State of Jammu-Kashmir - Section

Section 26 in Jammu and Kashmir State Electricity Regulatory Commission (Terms and Conditions for Tariff determination from Renewable Energy Sources) Regulations, 2013

26. Capacity Utilisation Factor (CUF).

(1)CUF norms for this control period shall be as follows:
Annual Mean Wind Power Density (W/m2) CUF
Upto 200 20%
201-250 22%
251-300 25%
301-400 30%
>400 32%
(2)The annual mean wind power density specified in sub-regulation (1) above shall be measured at 80 meter hub-height.
(3)For the purpose of classification of wind energy project into particular wind zone class, as per MNRE guidelines for wind measurement, wind mast either put-up by C-WET or a private developer and validated by C-WET would be normally extended 10 km from the mast-point to all directions for uniform terrain and limited to appropriate distant in complex terrain with regard to complexity of the site. Based on such validation by C-WET, State Nodal Agency should certify zoning of the proposed wind farm complex.