the   said   order   was   passed,   the  company   could   locate   e­mail   exchanges   between   the   company   and  original petitioner­ applicant hereinabove and the same would show that  infact   the   company   did   raise   objections   and   grievances   qua   non­ fulfillment   of   contractual   obligation   on   the   part   of   the   applicant,  therefore, now when this Court is examining the issue and prayers for  disbursement, these exchanges may be taken into consideration.

7. Learned   advocate   appearing   for   the   opponent   company  invited this Court's attention to page no.155, which happened to be the  Page 3 of 16 O/OJMCA/54/2014 ORDER first page of additional affidavit on behalf of respondent and submitted  that on page no.156, the e­mail exchanges, as many as five, which have  been produced as Annexed­A collectively to their affidavit, would clearly  indicate  that  the  dispute   qua non­fulfillment of contractual  obligation  was   very   much   existing   and   on   that   ground   alone,   there   was   no  tenability in the prayer for winding­up of the company.

8. Learned counsel for the applicant, extensively read the e­ mail exchanges from page no.158 to 167 and submitted that the contract  on which the invoices were raised, did not leave­out the erection and  commissioning of pay in question.  Infact, as per the work order and the  subsequent contract and e­mail exchanges between the parties, would  clearly indicate that there was consistent reminder to the petitioner for  completing   the   contractual   obligation   and   handover   the   fully  commissioned  cranes  after   its   repair.     This   commissioning   work   was  required to be assigned to some other agency, as the petitioner did not  do it and hence, the dispute, which was raised qua non­fulfillment of  contract may weigh with this Court in not permitting the disbursement  of the amount, which is deposited in this Court under the order dated 9 th  March, 2012.

9. Learned   counsel   appearing   for   the   opponent   company,  contended that the aforesaid facts, as could be seen from page no.158 to  167 of the main petition and the fact that the summary suit is already  filed and it is awaiting its final disposal, this Court may not dispose of  the amount or may transfer the amount to the Court, wherein summary  suit is pending and the disbursement of the amount be made subject to  final out­come of the summary suit and the winding­up petition itself be  dismissed as it is not tenable on account of the genuine dispute pending.

10. This Court is of the view that the application is required to  Page 4 of 16 O/OJMCA/54/2014 ORDER be disposed of and the prayer for disbursement of the amount deposited  in the Court pursuant to order dated 9 th  March, 2012 is required to be  allowed, on applicant furnishing appropriate security for refunding the  said   amount   in   case   of   any   adverse   outcome   in   the   winding­up  proceedings, for the following reasons i.e.      

(i) The order dated 9th  March, 2012 passed by learned single  Judge   contains   very   vital   observations   and   findings,   which   are   based  upon   the   pleadings   and   proceedings   before   the   Court.     Those  observations are required to be set­out hereunder.   

4. In response to the notice issued under the order passed   by   the   Court   after   hearing   the   petitioner   the   respondent   company   entered appearance and resisted the petition by filing reply affidavit.   In its reply affidavit the respondent company has, while dealing with   the assertions and allegations of the petitioner company, stated, inter   alia, that:

12. ........the   respondent   was   desirous   of   getting  repair, erection and commissioning of Gantry cranes - 2   nos., which were lying unused at its factory premises. The  prime concern of the respondent was to bring to use the   said cranes for its manufacturing activities. On the other   hand,   the   petitioner   was   desirous   of   starting   business  relations with the respondent, as the respondent company  enjoys good name and fame in the market of ship­building.  

Accordingly,   after   discussions,   the   respondent   company  placed   a   LOI   envisaging   the   exact   details   of   work   to   be   undertaken   by   the   petitioner,   which   was   agreed   and   accepted by the petitioner without any dispute or demur.   The  LOI   clearly   envisaged  the   job  description  which   was  "repair and erection and commissioning" of the cranes. It is   empathetically   submitted   that   the   prime   object   of   the   respondent was to put the cranes in use, and therefore, the   work of erection and commissioning of the cranes was as   important and integral part of LOI as that of the work of   repairs.   The   petitioner   had   agreed   to   undertake   the   job  which was clearly described in the LOI. It is submitted that   as  per   LOI,  the   petitioner  was  supposed  to   complete  the   work of first crane within 6 weeks from the date of start of   Page 5 of 16 O/OJMCA/54/2014 ORDER the   work   and   thereafter,   the   second   crane   in   2   weeks.  Therefore,   time   was   the   essence   of   the   contract,   as   the   functioning   of   the   cranes   had   direct   nexus   with   the   manufacturing activities of the respondent Company.

14. It   is   further   submitted   that   in   its   letter   dated   4.5.2010,   the   respondent   had   stated   that   though   after   carrying   out   the   repairs,   it   was   incumbent   upon   the   petitioner   to   depute   service   engineers   at   the   site   of   the   respondent company to complete the remaining work and   to make the cranes commissioned and operational but the   petitioner   miserably   failed   in   doing   so.   It   was   also  informed  that   power   supply  was   never  restricted   and/or  refused   or   not   made   available   to   the   petitioner.   As   a   manner   of   fact,   since   the   petitioner   did   not   carry   out   proper repairs of the cranes and did not bring the same to   operational state, the respondent company had to get the   incomplete   work   completed   by   appointing   other   agency   named Hebenkraft, to which, the respondent company had   to   pay   an   amount   of   approximately   Rs.23,00,000/­  excluding taxes for the work, which otherwise was to be   completed by the petitioner."  

5. Subsequently the respondent company filed additional   affidavit, particularly to place on record certain documents and details   in support of the factual aspects mentioned in its earlier affidavit. In   para   2   of   the   said   additional   affidavit   the   respondent   company   mentioned that:

"2. I state that I am filing the present affidavit only  for the limited purpose of placing on record of the petition   the documents related to the entrustment of work of repair  and erection of two Gantry cranes to a third party viz. M/s.   Hebankraft,   Thane,   Maharashtra.   The   said   work   was  required   to   be   entrusted   to   the   said   agency,   as   the   petitioner,   who   was   entrusted   the   said   work,   did   not   complete the work of repairs, erection and commissioning   of   the   cranes   successfully   and   to   the   satisfaction   of   the   respondent." 

7. ......The learned counsel for the petitioner relied on following   judgments:

(1)        The decision of the Calcutta High Court in the case   of   Hind   Hosiery   Mills   Pvt.   Ltd.   v.   Anand   Chemicals   Co.

[(2003) 115 Company Cases 739].

Page 6 of 16
      O/OJMCA/54/2014                                                     ORDER



      (2)      The decision of the Patna High Court in the case  
      of   Central   Bank   of   India   v.Sukhani   Mining   and 

Engineering Industries Pvt. Ltd. [(1977) 47 Company Cases   1].

(3) The decision by the Madras High Court in case of   Hoe   Leong   Corporation   Ltd.   v.   Vaishnovi   Infrastructure   Engineering P. Ltd. [(2011) 167 Company Cases 324.

(4) The   decision   of   the   Apex   Court   in   the   case   of   Madhusudan   Gordhandas   and   Co.   v.   Madhu   Woollen  Industries Pvt. Ltd. [(1972) 42 Company Cases 125].

(5) The decision by the High Court of Delhi in case of   Hotline Teletubes and Components Ltd. v. A.S.Impex Ltd.  [(2004) 1 Company Law Journal 412].

(6) The decision by the High Court of Delhi in the case   of Karam Chand Thapar & Bros. (Coal) Sales Ltd. v. Acme   Paper Limited [(1994) 1 Company Law Journal 274.

(7) The   decision   by   the   Apex   Court   in   the   case   of   Haryana   Telecom   Ltd.   v.   Sterlite   Industries   (India)   Ltd.   [(1999) 97 Company Cases 683.

(8) The decision by the Andhra Pradesh High Court in  the   case   between   Fibex   Inc.   v.   A.B.K.   Publications   Ltd.   [(1999) 97 Company Cases 947].

(9) The decision by the High Court of Delhi in the case   of   V.K.Jain   v.   Richa   Laboratories   (P.)   Ltd.   [(1993)   78   Company Cases 283 Delhi.

8. .....The learned counsel for the respondent company relied on   the below mentioned decisions in support of his contention:

(1) The   decision  in   case   of   IBA   Health   (India)  Pvt.  

Ltd. v. Info - Drive Systems Sdn.Bhd. [(2010) 10 SCC 553] (2) The  decision  in  case  of   Pradeshiya   Industrial   &   Investment Corp. of U.P. v. North India Petro Chemicals   Ltd. [1994 (79) Company Cases 835] (3) The decision in case of Amalgamated Commercial   Traders P. Ltd. v. ACK Krishnaswami [1965 (35) Company  Cases 456] (4) The decision in case of Tata Iron and Steel Co. v.   Micro Forge (India) Ltd. [2001 (104) Company Cases 533] Page 7 of 16 O/OJMCA/54/2014 ORDER (5) The decision in case of Rishi Enterprises, in Re.   [1992 (73) Company Cases 271].

(6) The decision in case of Shadi Lal Ent. Ltd. v. Co­ operative Ltd. [2001(103) Company Cases 863].

(7) The decision in case of Juneja Chemical Ind. Pvt.   Ltd. v. Alam Tannery Pvt. Ltd. [2007 (140) Company Cases  833].

(8) The decision in case of ICICI Bank Ltd. v. Saurav   Chemicals Ltd. [2010 (153) Company Cases 429].

(9) The decision in case of Gautam Electric Motors v.   Firm Shantilal & Bros. [MANU/DE/0086/1969].

(10) The decision in case of Madhusudan Gordhandas   & Co. v. Madhu Woollen Ind. Pvt. Ltd. [1972(42) Company   Cases 125].

10. In   its   rejoinder   affidavit   dated   9th  June   2011,   the   petitioner company has also claimed that the respondent company has   already   availed   benefit   of   CENVAT   and   VAT   credits   to   the   tune   of   Rs.2,30,438/­ on the basis of the work carried out by the petitioner   company. It is claimed that by taking  CENVAT  and VAT credit, the   respondent   has   admitted   and   approved   the   said   transaction   and   admitted its liability to pay the amounts.

12. It   emerges   from   the   above   referred   record   that   the   petitioner has claimed that the work of erection and commissioning   was beyond the scope of its contract which was restricted to the work   of repairs and overhauling  of the cranes which included the task of   dismantling, identifying and removing the parts and assembling etc.   for  repairing  and  fabricating  and  overhauling  and  transporting  the   parts   and   assemblies   i.e.   the   12   operational   aspects   of   repairs,   overhauls, supply and transport of the equipments.

13. The  respondent  company  has resisted  the petition  on   the   ground   that   since   the   petition   involves   and   raises   disputed   Page 8 of 16 O/OJMCA/54/2014 ORDER question of facts the petition ought not be entertained as the issues of   facts involved in the matter would require regular trial.

13.1. ......The learned counsel for the petitioner relied on the   decision in the case of Hotline Teletubes And Components Ltd.(supra)   so as to claim that if the dispute is not bonafide or is an afterthought   then petition may not be rejected. .......

14.2 Thus,   the   Court   is   required   to   decide   whether   the   grounds of defence are substantial or not and they do not "consist of   some ingenious mask invented to deprive a creditor and is not a mere   wrangle".

15.2 The grounds of dispute should not, as observed by the   Apex  Court,  "consist  of some  ingenious  mask  invented  to deprive  a   creditor   of   a   just   and   honest  entitlement   and   must   not   be   a   mere   wrangle". 

16.2 In present  case so as to address  the said aspect  it is   necessary to recall certain relevant dates. It s noticed from the record   that:

1 24.11.2007 The   petitioner   submitted   its   quotation   to   the   respondent.
2 03.12.2007 The respondent issued Letter of Intent 3 26.02.2008   &  The petitioner raised three invoices in the sum of Rs.
27.02.2008 4 March,   August  The   petitioner   forwarded   letters/reminders   raising  &   October,  demand for payment of the invoices amount.

2009   &   Feb   &  April, 2010   5 04.05.2010 The   respondent   forwarded   its   first   reply   to   the   petitioner.

6 15.07.2010 The respondent issued statutory notice.

Page 9 of 16

O/OJMCA/54/2014 ORDER 16.3. Besides the above mentioned dates other two dates are   also   relevant   to   note   viz.   26.09.2009   and   20.10.2009.   On   26.09.2009   a   company   named   Hebankraft   submitted   its   revised   quotation to the respondent and on 20.10.2009 the respondent issued   work order in favour of the said company i.e. Hebankraft.

16.6. It   is   pertinent   to   note   that   until   the  said   period   i.e.   30.08.2009 any grievance with regard to the petitioner's performance   of   contract   work   does   not   appear   to   have   been   raised   by   the   respondent   company.   The   respondent   company   has   not   placed   any   material,  not  even  a single  letter,  making  any remark  or grievance   about   any   alleged   delay   in   executing   the   work   or   unsatisfactory   performance of work or of any nature whatsoever. 

17. The   overall   effect   of   conjoint   consideration   and   the   reading   of   the   aforesaid   aspects   lead   the   Court   to   believe   that   the   disputes   raised   by   the   respondent   company   have   been   raised   as   afterthought and that the disputes were not raised contemporaneously   but have been raised only subsequently and from conjoint reading of   all facts and circumstances of the present case, which are illustratively   mentioned above, it comes out that the grounds of defence raised by   the  respondent  are  afterthoughts  and   consist  of  and  amount  to,   as   expressed   by   the   Apex   Court,   "some   ingenious   mask   invented   to   deprive   a   creditor   (in   present   case   the   petitioner)   of   its   bonafide   claim."

17.1. The aforesaid aspect is also evident from the fact that   though the petitioner issued three invoices in month of February 2008,   until May 2010, the respondent company never raised any grievance   with   reference   to   the   said   grievance   and   never   objected   the   said   invoices until (the petitioner's third intimation - demand served after   Page 10 of 16 O/OJMCA/54/2014 ORDER the service of 3 invoices) 4 th May 2010 and it is only on 4 th May 2010   the petitioner  company  came out with the aforesaid  reply.  The fact   that the respondent has come out with an afterthought dispute is also   evident from the fact that the respondent has availed CENVAT & VAT   credit.

18. In this context it is relevant to recall at this stage the   observations by the Apex Court in para 20 of the decision in the case   between   IBA   Health   (India)   Private   Limited   (2010   [10]   SCC   553)   extracted hereinabove in para 14 and 14.1.

21.2 Therefore the submission and presentation of a suit in   the civil Court by the petitioner for recovery of debt would not act as a   bar against present petition.

21.3. Likewise, the arbitration clause in the LOI also would   not act as a restriction  or obstacle or prohibition  in maintaining  a   winding up petition. 

21.4. Accordingly,   the   respondent   company's   contention   resisting the petition on the ground that the Letter of Intent / contract   contains   "Arbitration   Clause"   and   that   the   petitioner   has   already   instituted a civil suit for enforcing recovery of the dues, would not help   the respondent in opposing the petition on the said ground.

21.5 In this context reference needs to be made to a recent   decision   by   the   Apex   Court   in   the   case  between   Boozallen   and   Hamilton  Inc. v. SBI Home Finance  Limited  & Ors. [(2011)  5 SCC   532] the Apex Court has observed that:­ "........Adjudication of certain categories of proceedings are   reserved by the legislature exclusively for public fora as a   Page 11 of 16 O/OJMCA/54/2014 ORDER matter of public policy. Certain other  categories of cases   though  not   expressly   reserved   for  adjudication  by   public   fora (Courts and Tribunals), may by necessary implication  stand excluded from the purview of private fora......"  

21.9. In present case, the foregoing discussion demonstrates   that   the   petitioner   has   made   out   case   that   the   eventuality   contemplated under Section 433(e) and/or under Section 433(f) read   with Section 434(1)(a) exists and the dispute sought to be raised by   the respondent is an afterthought and lacks bonafides. In this view of   the   matter   this   Court   is   not   convinced   and   inclined   to   reject   and   dismiss   the   petition   at   threshold   on   the   ground   that   civil   remedy   and/or   remedy   of   arbitration   is   available   or   that   the   claim   is   disputed.  

23. In present case the Court has noticed that the dispute   sought to be raised by the respondent is in nature of afterthought and   lack bonafides and that therefore in the facts of present case the said   objection and contention cannot be sustained.

26. On this count is is relevant to note that this Court   has   in   the   case   between   Ficom   Organics   Ltd.   v.   Laffans   Petrochemicals   Ltd.   [(2000)   99   Company   Cases   471]   after   reaching   the   conclusion   that   the   dispute   raised   by   the   respondent   company   against   the   petitioner's   claim   was   not   bonafide, granted time to the  respondent company to  pay the   petitioner the claim amount. 

27. On   over   all   consideration   of   the   aforesaid   and   other   factual   aspects   recapitulated   hereinabove   earlier,   this   Court has found, and the Court is satisfied, that the dispute or   defence   raised   by   the   petitioner   is   an   afterthought   and   the   Page 12 of 16 O/OJMCA/54/2014 ORDER afterthought   dispute   or   defence   of   the   respondent   company   is   raised   with   a   view   to   resisting   the   petition   and   delaying   the   liability to make the payment of due and payable amount.  

28. As   mentioned   above,   when   the   court   reaches   a   conclusion that the respondent's defence lacks bonafides or that   it   consists   of   some   ingenious   mask   invented   to   frustrate   the   claim then the court may not frustrate the petition by throwing   out   the   petition   and   denying   the   order   of   admission   of   the   petition   on   the   grounds   raising   objections   against   maintainability of the petition.

30. Therefore, the court is inclined to accept and admit this   petition.   However,   the   Court   considers   it   appropriate   that   before   making   order   admitting   the   petition   and   permitting   publication   of   advertisement  it would  be in fitness  of things  and  also appropriate   (having   regard   to   the   other   aspects   urged   by   the   respondent   e.g.   pending  execution  of contracts  and  such  other  details)   to  grant   an   opportunity to the respondent company to deposit the invoice amounts   in this Court. Hence, below mentioned order is passed.

31. The  respondent  company   is  granted  time  of  4  weeks   from the receipt / service of a copy of this order or until 25 th  April   2012 whichever is earlier to deposit the invoice amount covered by the   3 invoices raised by the petitioner. 

(ii) The aforesaid observations, clearly indicate that the entire  issue with regard to existence of dispute so as to debar the petitioner  from   maintaining   main   petition,   is   now   open   to   be   raised   again   and  again, as the challenge to the order dated 9 th March, 2012 has resulted  into   disposal   of   the   O.J.   Appeal   no.26   of   2012   as   having   become  infructuous.   The respondent company preferred O.J. Appeal no.26 of  Page 13 of 16 O/OJMCA/54/2014 ORDER 2012 and in the memo of the O.J.Appeal, the following averments were  made, which are required to be taken into consideration.

"10. It   is   submitted   that   the   said   e­mails   are   admittedly   exchanged between the above parties during the aforesaid period.  It is   submitted that in the first e­mail dated 3.5.2008 itself, the appellant   had raised serious disputes and issues with regard to the conduct of   the respondent and have brought the deficiencies in the work to the   notice of the respondent.  However, the said emails could not be traced   during filing of the Affidavits in the proceedings of Company Petition   No.170   of   2010   in   spite   of   due   and   diligent   efforts   made   by   the   company, since the emails were in the account which was password   protected account.  It is only now that the company has been able to   trace  out those  emails.    Hence,  in view  of the said  eventuality,  the   appellant   has   filed   the   Review   Application   before   the   Ld.Company   Judge.  However, since by way of the impugned order, the appellant is   required to deposit the amount, as directed, on or before 25.4.2012,   and   the   present   appeal   is   preferred.     A   copy   of   the   said   review   application together with the annexures thereto is annexed hereto and   marked as Annexure­II."

Thus,   the   correspondence,   which   are   now   sought   to   be  pressed into service were available before the O.J. Appeal Bench and the  grounds were also pressed into service, now when those grounds though  pressed into service at one point of time were not relied upon for seeking  further   orders   and   the   company   respondent   chose   to   invite   an   order  after   depositing   the   amount,   a   question   arises   as   to   whether   is   the  respondent company now entitled to re­agitate the same issue time and  again.  The answer is emphatic "'No".  As the permission to the company  to re­agitate those issues would be barred by constructive  res judicata.  This   Court   cannot   permit   the   respondent   company   to   re­agitate   the  Page 14 of 16 O/OJMCA/54/2014 ORDER issue, which company had taken­up before the O.J. Appeal Bench and  when it did not chose to invite any order there, and when it did not seek  appropriate liberty to re­agitate them or an observation of the Court and  did not seek any liberty to press into service those grounds, then the  same  cannot  be  resurrected  for  resisting  the  prayer  for  disbursement.  Even   otherwise   also,   assuming   for   the   sake   of   examining   without  conceding   that   the   O.J.   Appellate   Bench,   did   permit   the   opponent­ original petitioner to seek relief of disbursement from the learned single  Judge   and   in   that   way,   the   Appellate   Bench   did   not   opine   upon   the  correspondence  clearly indicate  that  there  was  a  team  of  ten  persons  sent   by   the   present   petitioner   for   helping   the  erection  work   and   on  account of lack of cooperation from the respondent company, the team  had   to   go   back   to   the   petitioner.     These   are   the   correspondences  exchanged,   which   persuade   this   Court   to   hold   that   there   exists   no  ground   for   taking   different   view   from   the   one   taken   by   the   learned  single   Judge   and   expressed   it   in   the   order   dated   9 th  March,   2012.  Therefore, on this ground also, the Court is of the considered view that  the company failed in  establishing that the disbursement is not to be  made.

The   Company   did   not   have   any   entitlement   to   seek   re­ agitation   on   the   basis   of   the   e­mail   exchanges   and   correspondence  forming part from page no.158 to 167, as the review application being  O.J. M.C.A. No.74 of 2012 in Company Petition No.170 of 2010 seeking  review of the order dated 9th March, 2012 came to be withdrawn on 22nd  June, 2012 and the following order came to be passed.

"1. Heard Mr.Chudgar, learned advocate for the applicant.
2. Mr.Chudgar,   learned   advocate   for   the   applicant   has   submitted   that   he   has   received   instructions   from   his   client   to   withdraw this application.
3. The   permission   as   requested   for   is   granted.     The   Page 15 of 16 O/OJMCA/54/2014 ORDER application is disposed of as withdrawn.
Thus, from  any  angle,  it can  be  said  that the   respondent  company   did   not   have   any   entitlement   to   re­agitate   the   issue,   which  could said to be now any longer permitted to be agitated.      
(iii) The   Court   is   also   not   impressed   by   the   submission  canvassed   on   behalf   of   the   respondent   company   that   there   exists   a  bonafide dispute, as now, this Court at this stage, cannot go beyond the  observations recorded by the learned single Judge in his order dated 9 th  March, 2012 challenge where to has failed or not pressed, having raised  all the grounds which have been raised before this Court.  Moreover, the  detailed order dated 9th March, 2012 contain reasons, which this Court is  of the view cannot be said to have been whittled down in any manner on  account   of   the   correspondence   placed   on   record,   which   was   also  conforming part of the O.J. Appeal proceedings.  

11. In the result, the application is allowed.  Office is directed to  disburse   the   amount   deposited   under   order   of   this   Court   dated   9 th  March, 2012 to the applicant on his furnishing appropriate undertaking  before this Court, that in the eventuality and as per the final order in the  main  appeal, if   he  is called upon  to  refund the  said  amount,  he  will  refund it with appropriate interest that may determine at the relevant  time and appropriate security for refunding the same.              

(S.R.BRAHMBHATT, J.)  Rathod...

Page 16 of 16