Section 0(1) in The West Bengal Electricity Regulatory Commission (Terms and Conditions of Tariff) Regulations, 2011

1.1- The generating company or licensee shall file a perspective plan for approval of the Commission along with tariff application. The perspective plan shall be for a period of 5 years and shall be submitted with each tariff application and application for annual performance review.