State of Himachal Pradesh - Subsection

Section 5(7) in Himachal Pradesh Electricity Regulatory Commission (Promotion of Generation from the Renewable Energy Sources and Terms and Conditions for Tariff Determination) Regulations, 2017

(7)Notwithstanding anything contained in the preceding sub-regulation (6), where there are right of way problems or there are space limitations at the sub-station of the concerned licensee, the licensee may require the renewable energy generators to enter into suitable arrangement for joint project line(s) for two or more projects and inject power into the grid through the joint evacuation system.