28. Capital Cost.

(1)The normative capital cost for small hydro projects during first year of Control Period (FY 2013-14) shall be as follows:
Project Size Capital Cost (Rs. in Lac/ MW)
Below 5 MW 770
5 MW to 25 MW 700
(2)The capital cost for subsequent years shall be determined on the basis of indexation formula as outlined under Regulation 29.