Section 46(6) in The Punjab State Electricity Regulatory Commission (Conduct of Business) Regulations, 2005

(6)
(a)The Distribution Licensee shall satisfy the Commission that the electricity procured under long term power purchase otherwise than through a competitive bidding process or any short term power purchase is economical in the prevalent circumstances and that the Distribution Licensee has made prudent and best efforts to minimise the cost of purchase.
(b)The Commission may not permit any such long term purchase if the manner or method proposed for such procurement of electricity is not conducive to the objective of least cost purchase or for any other reason the purchase is not economical or efficient.