Legal Document View

Unlock Advanced Research with PRISMAI

- Know your Kanoon - Doc Gen Hub - Counter Argument - Case Predict AI - Talk with IK Doc - ...
Upgrade to Premium
[Cites 0, Cited by 0] [Entire Act]

State of Himachal Pradesh - Section

Section 39 in Himachal Pradesh Electricity Regulatory Commission (Terms and Conditions for Determination of Hydro Generation Tariff) Regulations, 2011

39. Disposal of Application.

(1)The Commission shall process the filings made by the generating company in accordance with these regulations and the Conduct of Business Regulations.
(2)Based on the generating company's filings, objections/ suggestions from public and other stakeholders, the Commission may, within 120 days of the receipt of the application, complete in all respects, and after considering all suggestions and objections from public and other stakeholders,-
(a)issue a tariff order with such modifications and/or such conditions, as may be deemed just and appropriate containing, inter alia targets for controllable items and the generation tariffs for each year of the control period; or
(b)reject the application for reasons to be recorded in writing if such application is not in accordance with the provisions of the Act and the rules and regulations made thereunder or the provisions of any other law for the time being in force.