Section 31 in Tamil Nadu Electricity Regulatory Commission Tamil Nadu Electricity Distribution Code

31. Inspections, testing and effecting supply.

(1)After completion of the wiring, notice must be sent to the Engineer by the intending consumer ( upon printed test report form obtainable free of cost from the offices of the Licensee) that the installation has been completed and tested and that the same is complete and ready for inspection and test by the Engineer. Notice of the Engineer's intention to inspect and test the installation will be sent to the intending consumer who must be present or his/her competent representative at the time fixed to give information that may be necessary concerning the installation. [Upon executing / signing of the test report, a copy of the test report shall be given to the consumer] [Inserted by Commission's Notification No TNERC/DC/8-8 dated 8.2.2008 (w.e.f. 27.2.2008).].
(2)The intending consumer shall avail himself of the supply within three months in case of HT and one month in case of LT from the date of issue of notice in writing, informing him that supply is available.
(3)[ If the intending consumer fails to avail the supply within the above period, a further three months notice in case of HT and one month notice in case of LT will be sent to the intending consumer to avail the supply. If he does not avail himself the supply during this notice period, the application will be treated as lapsed and cancelled in the case of Low Tension supply, and the application shall be treated as cancelled, terminating the agreement, in the case of High Tension supply. The service connection charges and the Security Deposit/development charges, etc. except Meter Caution Deposit will be forfeited. In case the intending consumer could not avail the supply under force majeure conditions, the Security Deposit and meter caution deposit shall be refunded to the intending consumer.] [Substituted by Notification No. TNERC/DC/8-19, dated 01-07-2014.]
(4)However, Licensees of the Distribution are delegated with powers to condone the delay on specific request from them if received before expiry of second notice period and to accord approval to effect supply any day after the date of expiry of second notice of availability of supply without forfeiture of development and other charges and cancellation of application subject to his/her consent to pay monthly minimum charges up to the date of availing supply.
(5)If the intending consumer avails supply during the notice period of availability of supply he shall pay the monthly minimum charges at the notified tariff rate for the period from the date of issue of first notice of supply availability till the date of availing supply.
(6)Requisition for supply or additional supply of electricity should be made in the prescribed form obtainable from the local office of the Licensee sufficiently in advance of the date of requirement of supply. Such Forms can also be made available in downloadable mode in the Licensee's website or allowed to be printed by others and made available in open market. The requisition should be made by the owner, or occupier, of the premises for which supply is required, and should indicate his / her full name and address. Any assistance or information required in filling up the form has to be given to the intending consumer at the local offices of the Licensee.