Union of India - Subsection

Section 10(2) in Central Electricity Regulatory Commission (Grant of Connectivity, Long-term Access and Medium-term Open Access in inter-State Transmission and related matters) Regulations, 2009

(2)Where necessary infrastructure required for energy metering and time-block-wise accounting already exists and required transmission capacity in the State network is available, the State Load Despatch Centre shall convey its concurrence to the applicant within ten working days of receipt of the application.