Union of India - Section

Section 28 in Central Electricity Regulatory Commission (Terms and Conditions of Tariff) Regulations, 2019

28. Special Allowance for Coal-based/Lignite fired Thermal Generating station.

(1)In case of coal-based/lignite fired thermal generating stations, the generating company, instead of availing renovation and modernization (R&M) may opt to avail a 'special allowance' in accordance with the norms specified in this Regulation, as compensation for meeting the requirement of expenses including renovation and modernisation beyond the useful life of the generating station or a unit thereof and in such an event, upward revision of the capital cost shall not be allowed and the applicable operational norms shall not be relaxed but the Special Allowance shall be included in the annual fixed cost:Provided that such option shall not be available for a generating station or unit thereof for which renovation and modernization has been undertaken and the expenditure has been admitted by the Commission before commencement of these regulations, or for a generating station or unit which is in a depleted condition or operating under relaxed operational and performance norms;Provided further that special allowance shall also be available for a generating station which has availed the Special Allowance during the tariff period 2009-14 or 2014-19 as applicable from the date of completion of the useful life.
(2)The Special Allowance admissible to a generating station shall be @ Rs 9.5 lakh per MW per year for the tariff period 2019-24.
(3)In the event of a generating station availing Special Allowance, the expenditure incurred upon or utilized from Special Allowance shall be maintained separately by the generating station and details of same shall be made available to the Commission as and when directed.
(4)The Special Allowance allowed under this Regulation shall be transferred to a separate fund for utilization towards Renovation &Modernisation activities, for which detailed methodology shall be issued separately.