| Category | Time Schedule |
| (a) Involving no Extension or Improvement work | Preferably within a week but not exceeding 30 days |
| (b) Involving Extension and improvement withoutDistribution Transformers | 60 days |
| (c) Involving Extension and Improvement withDistribution Transformers | 90 days |
| Category Time | Schedule for HT/EHT- | |
| HT | EHT | |
| (a) Involving Extension & Improvement | 60 days | 150 days |
| (b) Involving the enhancement of PowerTransformer/Addition of Power Transformer | 120 days | 180 days |
| (c) Involving the Commissioning of newsubstation | 180 days | 270 days |