Section 5(1)(ii) in Central Electricity Regulatory Commission (Deviation Settlement Mechanism and Related Matters) Regulations, 2014
(ii)[ the charges for the deviation for the generating stations other than those covered under proviso (i) of this Regulation, irrespective of the fuel source, when actual injection is higher or lower than the scheduled generation, shall not exceed the Cap Rate of 303.04 Paise/kWh.] [Substituted by Notification No. L-1/132/2013-CERC, dated 20.11.2018 (w.e.f. 6.1.2014).]