Section 12 in Tamil Nadu Electricity Regulatory Commission - Tamil Nadu Electricity Distribution Standards of Performance Regulations, 2004
12. Interruptions and restoration of supply.
| Interruption Due to | Power Restoration Time | |||
| Corporation | Urban Municipalities | Rural | Hill Area | |
| HT Supply failure | 1 hour | 3 hours | 6 hours | 12 hours |
| Fault in Transformer | 2 hours | 4 hours | 6 hours | 12 hours |
| Structure or LT Line or Pillar Box | ||||
| Fault of Distribution Transformer | 24 hours | 48 hours | 48 hours | 48 hours |
| Individual Service Connection fault | 3 hours | 9 hours | 12 hours | 24 hours |